Apex is running two programs, SAP S/4HANA and the Line 3 upgrade, and full production resumption is dated 24 Feb 2027. Open purchase order cleansing is 21 working days behind baseline and has used up all the float on the path to go-live on 3 Feb 2027.
- 1Decision needed by 4 Sep 2026: how to close the 2.0 FTE IT gap between SAP integration testing and SCADA integration, which overlap from 7 Sep 2026.
- 2Cleanse open purchase orders (APX.3.2.5) is 2% complete and forecast to finish 2 Oct 2026, 21 working days after baseline, because 14,000 purchase orders need manual cleansing. It sits on the critical path with 0 days of float.
- 3Nothing is late today, but integration testing and the user acceptance window behind it have no buffer. Go-live (3 Feb 2027) and production resumption (24 Feb 2027) move day for day with any further slip.
Schedule outlook
Production resumption is 24 Feb 2027, the same as baseline. The 21 working days lost on data migration have used all of its float, so any further slip on the migration, integration testing or user acceptance path moves go-live (3 Feb 2027) by the same amount.
Critical pathZero or negative float from Cleanse open purchase orders to Full production resumption
The longest path in the export runs from open purchase order cleansing to production resumption through 21 activities. Every stage has 0 days of float.
Delivery roadmapAs at 27 Apr 2026
The SAP program (A) and the Line 3 upgrade (B) meet at SAP go-live and production resumption. The shared IT team is what links A.4 and B.3 in September to November.
Decisions required
SAP integration testing and SCADA integration need 6.0 FTE from a team of 4.0
Requested: Decide how to cover the 2.0 FTE gap in the IT team in September: add capacity, or move the SCADA IT tasks (APX.9.1.3, APX.9.2.3) later. Those tasks have 36 and 26 working days of float, while integration testing (APX.4.2) has none.
Recommended: Protect integration testing and re-date the SCADA IT tasks within their float, rather than let the shared team slow the critical path.
If not decided: If integration testing slows, its zero float passes straight to user acceptance, go-live (3 Feb 2027) and production resumption (24 Feb 2027).
What could change the outcome
The top risks that could move this outlook. A preview of the full Risk Analysis tab.
Open purchase order cleansing is 21 working days behind baseline because 14,000 purchase orders need manual cleansing. Go-live is protected only because the buffer has been used.
Integration testing and SCADA integration need 6.0 FTE from a team of 4.0 FTE. Integration testing has no float; SCADA has 26 or more working days.
User acceptance testing starts 30 Oct 2026, straight after integration testing, with no float before go-live.
Workstream health
| Workstream | Complete | Position | Status |
|---|---|---|---|
| Program Management | 50% | On plan | On plan |
| Finance Systems | 41% | On plan | On plan |
| Supply Chain Systems | 41% | On plan | On plan |
| Production Systems | 46% | On plan | On plan |
| Quality and Compliance | 29% | On plan | On plan |
| IT Infrastructure | 45% | On plan | On plan |
| Integration | 28% | On plan | On plan |
| Data Migration | 16% | 1 delayed | Watch |
| Testing | 10% | On plan | On plan |
| Change and Training | 12% | On plan | On plan |
| Procurement and Shutdown | 91% | On plan | On plan |
| Mechanical Installation | 15% | On plan | On plan |
| Electrical and Automation | 0% | Not started yet | Not started |
- All 182 activities have an owner, and dependency links run through the whole project, so float and the critical path are calculated from schedule logic. No task is dated before the work it depends on.
- The export holds no resource assignments or capacity. The 6.0 FTE demand against 4.0 FTE is taken from source comments and cannot be checked against a resource plan.
Blueprint and equipment procurement are complete. Build and configuration is 33% complete and data migration 10%, and migration is where the buffer has gone: it is 21 working days behind baseline with no float.
- 1Blueprint (A.1) and equipment procurement and shutdown planning (B.1) are complete.
- 2Data migration (A.3) is 10% complete and 21 working days behind baseline on open purchase order cleansing.
- 3Integration testing and SCADA integration both need the IT team from 7 Sep 2026, which is 2.0 FTE short.
PhasesSelect a phase to expand
ScheduleAs at 27 Apr 2026
| WBS | Task | % | Start | Finish | Forecast | Owner | Status | Comments | |
|---|---|---|---|---|---|---|---|---|---|
| APX | Apex Manufacturing: SAP S/4HANA and Line 3 Upgrade | 31% | 05 Jan 2026 | 24 Feb 2027 | Program Director | In progress | |||
| APX.1 | A.1 Blueprint and design | 100% | 05 Jan 2026 | 31 Mar 2026 | 31 Mar 2026 ✓ | SAP Program Director | Done | ||
| APX.1.1 | Mobilisation and governance | 100% | 05 Jan 2026 | 23 Jan 2026 | 23 Jan 2026 ✓ | SAP Program Director | Done | ||
| APX.1.1.1 | Confirm program scope and business case | 100% | 05 Jan 2026 | 09 Jan 2026 | 09 Jan 2026 ✓ | SAP Program Director | Done | ||
| APX.1.1.2 | Establish program governance and steering committee | 100% | 12 Jan 2026 | 16 Jan 2026 | 16 Jan 2026 ✓ | SAP Program Director | Done | ||
| APX.1.1.3 | Mobilise implementation partner team | 100% | 19 Jan 2026 | 23 Jan 2026 | 23 Jan 2026 ✓ | Implementation Partner Lead | Done | ||
| APX.1.1.4 | Milestone: Program mobilised | — | 23 Jan 2026 | 23 Jan 2026 | 23 Jan 2026 ✓ | SAP Program Director | Done | ||
| APX.1.2 | Business blueprint workshops | 100% | 27 Jan 2026 | 30 Mar 2026 | 30 Mar 2026 ✓ | Business Process Lead | Done | ||
| APX.1.2.1 | Finance and controlling blueprint workshops | 100% | 27 Jan 2026 | 23 Feb 2026 | 23 Feb 2026 ✓ | Finance Lead | Done | ||
| APX.1.2.2 | Procurement and inventory blueprint workshops | 100% | 27 Jan 2026 | 23 Feb 2026 | 23 Feb 2026 ✓ | Supply Chain Lead | Done | ||
| APX.1.2.3 | Production planning blueprint workshops | 100% | 27 Jan 2026 | 25 Feb 2026 | 25 Feb 2026 ✓ | Production Systems Lead | Done | ||
| APX.1.2.4 | Sales and distribution blueprint workshops | 100% | 27 Jan 2026 | 13 Feb 2026 | 13 Feb 2026 ✓ | Supply Chain Lead | Done | ||
| APX.1.2.5 | Plant maintenance blueprint workshops | 100% | 27 Jan 2026 | 11 Feb 2026 | 11 Feb 2026 ✓ | Maintenance Manager | Done | ||
| APX.1.2.6 | Quality management blueprint workshops | 100% | 27 Jan 2026 | 11 Feb 2026 | 11 Feb 2026 ✓ | Quality Manager | Done | ||
| APX.1.2.7 | Warehouse and logistics blueprint workshops | 100% | 27 Jan 2026 | 11 Feb 2026 | 11 Feb 2026 ✓ | Warehouse Manager | Done | ||
| APX.1.2.8 | Fit-gap analysis | 100% | 26 Feb 2026 | 11 Mar 2026 | 11 Mar 2026 ✓ | Business Process Lead | Done | ||
| APX.1.2.9 | Draft business blueprint documents | 100% | 12 Mar 2026 | 25 Mar 2026 | 25 Mar 2026 ✓ | Business Analyst | Done | ||
| APX.1.2.10 | Blueprint review with process owners | 100% | 26 Mar 2026 | 30 Mar 2026 | 30 Mar 2026 ✓ | Business Process Lead | Done | ||
| APX.1.2.11 | Milestone: Business blueprint signed off | — | 30 Mar 2026 | 30 Mar 2026 | 30 Mar 2026 ✓ | SAP Program Director | Done | ||
| APX.1.3 | Technical design and strategy | 100% | 27 Jan 2026 | 31 Mar 2026 | 31 Mar 2026 ✓ | Solution Architect | Done | ||
| APX.1.3.1 | Technical architecture and landscape design | 100% | 27 Jan 2026 | 16 Feb 2026 | 16 Feb 2026 ✓ | Solution Architect | Done | ||
| APX.1.3.2 | Security and authorisation concept | 100% | 17 Feb 2026 | 02 Mar 2026 | 02 Mar 2026 ✓ | Security Architect | Done | ||
| APX.1.3.3 | Integration architecture design | 100% | 17 Feb 2026 | 04 Mar 2026 | 04 Mar 2026 ✓ | Integration Lead | Done | ||
| APX.1.3.4 | Data migration strategy and approach | 100% | 27 Jan 2026 | 09 Feb 2026 | 09 Feb 2026 ✓ | Data Migration Lead | Done | ||
| APX.1.3.5 | Test strategy and environment plan | 100% | 27 Jan 2026 | 05 Feb 2026 | 05 Feb 2026 ✓ | Test Manager | Done | ||
| APX.1.3.6 | Change management and training approach | 100% | 27 Jan 2026 | 05 Feb 2026 | 05 Feb 2026 ✓ | Change Manager | Done | ||
| APX.1.3.7 | Inventory current systems and interfaces | 100% | 27 Jan 2026 | 09 Feb 2026 | 09 Feb 2026 ✓ | Solution Architect | Done | ||
| APX.1.3.8 | Plant network and operational technology security assessment | 100% | 27 Jan 2026 | 09 Feb 2026 | 09 Feb 2026 ✓ | Security Architect | Done | ||
