Commercial operations is dated 15 Mar 2028, 47 working days behind baseline, because the tunnel boring machine is suspended at Section 3. The grid connection sequence is also out of order, which puts the date at 5 Apr 2028 if energisation comes first (modelled).
- 1Decision needed by 15 Oct 2027: Unit 1 first synchronisation waits for the energisation approval, or the overlap is confirmed in writing.
- 2The Section 3 tunnel drive (MHU.2.4.17) is 60% complete and suspended after the machine met a fault zone. A geotechnical variation is under assessment, an extension of time claim is active, and commercial operations is 