| APX.1.3.9 | Master data governance design | 100% | 27 Jan 2026 | 05 Feb 2026 | 05 Feb 2026 ✓ | Data Migration Lead | Done | ||
| APX.1.3.10 | Define benefits tracking and program KPIs | 100% | 27 Jan 2026 | 02 Feb 2026 | 02 Feb 2026 ✓ | SAP Program Director | Done | ||
| APX.1.3.11 | Approve build plan and cut-over principles | 100% | 31 Mar 2026 | 31 Mar 2026 | 31 Mar 2026 ✓ | SAP Program Director | Done | ||
| APX.2 | A.2 Build and configuration | 33% | 01 Apr 2026 | 31 Aug 2026 | Solution Architect | In progress | |||
| APX.2.1 | Technical environments | 38% | 01 Apr 2026 | 28 May 2026 | IT Infrastructure Manager | In progress | |||
| APX.2.1.1 | Provision development and quality systems | 100% | 01 Apr 2026 | 16 Apr 2026 | 16 Apr 2026 ✓ | IT Infrastructure Manager | Done | ||
| APX.2.1.2 | Install SAP Fiori front end and gateway | 60% | 17 Apr 2026 | 30 Apr 2026 | Basis Lead | In progress | |||
| APX.2.1.3 | Configure user roles and authorisations | 0% | 01 May 2026 | 28 May 2026 | Security Architect | Not started | |||
| APX.2.1.4 | Provision production and disaster recovery systems | 0% | 01 May 2026 | 28 May 2026 | IT Infrastructure Manager | Not started | |||
| APX.2.1.5 | Network and plant connectivity upgrade | 64% | 01 Apr 2026 | 07 May 2026 | Network Lead | In progress | |||
| APX.2.2 | Finance configuration | 43% | 01 Apr 2026 | 20 Jul 2026 | Finance Lead | In progress | |||
| APX.2.2.1 | Configure general ledger and chart of accounts | 100% | 01 Apr 2026 | 20 Apr 2026 | 20 Apr 2026 ✓ | Finance Lead | Done | ||
| APX.2.2.2 | Configure controlling and cost centres | 33% | 21 Apr 2026 | 06 May 2026 | Finance Lead | In progress | |||
| APX.2.2.3 | Configure accounts payable and receivable | 0% | 07 May 2026 | 28 May 2026 | Finance Lead | Not started | |||
| APX.2.2.4 | Configure asset accounting | 0% | 29 May 2026 | 10 Jun 2026 | Finance Lead | Not started | |||
| APX.2.2.5 | Configure financial close and reporting | 0% | 11 Jun 2026 | 02 Jul 2026 | Finance Lead | Not started | |||
| APX.2.2.6 | Finance unit testing | 0% | 03 Jul 2026 | 20 Jul 2026 | Finance Lead | Not started | |||
| APX.2.2.7 | Configure treasury and bank connectivity | 100% | 01 Apr 2026 | 23 Apr 2026 | 23 Apr 2026 ✓ | Finance Lead | Done | ||
| APX.2.2.8 | Configure intercompany and consolidation | 100% | 01 Apr 2026 | 23 Apr 2026 | 23 Apr 2026 ✓ | Finance Lead | Done | ||
| APX.2.3 | Supply chain configuration | 18% | 01 Apr 2026 | 06 Aug 2026 | Supply Chain Lead | In progress | |||
| APX.2.3.1 | Configure procurement and purchasing | 80% | 01 Apr 2026 | 30 Apr 2026 | Supply Chain Lead | In progress | |||
| APX.2.3.2 | Configure inventory management | 0% | 01 May 2026 | 21 May 2026 | Supply Chain Lead | Not started | |||
| APX.2.3.3 | Configure warehouse management | 0% | 22 May 2026 | 12 Jun 2026 | Warehouse Manager | Not started | |||
| APX.2.3.4 | Configure sales and distribution | 0% | 15 Jun 2026 | 03 Jul 2026 | Supply Chain Lead | Not started | |||
| APX.2.3.5 | Configure supplier and customer portals | 0% | 06 Jul 2026 | 21 Jul 2026 | Supply Chain Lead | Not started | |||
| APX.2.3.6 | Supply chain unit testing | 0% | 22 Jul 2026 | 06 Aug 2026 | Supply Chain Lead | Not started | |||
| APX.2.4 | Production configuration | 29% | 01 Apr 2026 | 07 Aug 2026 | Production Systems Lead | In progress | |||
| APX.2.4.1 | Configure bills of materials and routings | 80% | 01 Apr 2026 | 30 Apr 2026 | Production Systems Lead | In progress | |||
| APX.2.4.2 | Configure production planning and scheduling | 0% | 01 May 2026 | 28 May 2026 | Production Systems Lead | Not started | |||
| APX.2.4.3 | Configure shop floor execution | 0% | 29 May 2026 | 24 Jun 2026 | Production Systems Lead | Not started | |||
| APX.2.4.4 | Configure plant maintenance | 0% | 25 Jun 2026 | 10 Jul 2026 | Maintenance Manager | Not started | |||
| APX.2.4.5 | Configure quality management and inspection plans | 0% | 13 Jul 2026 | 24 Jul 2026 | Quality Manager | Not started | |||
| APX.2.4.6 | Production unit testing | 0% | 27 Jul 2026 | 07 Aug 2026 | Production Systems Lead | Not started | |||
| APX.2.4.7 | Configure demand and capacity planning | 80% | 01 Apr 2026 | 30 Apr 2026 | Production Systems Lead | In progress | |||
| APX.2.5 | Custom development | 38% | 01 Apr 2026 | 26 Jun 2026 | Development Lead | In progress | |||
| APX.2.5.1 | Develop custom reports | 64% | 01 Apr 2026 | 07 May 2026 | Development Lead | In progress | |||
| APX.2.5.2 | Develop interfaces to plant control systems | 46% | 01 Apr 2026 | 21 May 2026 | Integration Lead | In progress | |||
| APX.2.5.3 | Develop custom workflows and approvals | 0% | 08 May 2026 | 04 Jun 2026 | Development Lead | Not started | |||
| APX.2.5.4 | Code review and unit test of custom objects | 0% | 05 Jun 2026 | 26 Jun 2026 | Development Lead | Not started | |||
| APX.2.5.5 | Develop data migration load programs | 46% | 01 Apr 2026 | 21 May 2026 | Data Migration Lead | In progress | |||
| APX.2.5.6 | Develop custom forms and labels | 100% | 01 Apr 2026 | 23 Apr 2026 | 23 Apr 2026 ✓ | Development Lead | Done | ||
| APX.2.5.7 | Build analytics dashboards | 0% | 08 May 2026 | 04 Jun 2026 | Development Lead | Not started | |||
| APX.2.6 | Build completion | 0% | 10 Aug 2026 | 31 Aug 2026 | Solution Architect | Not started | |||
| APX.2.6.1 | Integrated configuration review | 0% | 10 Aug 2026 | 21 Aug 2026 | Solution Architect | Not started | |||
| APX.2.6.2 | Build and configuration quality gate | 0% | 24 Aug 2026 | 31 Aug 2026 | SAP Program Director | Not started | |||
| APX.2.6.3 | Milestone: Build and configuration complete | — | 31 Aug 2026 | 31 Aug 2026 | SAP Program Director | Not started | |||
| APX.3 | A.3 Data migration | 10% | 01 Apr 2026 | 30 Sep 2026 | 29 Oct 2026 | Data Migration Lead | In progress | ||
| APX.3.1 | Migration planning | 100% | 01 Apr 2026 | 23 Apr 2026 | 23 Apr 2026 ✓ | Data Migration Lead | Done | ||
| APX.3.1.1 | Define migration objects and scope | 100% | 01 Apr 2026 | 09 Apr 2026 | 09 Apr 2026 ✓ | Data Migration Lead | Done | ||
| APX.3.1.2 | Data quality baseline assessment | 100% | 10 Apr 2026 | 17 Apr 2026 | 17 Apr 2026 ✓ | Data Quality Analyst | Done | The assessment found 14,000 open purchase orders that need manual cleansing. | |
| APX.3.1.3 | Assign data owners and cleansing responsibilities | 100% | 20 Apr 2026 | 22 Apr 2026 | 22 Apr 2026 ✓ | Data Migration Lead | Done | ||
| APX.3.1.4 | Select migration tooling and reconciliation approach | 100% | 10 Apr 2026 | 23 Apr 2026 | 23 Apr 2026 ✓ | Data Migration Lead | Done | ||
| APX.3.2 | Data cleansing | 5% | 23 Apr 2026 | 03 Sep 2026 | 02 Oct 2026 | Data Quality Analyst | In progress | ||
| APX.3.2.1 | Cleanse customer master data | 8% | 23 Apr 2026 | 27 May 2026 | Data Quality Analyst | In progress | |||
| APX.3.2.2 | Cleanse vendor master data | 8% | 23 Apr 2026 | 27 May 2026 | Data Quality Analyst | In progress | |||
| APX.3.2.3 | Cleanse material master data | 5% | 23 Apr 2026 | 18 Jun 2026 | Data Quality Analyst | In progress | |||
| APX.3.2.4 | Cleanse bills of materials and routings | 7% | 23 Apr 2026 | 03 Jun 2026 | Production Systems Lead | In progress | |||
| APX.3.2.5 | Cleanse open purchase orders | 2% | 23 Apr 2026 | 03 Sep 2026 | 02 Oct 2026 | Data Quality Analyst | Delayed | Manual cleansing of 14,000 open purchase orders is forecast to finish 21 working days after baseline. | |
| APX.3.2.6 | Cleanse employee and cost centre data | 20% | 23 Apr 2026 | 06 May 2026 | Data Quality Analyst | In progress | |||
| APX.3.2.7 | Cleanse open sales orders and contracts | 10% | 23 Apr 2026 | 20 May 2026 | Data Quality Analyst | In progress | |||
| APX.3.2.8 | Data owner sign-off of cleansed master data | 0% | 19 Jun 2026 | 25 Jun 2026 | Data Migration Lead | Not started | |||
| APX.3.3 | Migration build | 3% | 24 Apr 2026 | 10 Jul 2026 | Data Migration Lead | In progress | |||
| APX.3.3.1 | Build extraction and transformation rules | 3% | 24 Apr 2026 | 04 Jun 2026 | Data Migration Lead | In progress | |||
| APX.3.3.2 | Build reconciliation reports | 0% | 05 Jun 2026 | 26 Jun 2026 | Data Migration Lead | Not started | |||
| APX.3.3.3 | Migration tooling unit test | 0% | 29 Jun 2026 | 10 Jul 2026 | Data Migration Lead | Not started | |||
| APX.3.3.4 | Reconcile historical balances for migration | 7% | 24 Apr 2026 | 14 May 2026 | Finance Lead | In progress | |||
| APX.3.4 | Mock loads | 0% | 10 Aug 2026 | 30 Sep 2026 | 29 Oct 2026 | Data Migration Lead | Not started | ||
| APX.3.4.1 | Mock load 1: master data | 0% | 10 Aug 2026 | 21 Aug 2026 | Data Migration Lead | Not started | |||
| APX.3.4.2 | Mock load 1 reconciliation and defect fixing | 0% | 24 Aug 2026 | 04 Sep 2026 | Data Migration Lead | Not started | |||
| APX.3.4.3 | Mock load 2: master and transactional data | 0% | 06 Oct 2026 | 18 Sep 2026 | 19 Oct 2026 | Data Migration Lead | Not started | ||
| APX.3.4.4 | Mock load 2 reconciliation and defect fixing | 0% | 20 Oct 2026 | 30 Sep 2026 | 29 Oct 2026 | Data Migration Lead | Not started | ||
| APX.3.4.5 | Milestone: Mock load 2 signed off by data owners | — | 29 Oct 2026 | 30 Sep 2026 | 29 Oct 2026 | Data Migration Lead | Not started | ||
| APX.4 | A.4 Integration testing | 0% | 01 Sep 2026 | 29 Oct 2026 | Test Manager | Not started | |||
| APX.4.1 | Test preparation | 0% | 01 Sep 2026 | 04 Sep 2026 | Test Manager | Not started | |||
| APX.4.1.1 | Prepare integration test environment and data | 0% | 01 Sep 2026 | 04 Sep 2026 | Test Manager | Not started | |||
| APX.4.1.2 | Finalise integration test scenarios and scripts | 0% | 01 Sep 2026 | 04 Sep 2026 | Test Manager | Not started | |||
| APX.4.2 | SAP integration testing | 0% | 07 Sep 2026 | 26 Oct 2026 | Integration Lead | Not started | |||
| APX.4.2.1 | Interface testing: finance and banking | 0% | 07 Sep 2026 | 14 Sep 2026 | Integration Lead | Not started | IT integration team demand is 6.0 FTE across this window against 4.0 FTE available. Decision outstanding. | ||
| APX.4.2.2 | Interface testing: supplier and customer portals | 0% | 07 Sep 2026 | 14 Sep 2026 | Integration Lead | Not started | |||
| APX.4.2.3 | Interface testing: plant control and shop floor systems | 0% | 15 Sep 2026 | 28 Sep 2026 | Integration Lead | Not started | IT integration team demand is 6.0 FTE across this window against 4.0 FTE available. Decision outstanding. | ||
| APX.4.2.4 | End-to-end cycle 1: order to cash | 0% | 15 Sep 2026 | 28 Sep 2026 | Test Manager | Not started | |||
| APX.4.2.5 | End-to-end cycle 1: procure to pay | 0% | 15 Sep 2026 | 28 Sep 2026 | Test Manager | Not started | |||
| APX.4.2.6 | End-to-end cycle 1: plan to produce | 0% | 29 Sep 2026 | 14 Oct 2026 | Test Manager | Not started | |||
| APX.4.2.7 | Integration defect fixing and retest | 0% | 15 Oct 2026 | 26 Oct 2026 | Integration Lead | Not started | |||
| APX.4.3 | Non-functional testing | 0% | 07 Sep 2026 | 29 Oct 2026 | Test Manager | Not started | |||
| APX.4.3.1 | Performance and volume testing | 0% | 07 Sep 2026 | 18 Sep 2026 | Test Manager | Not started | |||
| APX.4.3.2 | Security and authorisation testing | 0% | 07 Sep 2026 | 16 Sep 2026 | Security Architect | Not started | |||
| APX.4.3.3 | Disaster recovery and failover test | 0% | 21 Sep 2026 | 25 Sep 2026 | IT Infrastructure Manager | Not started | |||
| APX.4.3.4 | Build regression test pack | 0% | 07 Sep 2026 | 16 Sep 2026 | Test Manager | Not started | |||
| APX.4.3.5 | Set up interface monitoring and alerting | 0% | 07 Sep 2026 | 14 Sep 2026 | Integration Lead | Not started | |||
| APX.4.3.6 | Integration test exit review | 0% | 27 Oct 2026 | 29 Oct 2026 | Test Manager | Not started | |||
| APX.5 | A.5 User acceptance testing | 0% | 30 Oct 2026 | 15 Dec 2026 | Test Manager | Not started | |||
| APX.5.1 | UAT preparation | 0% | 30 Oct 2026 | 17 Nov 2026 | Test Manager | Not started | |||
| APX.5.1.1 | Refresh UAT environment with mock load 2 data | 0% | 30 Oct 2026 | 03 Nov 2026 | IT Infrastructure Manager | Not started | |||
| APX.5.1.2 | Prepare UAT scripts and test data | 0% | 04 Nov 2026 | 10 Nov 2026 | Test Manager | Not started | |||
| APX.5.1.3 | Train UAT testers and business super users | 0% | 11 Nov 2026 | 17 Nov 2026 | Change Manager | Not started | |||
| APX.5.2 | UAT cycles | 0% | 18 Nov 2026 | 15 Dec 2026 | Test Manager | Not started | |||
| APX.5.2.1 | UAT cycle 1: finance | 0% | 18 Nov 2026 | 27 Nov 2026 | Finance Lead | Not started | |||
| APX.5.2.2 | UAT cycle 1: supply chain and warehouse | 0% | 18 Nov 2026 | 27 Nov 2026 | Supply Chain Lead | Not started | |||
| APX.5.2.3 | UAT cycle 1: production and maintenance | 0% | 18 Nov 2026 | 27 Nov 2026 | Production Systems Lead | Not started | |||
| APX.5.2.4 | UAT defect resolution | 0% | 30 Nov 2026 | 08 Dec 2026 | Integration Lead | Not started | |||
| APX.5.2.5 | UAT cycle 2: regression and retest | 0% | 09 Dec 2026 | 15 Dec 2026 | Test Manager | Not started | |||
| APX.5.2.6 | Milestone: Business sign-off of user acceptance | — | 15 Dec 2026 | 15 Dec 2026 | Plant Manager | Not started | |||
| APX.5.3 | End user readiness | 0% | 18 Nov 2026 | 15 Dec 2026 | Change Manager | Not started | |||
| APX.5.3.1 | Deliver end user training: finance and procurement | 0% | 18 Nov 2026 | 08 Dec 2026 | Change Manager | Not started | |||
| APX.5.3.2 | Deliver end user training: production and warehouse | 0% | 18 Nov 2026 | 08 Dec 2026 | Change Manager | Not started | |||
| APX.5.3.3 | Business readiness assessment | 0% | 09 Dec 2026 | 15 Dec 2026 | Change Manager | Not started | |||
| APX.5.3.4 | Supplier and customer communications on go-live | 0% | 18 Nov 2026 | 01 Dec 2026 | Supply Chain Lead | Not started | |||
| APX.6 | A.6 Cutover, go-live and hypercare | 0% | 16 Dec 2026 | 24 Feb 2027 | SAP Program Director | Not started | |||
| APX.6.1 | Cutover preparation | 0% | 16 Dec 2026 | 03 Feb 2027 | Cutover Manager | Not started | |||
| APX.6.1.1 | Detailed cutover plan and runbook | 0% | 16 Dec 2026 | 23 Dec 2026 | Cutover Manager | Not started | |||
| APX.6.1.2 | Cutover rehearsal 1 | 0% | 24 Dec 2026 | 31 Dec 2026 | Cutover Manager | Not started | |||
| APX.6.1.3 | Year-end finance close and system freeze | 0% | 04 Jan 2027 | 12 Jan 2027 | Finance Lead | Not started | |||
| APX.6.1.4 | Set up cutover command centre | 0% | 13 Jan 2027 | 15 Jan 2027 | Cutover Manager | Not started | |||
| APX.6.1.5 | Cutover rehearsal 2 and data reconciliation | 0% | 18 Jan 2027 | 22 Jan 2027 | Cutover Manager | Not started | |||
| APX.6.1.6 | Final data load and reconciliation | 0% | 25 Jan 2027 | 01 Feb 2027 | Data Migration Lead | Not started | |||
| APX.6.1.7 | Go-live readiness review | 0% | 02 Feb 2027 | 03 Feb 2027 | SAP Program Director | Not started | |||
| APX.6.1.8 | Milestone: SAP go-live | — | 03 Feb 2027 | 03 Feb 2027 | SAP Program Director | Not started | |||
| APX.6.2 | Hypercare | 0% | 04 Feb 2027 | 24 Feb 2027 | Hypercare Lead | Not started | |||
| APX.6.2.1 | Hypercare: floor-walkers and daily triage | 0% | 04 Feb 2027 | 24 Feb 2027 | Hypercare Lead | Not started | |||
| APX.6.2.2 | First month-end close on new system | 0% | 04 Feb 2027 | 15 Feb 2027 | Finance Lead | Not started | |||
| APX.6.2.3 | Post go-live process and controls review | 0% | 04 Feb 2027 | 15 Feb 2027 | Internal Audit Manager | Not started | |||
| APX.6.2.4 | Stabilisation issue closure | 0% | 04 Feb 2027 | 19 Feb 2027 | Integration Lead | Not started | |||
| APX.6.2.5 | Hand over to business as usual support | 0% | 22 Feb 2027 | 24 Feb 2027 | IT Infrastructure Manager | Not started | |||
| APX.6.2.6 | Milestone: Hypercare complete | — | 24 Feb 2027 | 24 Feb 2027 | SAP Program Director | Not started | |||
| APX.7 | B.1 Equipment procurement and shutdown planning | 100% | 05 Jan 2026 | 27 Feb 2026 | 27 Feb 2026 ✓ | Line 3 Project Manager | Done | ||
| APX.7.1 | Equipment procurement | 100% | 05 Jan 2026 | 27 Feb 2026 | 27 Feb 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.1 | Survey and laser scan existing Line 3 | 100% | 05 Jan 2026 | 14 Jan 2026 | 14 Jan 2026 ✓ | Line 3 Project Manager | Done | ||
| APX.7.1.2 | Define Line 3 upgrade scope and specification | 100% | 05 Jan 2026 | 14 Jan 2026 | 14 Jan 2026 ✓ | Line 3 Project Manager | Done | ||
| APX.7.1.3 | Request for quotation: drives, PLCs and HMI | 100% | 15 Jan 2026 | 21 Jan 2026 | 21 Jan 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.4 | Evaluate quotations and award to Siemens | 100% | 22 Jan 2026 | 29 Jan 2026 | 29 Jan 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.5 | Place Siemens equipment order | 100% | 30 Jan 2026 | 03 Feb 2026 | 03 Feb 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.6 | Siemens equipment manufacture and delivery | 100% | 04 Feb 2026 | 27 Feb 2026 | 27 Feb 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.7 | Tender and award: forming equipment and conveyors | 100% | 15 Jan 2026 | 05 Feb 2026 | 05 Feb 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.8 | Tender and award: guarding and safety systems | 100% | 15 Jan 2026 | 02 Feb 2026 | 02 Feb 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.9 | Tender and award: electrical and utilities contractor | 100% | 15 Jan 2026 | 05 Feb 2026 | 05 Feb 2026 ✓ | Procurement Manager | Done | ||
| APX.7.1.10 | Milestone: All Line 3 equipment ordered | — | 05 Feb 2026 | 05 Feb 2026 | 05 Feb 2026 ✓ | Procurement Manager | Done | ||
| APX.7.2 | Shutdown planning | 100% | 15 Jan 2026 | 24 Feb 2026 | 24 Feb 2026 ✓ | Shutdown Planner | Done | ||
| APX.7.2.1 | Develop shutdown plan and sequencing | 100% | 15 Jan 2026 | 10 Feb 2026 | 10 Feb 2026 ✓ | Shutdown Planner | Done | ||
| APX.7.2.2 | Contractor mobilisation and induction plan | 100% | 11 Feb 2026 | 24 Feb 2026 | 24 Feb 2026 ✓ | Shutdown Planner | Done | ||
| APX.7.2.3 | Safety management plan and permits | 100% | 11 Feb 2026 | 23 Feb 2026 | 23 Feb 2026 ✓ | Safety Manager | Done | ||
| APX.7.2.4 | Hazard and operability study | 100% | 11 Feb 2026 | 20 Feb 2026 | 20 Feb 2026 ✓ | Safety Manager | Done | ||
| APX.7.2.5 | Spares and consumables list | 100% | 15 Jan 2026 | 21 Jan 2026 | 21 Jan 2026 ✓ | Maintenance Manager | Done | ||
| APX.7.2.6 | Customer supply and inventory build plan | 100% | 15 Jan 2026 | 05 Feb 2026 | 05 Feb 2026 ✓ | Production Planner | Done | ||
| APX.7.2.7 | Milestone: Shutdown plan approved | — | 24 Feb 2026 | 24 Feb 2026 | 24 Feb 2026 ✓ | Plant Manager | Done | ||
| APX.8 | B.2 Mechanical installation | 13% | 09 Mar 2026 | 02 Sep 2026 | Mechanical Lead | In progress | |||
| APX.8.1 | Strip-out and civil | 57% | 09 Mar 2026 | 29 May 2026 | Mechanical Lead | In progress | |||
| APX.8.1.1 | Line 3 production shutdown and isolation | 100% | 09 Mar 2026 | 11 Mar 2026 | 11 Mar 2026 ✓ | Plant Manager | Done | ||
| APX.8.1.2 | Strip out existing Line 3 equipment | 100% | 12 Mar 2026 | 14 Apr 2026 | 14 Apr 2026 ✓ | Mechanical Contractor | Done | ||
| APX.8.1.3 | Foundation and floor modifications | 44% | 15 Apr 2026 | 08 May 2026 | Civil Contractor | In progress | |||
| APX.8.1.4 | Install structural steel and platforms | 0% | 11 May 2026 | 29 May 2026 | Mechanical Contractor | Not started | |||
| APX.8.2 | Equipment installation | 0% | 11 May 2026 | 21 Aug 2026 | Mechanical Lead | Not started | |||
| APX.8.2.1 | Install forming and press equipment | 0% | 11 May 2026 | 06 Jul 2026 | Mechanical Contractor | Not started | |||
| APX.8.2.2 | Install conveyors and material handling | 0% | 01 Jun 2026 | 13 Jul 2026 | Mechanical Contractor | Not started | |||
| APX.8.2.3 | Install robotic cell frames and tooling | 0% | 07 Jul 2026 | 05 Aug 2026 | Mechanical Contractor | Not started | |||
| APX.8.2.4 | Install dust extraction and ventilation | 0% | 14 Jul 2026 | 03 Aug 2026 | Mechanical Contractor | Not started | |||
| APX.8.2.5 | Install guarding and safety systems | 0% | 06 Aug 2026 | 21 Aug 2026 | Mechanical Contractor | Not started | |||
| APX.8.3 | Utilities | 0% | 11 May 2026 | 27 Jul 2026 | Electrical Lead | Not started | |||
| APX.8.3.1 | Install power distribution and switchboards | 0% | 11 May 2026 | 15 Jun 2026 | Electrical Contractor | Not started | |||
| APX.8.3.2 | Install compressed air and cooling water | 0% | 11 May 2026 | 05 Jun 2026 | Mechanical Contractor | Not started | |||
| APX.8.3.3 | Install cable trays and field wiring | 0% | 16 Jun 2026 | 27 Jul 2026 | Electrical Contractor | Not started | |||
| APX.8.4 | Mechanical completion | 0% | 24 Aug 2026 | 02 Sep 2026 | Mechanical Lead | Not started | |||
| APX.8.4.1 | Mechanical completion inspection and punch list | 0% | 24 Aug 2026 | 02 Sep 2026 | Mechanical Lead | Not started | |||
| APX.8.4.2 | Milestone: Mechanical completion | — | 28 Aug 2026 | 02 Sep 2026 | Mechanical Lead | Not started | |||
| APX.9 | B.3 SCADA and automation integration | 0% | 01 Sep 2026 | 02 Dec 2026 | Controls Engineer | Not started | |||
| APX.9.1 | Controls installation | 0% | 01 Sep 2026 | 02 Oct 2026 | Controls Engineer | Not started | |||
| APX.9.1.1 | Install and wire PLC panels and drives | 0% | 01 Sep 2026 | 23 Sep 2026 | Controls Contractor | Not started | |||
| APX.9.1.2 | Install field instrumentation and sensors | 0% | 01 Sep 2026 | 30 Sep 2026 | Controls Contractor | Not started | |||
| APX.9.1.3 | Install SCADA servers and HMI stations | 0% | 01 Sep 2026 | 16 Sep 2026 | IT Infrastructure Manager | Not started | IT team also committed to A.4 integration testing in the same window. Gap: 2.0 FTE unresolved. | ||
| APX.9.1.4 | Install control network and cybersecurity controls | 0% | 15 Sep 2026 | 02 Oct 2026 | Network Lead | Not started | |||
| APX.9.2 | Controls configuration | 0% | 22 Sep 2026 | 12 Nov 2026 | Controls Engineer | Not started | |||
| APX.9.2.1 | Load and test PLC programs | 0% | 22 Sep 2026 | 20 Oct 2026 | Controls Engineer | Not started | |||
| APX.9.2.2 | Configure SCADA screens and historian | 0% | 29 Sep 2026 | 22 Oct 2026 | Controls Engineer | Not started | |||
| APX.9.2.3 | Integrate Line 3 with SAP shop floor interface | 0% | 21 Oct 2026 | 12 Nov 2026 | Integration Lead | Not started | IT team also committed to A.4 integration testing in the same window. Gap: 2.0 FTE unresolved. | ||
| APX.9.2.4 | Control loop tuning and safety interlock verification | 0% | 19 Oct 2026 | 03 Nov 2026 | Controls Engineer | Not started | |||
| APX.9.3 | Acceptance testing | 0% | 21 Oct 2026 | 02 Dec 2026 | Controls Engineer | Not started | |||
| APX.9.3.1 | Alarm rationalisation and operator interface review | 0% | 21 Oct 2026 | 03 Nov 2026 | Controls Engineer | Not started | |||
| APX.9.3.2 | Factory acceptance tests | 0% | 11 Nov 2026 | 20 Nov 2026 | Controls Engineer | Not started | |||
| APX.9.3.3 | Site acceptance tests | 0% | 19 Nov 2026 | 02 Dec 2026 | Controls Engineer | Not started | |||
| APX.9.3.4 | Operator training on new controls | 0% | 19 Nov 2026 | 27 Nov 2026 | Change Manager | Not started | |||
| APX.9.3.5 | Milestone: Controls integration complete | — | 30 Nov 2026 | 02 Dec 2026 | Controls Engineer | Not started | |||
| APX.10 | B.4 Commissioning and ISO 9001 re-certification | 0% | 01 Dec 2026 | 29 Dec 2026 | Quality Manager | Not started | |||
| APX.10.1 | Commissioning | 0% | 01 Dec 2026 | 17 Dec 2026 | Commissioning Lead | Not started | |||
| APX.10.1.1 | Cold commissioning of Line 3 equipment | 0% | 01 Dec 2026 | 08 Dec 2026 | Commissioning Lead | Not started | |||
| APX.10.1.2 | Hot commissioning and trial production runs | 0% | 07 Dec 2026 | 14 Dec 2026 | Commissioning Lead | Not started | |||
| APX.10.1.3 | Process capability studies | 0% | 11 Dec 2026 | 17 Dec 2026 | Quality Manager | Not started | |||
| APX.10.1.4 | Operator competency assessment | 0% | 07 Dec 2026 | 14 Dec 2026 | Commissioning Lead | Not started | |||
| APX.10.1.5 | Update maintenance procedures and spares | 0% | 07 Dec 2026 | 15 Dec 2026 | Maintenance Manager | Not started | |||
| APX.10.2 | ISO 9001 re-certification | 0% | 01 Dec 2026 | 29 Dec 2026 | Quality Manager | Not started | |||
| APX.10.2.1 | Update quality documentation and work instructions | 0% | 01 Dec 2026 | 14 Dec 2026 | Quality Manager | Not started | |||
| APX.10.2.2 | Internal audit of Line 3 processes | 0% | 11 Dec 2026 | 17 Dec 2026 | Quality Manager | Not started | |||
| APX.10.2.3 | ISO 9001 re-certification audit | 0% | 16 Dec 2026 | 22 Dec 2026 | Quality Manager | Not started | |||
| APX.10.2.4 | Close audit findings | 0% | 21 Dec 2026 | 29 Dec 2026 | Quality Manager | Not started | |||
| APX.10.2.5 | Milestone: ISO 9001 certificate confirmed | — | 23 Dec 2026 | 29 Dec 2026 | Quality Manager | Not started | |||
| APX.11 | C Production restart | 0% | 04 Feb 2027 | 24 Feb 2027 | Plant Manager | Not started | |||
| APX.11.1 | Restart and ramp-up | 0% | 04 Feb 2027 | 24 Feb 2027 | Plant Manager | Not started | |||
| APX.11.1.1 | Production restart readiness review | 0% | 04 Feb 2027 | 10 Feb 2027 | Plant Manager | Not started | |||
| APX.11.1.2 | Ramp-up to full rate on new system | 0% | 11 Feb 2027 | 24 Feb 2027 | Plant Manager | Not started | |||
| APX.11.1.3 | Milestone: Full production resumption | — | 24 Feb 2027 | 24 Feb 2027 | Plant Manager | Not started |
227 rows from the Apex demonstration schedule export. Finish dates in red are past plan or forecast beyond plan.
Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal.
Data migration has used all of its float
Cleanse open purchase orders (APX.3.2.5, Data Quality Analyst) is 2% complete and now finishes 2 Oct 2026, against a baseline of 3 Sep 2026. The baseline assessment (APX.3.1.2) found 14,000 open purchase orders that need manual cleansing.
The task is 21 working days behind baseline and has 0 days of float. Mock load 2 sign-off (29 Oct 2026) and the work behind it to go-live (3 Feb 2027) are on the same path, so any further slip on cleansing moves go-live and production resumption (24 Feb 2027) by the same amount. Nothing is late today, because the delay has so far been absorbed by the buffer.
The IT team is double-booked from September
Interface testing in A.4 (APX.4.2.1 and APX.4.2.3, Integration Lead) and the SCADA IT tasks in B.3 (APX.9.1.3 and APX.9.2.3) are dated into the same weeks from 7 Sep 2026. Source comments put demand at 6.0 FTE against 4.0 FTE available and the decision is outstanding.
Integration testing has 0 days of float, so a shortage there delays go-live and production resumption day for day. The SCADA tasks have 36 and 26 working days of float in the export, so moving them is the cheaper way to close a 2.0 FTE gap (recommended, not in the schedule).
User acceptance testing starts with no buffer
User acceptance testing (A.5) starts 30 Oct 2026, the working day after integration testing and data migration both finish on 29 Oct 2026.
Both feeders have 0 days of float, so any slip in either shortens the acceptance window or pushes go-live. The year-end close and system freeze that follows acceptance is also on the path to go-live (3 Feb 2027).
Action 1 depends on an executive decision. See Decisions Required on the Executive Overview.
Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal. Owners and due dates are Cherry recommendations. Urgency is measured from the 27 Apr 2026 status date: This week = due within 5 working days, This month = within 20, Monitor = later. The export does not hold action owners or due dates.
Decide how to cover the 2.0 FTE IT gap before integration testing starts
Integration testing and SCADA integration are dated into the same weeks.
Owner: IT Infrastructure Manager, with the Integration Lead and the Line 3 Project Manager. Due: 4 Sep 2026, the last working day before the first interface test. Either add capacity, or move the SCADA IT tasks later within their 26 to 36 working days of float. Protect integration testing, which has none.
Add cleansing capacity and track a weekly burn-down on open purchase orders
The task is 21 working days behind baseline with no float.
Owner: Data Migration Lead. Due: 15 May 2026. Agree the extra reviewers or tooling needed for 14,000 purchase orders, and report the count remaining each week against the 3 Sep 2026 baseline finish. Any day recovered here is a day of float back on the path to go-live.
Protect the user acceptance window with the business
There is no buffer between integration testing and acceptance.
Owner: Test Manager, with the Plant Manager. Due: 31 Aug 2026, before integration testing starts. Agree what scope moves to a second acceptance cycle if integration testing finishes late, so the 15 Dec 2026 acceptance end date does not move.
Program Management21 activities · lead: SAP Program Director
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Confirm program scope and business case | 05 Jan 2026 | 09 Jan 2026 | SAP Program Director | 100% | Done | |
| Establish program governance and steering committee | 12 Jan 2026 | 16 Jan 2026 | SAP Program Director | 100% | Done | |
| Mobilise implementation partner team | 19 Jan 2026 | 23 Jan 2026 | Implementation Partner Lead | 100% | Done | |
| Milestone: Program mobilised | 23 Jan 2026 | 23 Jan 2026 | SAP Program Director | — | Done | |
| Fit-gap analysis | 26 Feb 2026 | 11 Mar 2026 | Business Process Lead | 100% | Done | |
| Draft business blueprint documents | 12 Mar 2026 | 25 Mar 2026 | Business Analyst | 100% | Done | |
| Blueprint review with process owners | 26 Mar 2026 | 30 Mar 2026 | Business Process Lead | 100% | Done | |
| Milestone: Business blueprint signed off | 30 Mar 2026 | 30 Mar 2026 | SAP Program Director | — | Done | |
| Define benefits tracking and program KPIs | 27 Jan 2026 | 02 Feb 2026 | SAP Program Director | 100% | Done | |
| Approve build plan and cut-over principles | 31 Mar 2026 | 31 Mar 2026 | SAP Program Director | 100% | Done | |
| Integrated configuration review | 10 Aug 2026 | 21 Aug 2026 | Solution Architect | 0% | Not started | |
| Build and configuration quality gate | 24 Aug 2026 | 31 Aug 2026 | SAP Program Director | 0% | Not started | |
| Milestone: Build and configuration complete | 31 Aug 2026 | 31 Aug 2026 | SAP Program Director | — | Not started | |
| Detailed cutover plan and runbook | 16 Dec 2026 | 23 Dec 2026 | Cutover Manager | 0% | Not started | |
| Cutover rehearsal 1 | 24 Dec 2026 | 31 Dec 2026 | Cutover Manager | 0% | Not started | |
| Set up cutover command centre | 13 Jan 2027 | 15 Jan 2027 | Cutover Manager | 0% | Not started | |
| Cutover rehearsal 2 and data reconciliation | 18 Jan 2027 | 22 Jan 2027 | Cutover Manager | 0% | Not started | |
| Go-live readiness review | 02 Feb 2027 | 03 Feb 2027 | SAP Program Director | 0% | Not started | |
| Milestone: SAP go-live | 03 Feb 2027 | 03 Feb 2027 | SAP Program Director | — | Not started | |
| Post go-live process and controls review | 04 Feb 2027 | 15 Feb 2027 | Internal Audit Manager | 0% | Not started | |
| Milestone: Hypercare complete | 24 Feb 2027 | 24 Feb 2027 | SAP Program Director | — | Not started |
Finance Systems13 activities · lead: Finance Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Finance and controlling blueprint workshops | 27 Jan 2026 | 23 Feb 2026 | Finance Lead | 100% | Done | |
| Configure general ledger and chart of accounts | 01 Apr 2026 | 20 Apr 2026 | Finance Lead | 100% | Done | |
| Configure controlling and cost centres | 21 Apr 2026 | 06 May 2026 | Finance Lead | 33% | In progress | |
| Configure accounts payable and receivable | 07 May 2026 | 28 May 2026 | Finance Lead | 0% | Not started | |
| Configure asset accounting | 29 May 2026 | 10 Jun 2026 | Finance Lead | 0% | Not started | |
| Configure financial close and reporting | 11 Jun 2026 | 02 Jul 2026 | Finance Lead | 0% | Not started | |
| Finance unit testing | 03 Jul 2026 | 20 Jul 2026 | Finance Lead | 0% | Not started | |
| Configure treasury and bank connectivity | 01 Apr 2026 | 23 Apr 2026 | Finance Lead | 100% | Done | |
| Configure intercompany and consolidation | 01 Apr 2026 | 23 Apr 2026 | Finance Lead | 100% | Done | |
| Reconcile historical balances for migration | 24 Apr 2026 | 14 May 2026 | Finance Lead | 7% | In progress | |
| UAT cycle 1: finance | 18 Nov 2026 | 27 Nov 2026 | Finance Lead | 0% | Not started | |
| Year-end finance close and system freeze | 04 Jan 2027 | 12 Jan 2027 | Finance Lead | 0% | Not started | |
| First month-end close on new system | 04 Feb 2027 | 15 Feb 2027 | Finance Lead | 0% | Not started |
Supply Chain Systems11 activities · lead: Supply Chain Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Procurement and inventory blueprint workshops | 27 Jan 2026 | 23 Feb 2026 | Supply Chain Lead | 100% | Done | |
| Sales and distribution blueprint workshops | 27 Jan 2026 | 13 Feb 2026 | Supply Chain Lead | 100% | Done | |
| Warehouse and logistics blueprint workshops | 27 Jan 2026 | 11 Feb 2026 | Warehouse Manager | 100% | Done | |
| Configure procurement and purchasing | 01 Apr 2026 | 30 Apr 2026 | Supply Chain Lead | 80% | In progress | |
| Configure inventory management | 01 May 2026 | 21 May 2026 | Supply Chain Lead | 0% | Not started | |
| Configure warehouse management | 22 May 2026 | 12 Jun 2026 | Warehouse Manager | 0% | Not started | |
| Configure sales and distribution | 15 Jun 2026 | 03 Jul 2026 | Supply Chain Lead | 0% | Not started | |
| Configure supplier and customer portals | 06 Jul 2026 | 21 Jul 2026 | Supply Chain Lead | 0% | Not started | |
| Supply chain unit testing | 22 Jul 2026 | 06 Aug 2026 | Supply Chain Lead | 0% | Not started | |
| UAT cycle 1: supply chain and warehouse | 18 Nov 2026 | 27 Nov 2026 | Supply Chain Lead | 0% | Not started | |
| Supplier and customer communications on go-live | 18 Nov 2026 | 01 Dec 2026 | Supply Chain Lead | 0% | Not started |
Production Systems9 activities · lead: Production Systems Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Production planning blueprint workshops | 27 Jan 2026 | 25 Feb 2026 | Production Systems Lead | 100% | Done | |
| Plant maintenance blueprint workshops | 27 Jan 2026 | 11 Feb 2026 | Maintenance Manager | 100% | Done | |
| Configure bills of materials and routings | 01 Apr 2026 | 30 Apr 2026 | Production Systems Lead | 80% | In progress | |
| Configure production planning and scheduling | 01 May 2026 | 28 May 2026 | Production Systems Lead | 0% | Not started | |
| Configure shop floor execution | 29 May 2026 | 24 Jun 2026 | Production Systems Lead | 0% | Not started | |
| Configure plant maintenance | 25 Jun 2026 | 10 Jul 2026 | Maintenance Manager | 0% | Not started | |
| Production unit testing | 27 Jul 2026 | 07 Aug 2026 | Production Systems Lead | 0% | Not started | |
| Configure demand and capacity planning | 01 Apr 2026 | 30 Apr 2026 | Production Systems Lead | 80% | In progress | |
| UAT cycle 1: production and maintenance | 18 Nov 2026 | 27 Nov 2026 | Production Systems Lead | 0% | Not started |
Quality and Compliance8 activities · lead: Quality Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Quality management blueprint workshops | 27 Jan 2026 | 11 Feb 2026 | Quality Manager | 100% | Done | |
| Configure quality management and inspection plans | 13 Jul 2026 | 24 Jul 2026 | Quality Manager | 0% | Not started | |
| Process capability studies | 11 Dec 2026 | 17 Dec 2026 | Quality Manager | 0% | Not started | |
| Update quality documentation and work instructions | 01 Dec 2026 | 14 Dec 2026 | Quality Manager | 0% | Not started | |
| Internal audit of Line 3 processes | 11 Dec 2026 | 17 Dec 2026 | Quality Manager | 0% | Not started | |
| ISO 9001 re-certification audit | 16 Dec 2026 | 22 Dec 2026 | Quality Manager | 0% | Not started | |
| Close audit findings | 21 Dec 2026 | 29 Dec 2026 | Quality Manager | 0% | Not started | |
| Milestone: ISO 9001 certificate confirmed | 23 Dec 2026 | 29 Dec 2026 | Quality Manager | — | Not started |
IT Infrastructure15 activities · lead: IT Infrastructure Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Technical architecture and landscape design | 27 Jan 2026 | 16 Feb 2026 | Solution Architect | 100% | Done | |
| Security and authorisation concept | 17 Feb 2026 | 02 Mar 2026 | Security Architect | 100% | Done | |
| Inventory current systems and interfaces | 27 Jan 2026 | 09 Feb 2026 | Solution Architect | 100% | Done | |
| Plant network and operational technology security assessment | 27 Jan 2026 | 09 Feb 2026 | Security Architect | 100% | Done | |
| Provision development and quality systems | 01 Apr 2026 | 16 Apr 2026 | IT Infrastructure Manager | 100% | Done | |
| Install SAP Fiori front end and gateway | 17 Apr 2026 | 30 Apr 2026 | Basis Lead | 60% | In progress | |
| Configure user roles and authorisations | 01 May 2026 | 28 May 2026 | Security Architect | 0% | Not started | |
| Provision production and disaster recovery systems | 01 May 2026 | 28 May 2026 | IT Infrastructure Manager | 0% | Not started | |
| Network and plant connectivity upgrade | 01 Apr 2026 | 07 May 2026 | Network Lead | 64% | In progress | |
| Security and authorisation testing | 07 Sep 2026 | 16 Sep 2026 | Security Architect | 0% | Not started | |
| Disaster recovery and failover test | 21 Sep 2026 | 25 Sep 2026 | IT Infrastructure Manager | 0% | Not started | |
| Refresh UAT environment with mock load 2 data | 30 Oct 2026 | 03 Nov 2026 | IT Infrastructure Manager | 0% | Not started | |
| Hand over to business as usual support | 22 Feb 2027 | 24 Feb 2027 | IT Infrastructure Manager | 0% | Not started | |
| Install SCADA servers and HMI stations | 01 Sep 2026 | 16 Sep 2026 | IT Infrastructure Manager | 0% | Not started | |
| Install control network and cybersecurity controls | 15 Sep 2026 | 02 Oct 2026 | Network Lead | 0% | Not started |
Integration15 activities · lead: Integration Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Integration architecture design | 17 Feb 2026 | 04 Mar 2026 | Integration Lead | 100% | Done | |
| Develop custom reports | 01 Apr 2026 | 07 May 2026 | Development Lead | 64% | In progress | |
| Develop interfaces to plant control systems | 01 Apr 2026 | 21 May 2026 | Integration Lead | 46% | In progress | |
| Develop custom workflows and approvals | 08 May 2026 | 04 Jun 2026 | Development Lead | 0% | Not started | |
| Code review and unit test of custom objects | 05 Jun 2026 | 26 Jun 2026 | Development Lead | 0% | Not started | |
| Develop custom forms and labels | 01 Apr 2026 | 23 Apr 2026 | Development Lead | 100% | Done | |
| Build analytics dashboards | 08 May 2026 | 04 Jun 2026 | Development Lead | 0% | Not started | |
| Interface testing: finance and banking | 07 Sep 2026 | 14 Sep 2026 | Integration Lead | 0% | Not started | |
| Interface testing: supplier and customer portals | 07 Sep 2026 | 14 Sep 2026 | Integration Lead | 0% | Not started | |
| Interface testing: plant control and shop floor systems | 15 Sep 2026 | 28 Sep 2026 | Integration Lead | 0% | Not started | |
| Integration defect fixing and retest | 15 Oct 2026 | 26 Oct 2026 | Integration Lead | 0% | Not started | |
| Set up interface monitoring and alerting | 07 Sep 2026 | 14 Sep 2026 | Integration Lead | 0% | Not started | |
| UAT defect resolution | 30 Nov 2026 | 08 Dec 2026 | Integration Lead | 0% | Not started | |
| Stabilisation issue closure | 04 Feb 2027 | 19 Feb 2027 | Integration Lead | 0% | Not started | |
| Integrate Line 3 with SAP shop floor interface | 21 Oct 2026 | 12 Nov 2026 | Integration Lead | 0% | Not started |
Data Migration24 activities · lead: Data Migration Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Data migration strategy and approach | 27 Jan 2026 | 09 Feb 2026 | Data Migration Lead | 100% | Done | |
| Master data governance design | 27 Jan 2026 | 05 Feb 2026 | Data Migration Lead | 100% | Done | |
| Develop data migration load programs | 01 Apr 2026 | 21 May 2026 | Data Migration Lead | 46% | In progress | |
| Define migration objects and scope | 01 Apr 2026 | 09 Apr 2026 | Data Migration Lead | 100% | Done | |
| Data quality baseline assessment | 10 Apr 2026 | 17 Apr 2026 | Data Quality Analyst | 100% | Done | |
| Assign data owners and cleansing responsibilities | 20 Apr 2026 | 22 Apr 2026 | Data Migration Lead | 100% | Done | |
| Select migration tooling and reconciliation approach | 10 Apr 2026 | 23 Apr 2026 | Data Migration Lead | 100% | Done | |
| Cleanse customer master data | 23 Apr 2026 | 27 May 2026 | Data Quality Analyst | 8% | In progress | |
| Cleanse vendor master data | 23 Apr 2026 | 27 May 2026 | Data Quality Analyst | 8% | In progress | |
| Cleanse material master data | 23 Apr 2026 | 18 Jun 2026 | Data Quality Analyst | 5% | In progress | |
| Cleanse bills of materials and routings | 23 Apr 2026 | 03 Jun 2026 | Production Systems Lead | 7% | In progress | |
| Cleanse open purchase orders | 23 Apr 2026 | 02 Oct 2026 | Data Quality Analyst | 2% | Delayed | |
| Cleanse employee and cost centre data | 23 Apr 2026 | 06 May 2026 | Data Quality Analyst | 20% | In progress | |
| Cleanse open sales orders and contracts | 23 Apr 2026 | 20 May 2026 | Data Quality Analyst | 10% | In progress | |
| Data owner sign-off of cleansed master data | 19 Jun 2026 | 25 Jun 2026 | Data Migration Lead | 0% | Not started | |
| Build extraction and transformation rules | 24 Apr 2026 | 04 Jun 2026 | Data Migration Lead | 3% | In progress | |
| Build reconciliation reports | 05 Jun 2026 | 26 Jun 2026 | Data Migration Lead | 0% | Not started | |
| Migration tooling unit test | 29 Jun 2026 | 10 Jul 2026 | Data Migration Lead | 0% | Not started | |
| Mock load 1: master data | 10 Aug 2026 | 21 Aug 2026 | Data Migration Lead | 0% | Not started | |
| Mock load 1 reconciliation and defect fixing | 24 Aug 2026 | 04 Sep 2026 | Data Migration Lead | 0% | Not started | |
| Mock load 2: master and transactional data | 06 Oct 2026 | 19 Oct 2026 | Data Migration Lead | 0% | Not started | |
| Mock load 2 reconciliation and defect fixing | 20 Oct 2026 | 29 Oct 2026 | Data Migration Lead | 0% | Not started | |
| Milestone: Mock load 2 signed off by data owners | 29 Oct 2026 | 29 Oct 2026 | Data Migration Lead | — | Not started | |
| Final data load and reconciliation | 25 Jan 2027 | 01 Feb 2027 | Data Migration Lead | 0% | Not started |
Testing12 activities · lead: Test Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Test strategy and environment plan | 27 Jan 2026 | 05 Feb 2026 | Test Manager | 100% | Done | |
| Prepare integration test environment and data | 01 Sep 2026 | 04 Sep 2026 | Test Manager | 0% | Not started | |
| Finalise integration test scenarios and scripts | 01 Sep 2026 | 04 Sep 2026 | Test Manager | 0% | Not started | |
| End-to-end cycle 1: order to cash | 15 Sep 2026 | 28 Sep 2026 | Test Manager | 0% | Not started | |
| End-to-end cycle 1: procure to pay | 15 Sep 2026 | 28 Sep 2026 | Test Manager | 0% | Not started | |
| End-to-end cycle 1: plan to produce | 29 Sep 2026 | 14 Oct 2026 | Test Manager | 0% | Not started | |
| Performance and volume testing | 07 Sep 2026 | 18 Sep 2026 | Test Manager | 0% | Not started | |
| Build regression test pack | 07 Sep 2026 | 16 Sep 2026 | Test Manager | 0% | Not started | |
| Integration test exit review | 27 Oct 2026 | 29 Oct 2026 | Test Manager | 0% | Not started | |
| Prepare UAT scripts and test data | 04 Nov 2026 | 10 Nov 2026 | Test Manager | 0% | Not started | |
| UAT cycle 2: regression and retest | 09 Dec 2026 | 15 Dec 2026 | Test Manager | 0% | Not started | |
| Milestone: Business sign-off of user acceptance | 15 Dec 2026 | 15 Dec 2026 | Plant Manager | — | Not started |
Change and Training7 activities · lead: Change Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Change management and training approach | 27 Jan 2026 | 05 Feb 2026 | Change Manager | 100% | Done | |
| Train UAT testers and business super users | 11 Nov 2026 | 17 Nov 2026 | Change Manager | 0% | Not started | |
| Deliver end user training: finance and procurement | 18 Nov 2026 | 08 Dec 2026 | Change Manager | 0% | Not started | |
| Deliver end user training: production and warehouse | 18 Nov 2026 | 08 Dec 2026 | Change Manager | 0% | Not started | |
| Business readiness assessment | 09 Dec 2026 | 15 Dec 2026 | Change Manager | 0% | Not started | |
| Hypercare: floor-walkers and daily triage | 04 Feb 2027 | 24 Feb 2027 | Hypercare Lead | 0% | Not started | |
| Operator training on new controls | 19 Nov 2026 | 27 Nov 2026 | Change Manager | 0% | Not started |
Procurement and Shutdown20 activities · lead: Procurement Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Survey and laser scan existing Line 3 | 05 Jan 2026 | 14 Jan 2026 | Line 3 Project Manager | 100% | Done | |
| Define Line 3 upgrade scope and specification | 05 Jan 2026 | 14 Jan 2026 | Line 3 Project Manager | 100% | Done | |
| Request for quotation: drives, PLCs and HMI | 15 Jan 2026 | 21 Jan 2026 | Procurement Manager | 100% | Done | |
| Evaluate quotations and award to Siemens | 22 Jan 2026 | 29 Jan 2026 | Procurement Manager | 100% | Done | |
| Place Siemens equipment order | 30 Jan 2026 | 03 Feb 2026 | Procurement Manager | 100% | Done | |
| Siemens equipment manufacture and delivery | 04 Feb 2026 | 27 Feb 2026 | Procurement Manager | 100% | Done | |
| Tender and award: forming equipment and conveyors | 15 Jan 2026 | 05 Feb 2026 | Procurement Manager | 100% | Done | |
| Tender and award: guarding and safety systems | 15 Jan 2026 | 02 Feb 2026 | Procurement Manager | 100% | Done | |
| Tender and award: electrical and utilities contractor | 15 Jan 2026 | 05 Feb 2026 | Procurement Manager | 100% | Done | |
| Milestone: All Line 3 equipment ordered | 05 Feb 2026 | 05 Feb 2026 | Procurement Manager | — | Done | |
| Develop shutdown plan and sequencing | 15 Jan 2026 | 10 Feb 2026 | Shutdown Planner | 100% | Done | |
| Contractor mobilisation and induction plan | 11 Feb 2026 | 24 Feb 2026 | Shutdown Planner | 100% | Done | |
| Safety management plan and permits | 11 Feb 2026 | 23 Feb 2026 | Safety Manager | 100% | Done | |
| Hazard and operability study | 11 Feb 2026 | 20 Feb 2026 | Safety Manager | 100% | Done | |
| Spares and consumables list | 15 Jan 2026 | 21 Jan 2026 | Maintenance Manager | 100% | Done | |
| Customer supply and inventory build plan | 15 Jan 2026 | 05 Feb 2026 | Production Planner | 100% | Done | |
| Milestone: Shutdown plan approved | 24 Feb 2026 | 24 Feb 2026 | Plant Manager | — | Done | |
| Production restart readiness review | 04 Feb 2027 | 10 Feb 2027 | Plant Manager | 0% | Not started | |
| Ramp-up to full rate on new system | 11 Feb 2027 | 24 Feb 2027 | Plant Manager | 0% | Not started | |
| Milestone: Full production resumption | 24 Feb 2027 | 24 Feb 2027 | Plant Manager | — | Not started |
Mechanical Installation16 activities · lead: Mechanical Contractor
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Line 3 production shutdown and isolation | 09 Mar 2026 | 11 Mar 2026 | Plant Manager | 100% | Done | |
| Strip out existing Line 3 equipment | 12 Mar 2026 | 14 Apr 2026 | Mechanical Contractor | 100% | Done | |
| Foundation and floor modifications | 15 Apr 2026 | 08 May 2026 | Civil Contractor | 44% | In progress | |
| Install structural steel and platforms | 11 May 2026 | 29 May 2026 | Mechanical Contractor | 0% | Not started | |
| Install forming and press equipment | 11 May 2026 | 06 Jul 2026 | Mechanical Contractor | 0% | Not started | |
| Install conveyors and material handling | 01 Jun 2026 | 13 Jul 2026 | Mechanical Contractor | 0% | Not started | |
| Install robotic cell frames and tooling | 07 Jul 2026 | 05 Aug 2026 | Mechanical Contractor | 0% | Not started | |
| Install dust extraction and ventilation | 14 Jul 2026 | 03 Aug 2026 | Mechanical Contractor | 0% | Not started | |
| Install guarding and safety systems | 06 Aug 2026 | 21 Aug 2026 | Mechanical Contractor | 0% | Not started | |
| Install compressed air and cooling water | 11 May 2026 | 05 Jun 2026 | Mechanical Contractor | 0% | Not started | |
| Mechanical completion inspection and punch list | 24 Aug 2026 | 02 Sep 2026 | Mechanical Lead | 0% | Not started | |
| Milestone: Mechanical completion | 28 Aug 2026 | 02 Sep 2026 | Mechanical Lead | — | Not started | |
| Cold commissioning of Line 3 equipment | 01 Dec 2026 | 08 Dec 2026 | Commissioning Lead | 0% | Not started | |
| Hot commissioning and trial production runs | 07 Dec 2026 | 14 Dec 2026 | Commissioning Lead | 0% | Not started | |
| Operator competency assessment | 07 Dec 2026 | 14 Dec 2026 | Commissioning Lead | 0% | Not started | |
| Update maintenance procedures and spares | 07 Dec 2026 | 15 Dec 2026 | Maintenance Manager | 0% | Not started |
Electrical and Automation11 activities · lead: Controls Engineer
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Install power distribution and switchboards | 11 May 2026 | 15 Jun 2026 | Electrical Contractor | 0% | Not started | |
| Install cable trays and field wiring | 16 Jun 2026 | 27 Jul 2026 | Electrical Contractor | 0% | Not started | |
| Install and wire PLC panels and drives | 01 Sep 2026 | 23 Sep 2026 | Controls Contractor | 0% | Not started | |
| Install field instrumentation and sensors | 01 Sep 2026 | 30 Sep 2026 | Controls Contractor | 0% | Not started | |
| Load and test PLC programs | 22 Sep 2026 | 20 Oct 2026 | Controls Engineer | 0% | Not started | |
| Configure SCADA screens and historian | 29 Sep 2026 | 22 Oct 2026 | Controls Engineer | 0% | Not started | |
| Control loop tuning and safety interlock verification | 19 Oct 2026 | 03 Nov 2026 | Controls Engineer | 0% | Not started | |
| Alarm rationalisation and operator interface review | 21 Oct 2026 | 03 Nov 2026 | Controls Engineer | 0% | Not started | |
| Factory acceptance tests | 11 Nov 2026 | 20 Nov 2026 | Controls Engineer | 0% | Not started | |
| Site acceptance tests | 19 Nov 2026 | 02 Dec 2026 | Controls Engineer | 0% | Not started | |
| Milestone: Controls integration complete | 30 Nov 2026 | 02 Dec 2026 | Controls Engineer | — | Not started |
Critical pathFrom the schedule export
The critical path in the export runs from Cleanse open purchase orders through mock load 2, user acceptance, cutover and SAP go-live, then the production restart review and ramp-up, to Full production resumption, with 0 days of float at every stage. Integration testing runs in parallel and also has no float. The Line 3 upgrade (B) has about 26 working days of float, so it is not driving the end date. No task is dated before the work it depends on, so there is no dependency-corrected scenario.
Sequence: 21 stages, read left to right and top to bottom. Critical activities are counted separately, as the longest path covers more tasks than the stages shown.
Critical path sequence
Critical task detail
| WBS | Task | Duration | Planned finish | Forecast | Owner | |
|---|---|---|---|---|---|---|
| APX.2.4.1 | Configure bills of materials and routings | 20d | 30 Apr 2026 | 30 Apr 2026 | 0d | Production Systems Lead |
| APX.2.4.2 | Configure production planning and scheduling | 20d | 28 May 2026 | 28 May 2026 | 0d | Production Systems Lead |
| APX.2.4.3 | Configure shop floor execution | 18d | 24 Jun 2026 | 24 Jun 2026 | 0d | Production Systems Lead |
| APX.2.4.4 | Configure plant maintenance | 12d | 10 Jul 2026 | 10 Jul 2026 | 0d | Maintenance Manager |
| APX.2.4.5 | Configure quality management and inspection plans | 10d | 24 Jul 2026 | 24 Jul 2026 | 0d | Quality Manager |
| APX.2.4.6 | Production unit testing | 10d | 07 Aug 2026 | 07 Aug 2026 | 0d | Production Systems Lead |
| APX.2.6.1 | Integrated configuration review | 10d | 21 Aug 2026 | 21 Aug 2026 | 0d | Solution Architect |
| APX.2.6.2 | Build and configuration quality gate | 6d | 31 Aug 2026 | 31 Aug 2026 | 0d | SAP Program Director |
| APX.2.6.3 | ◆ Build and configuration complete | — | 31 Aug 2026 | 31 Aug 2026 | 0d | SAP Program Director |
| APX.3.2.5 | Cleanse open purchase orders Alert | 116d | 03 Sep 2026 | 02 Oct 2026 | 0d | Data Quality Analyst |
| APX.3.4.3 | Mock load 2: master and transactional data | 10d | 18 Sep 2026 | 19 Oct 2026 | 0d | Data Migration Lead |
| APX.3.4.4 | Mock load 2 reconciliation and defect fixing | 8d | 30 Sep 2026 | 29 Oct 2026 | 0d | Data Migration Lead |
| APX.3.4.5 | ◆ Mock load 2 signed off by data owners | — | 30 Sep 2026 | 29 Oct 2026 | 0d | Data Migration Lead |
| APX.4.1.1 | Prepare integration test environment and data | 4d | 04 Sep 2026 | 04 Sep 2026 | 0d | Test Manager |
| APX.4.1.2 | Finalise integration test scenarios and scripts | 4d | 04 Sep 2026 | 04 Sep 2026 | 0d | Test Manager |
| APX.4.2.1 | Interface testing: finance and banking Alert | 6d | 14 Sep 2026 | 14 Sep 2026 | 0d | Integration Lead |
| APX.4.2.3 | Interface testing: plant control and shop floor systems Alert | 10d | 28 Sep 2026 | 28 Sep 2026 | 0d | Integration Lead |
| APX.4.2.6 | End-to-end cycle 1: plan to produce | 11d | 14 Oct 2026 | 14 Oct 2026 | 0d | Test Manager |
| APX.4.2.7 | Integration defect fixing and retest | 8d | 26 Oct 2026 | 26 Oct 2026 | 0d | Integration Lead |
| APX.4.3.6 | Integration test exit review | 3d | 29 Oct 2026 | 29 Oct 2026 | 0d | Test Manager |
| APX.5.1.1 | Refresh UAT environment with mock load 2 data | 3d | 03 Nov 2026 | 03 Nov 2026 | 0d | IT Infrastructure Manager |
| APX.5.1.2 | Prepare UAT scripts and test data | 5d | 10 Nov 2026 | 10 Nov 2026 | 0d | Test Manager |
| APX.5.1.3 | Train UAT testers and business super users | 5d | 17 Nov 2026 | 17 Nov 2026 | 0d | Change Manager |
| APX.5.2.1 | UAT cycle 1: finance | 8d | 27 Nov 2026 | 27 Nov 2026 | 0d | Finance Lead |
| APX.5.2.2 | UAT cycle 1: supply chain and warehouse | 8d | 27 Nov 2026 | 27 Nov 2026 | 0d | Supply Chain Lead |
| APX.5.2.3 | UAT cycle 1: production and maintenance | 8d | 27 Nov 2026 | 27 Nov 2026 | 0d | Production Systems Lead |
| APX.5.2.4 | UAT defect resolution | 7d | 08 Dec 2026 | 08 Dec 2026 | 0d | Integration Lead |
| APX.5.2.5 | UAT cycle 2: regression and retest | 5d | 15 Dec 2026 | 15 Dec 2026 | 0d | Test Manager |
| APX.6.1.1 | Detailed cutover plan and runbook | 6d | 23 Dec 2026 | 23 Dec 2026 | 0d | Cutover Manager |
| APX.6.1.2 | Cutover rehearsal 1 | 4d | 31 Dec 2026 | 31 Dec 2026 | 0d | Cutover Manager |
| APX.6.1.3 | Year-end finance close and system freeze | 7d | 12 Jan 2027 | 12 Jan 2027 | 0d | Finance Lead |
| APX.6.1.4 | Set up cutover command centre | 3d | 15 Jan 2027 | 15 Jan 2027 | 0d | Cutover Manager |
| APX.6.1.5 | Cutover rehearsal 2 and data reconciliation | 5d | 22 Jan 2027 | 22 Jan 2027 | 0d | Cutover Manager |
| APX.6.1.6 | Final data load and reconciliation | 5d | 01 Feb 2027 | 01 Feb 2027 | 0d | Data Migration Lead |
| APX.6.1.7 | Go-live readiness review | 2d | 03 Feb 2027 | 03 Feb 2027 | 0d | SAP Program Director |
| APX.6.1.8 | ◆ SAP go-live | — | 03 Feb 2027 | 03 Feb 2027 | 0d | SAP Program Director |
| APX.6.2.1 | Hypercare: floor-walkers and daily triage | 15d | 24 Feb 2027 | 24 Feb 2027 | 0d | Hypercare Lead |
| APX.6.2.4 | Stabilisation issue closure | 12d | 19 Feb 2027 | 19 Feb 2027 | 0d | Integration Lead |
| APX.6.2.5 | Hand over to business as usual support | 3d | 24 Feb 2027 | 24 Feb 2027 | 0d | IT Infrastructure Manager |
| APX.6.2.6 | ◆ Hypercare complete | — | 24 Feb 2027 | 24 Feb 2027 | 0d | SAP Program Director |
| APX.11.1.1 | Production restart readiness review | 5d | 10 Feb 2027 | 10 Feb 2027 | 0d | Plant Manager |
| APX.11.1.2 | Ramp-up to full rate on new system | 10d | 24 Feb 2027 | 24 Feb 2027 | 0d | Plant Manager |
| APX.11.1.3 | ◆ Full production resumption | — | 24 Feb 2027 | 24 Feb 2027 | 0d | Plant Manager |
All 43 critical activities are shown. This table is not curated or capped.
Near-critical tasks
Configure procurement and purchasing1 working days of float
Configure inventory management1 working days of float
Configure warehouse management1 working days of float
Configure sales and distribution1 working days of float
Configure supplier and customer portals1 working days of float
Supply chain unit testing1 working days of float
First month-end close on new system4 working days of float
Post go-live process and controls review4 working days of float
Milestone: Business sign-off of user acceptance10 working days of float
Deliver end user training: finance and procurement10 working days of float
Deliver end user training: production and warehouse10 working days of float
Business readiness assessment10 working days of float
Float distribution
How this was calculatedAssumptions and limits
- Source. Every date, percentage, float and comment comes from the schedule export at the 27 Apr 2026 status date. Cherry adds only labelled calculations and recommendations.
- Links. The export lists predecessors by row ID and treats every link as finish-to-start. It has no lag, constraint or link-type column, so none is assumed. A task starts the next working day after its predecessor finishes; a milestone may share its predecessor's date. Cherry found no task dated before the work it depends on.
- Calendar. Working days are Monday to Friday excluding an illustrative NSW public-holiday list. The export names the list but does not contain it, so Cherry cannot verify it.
- Float. The export's Total Float is working days to the approved completion date (the baseline finish of Full production resumption). Cherry recomputed it independently for the 128 incomplete activities that carry a float value. The zero-float path runs through data migration to go-live and resumption.
- Progress. Overall 31% is duration-weighted across activities (a milestone counts as one day). Planned 32% applies the same weights to baseline dates at the status date. Phase and workstream percentages use the same method.
- Health rating. No task is late and no link is violated, so the rating rests on the zero float on the path to go-live, a task forecast behind baseline, and the unresolved resource gap in source comments. Cherry has not seen a resource plan.
- Near-critical. A fixed 1 to 10 working days. At this project's remaining duration a proportional threshold of 5 percent would be about 11 days, so the count is sensitive to the rule.
- Workstream status. At risk = any incomplete task with negative float. Watch = no negative float but a task marked Delayed. Otherwise Complete, Not started or On plan.
- Not assessed. Cost, resource capacity, hard constraints, link types and lag. The ISO 9001 audit date is treated as a normal task; the export holds no constraint for it.
Apex Manufacturing is a fictional manufacturer, built to show how Cherry reads a project schedule export. It does not describe a real company or project team, and no real organisation has used or endorsed Cherry for it.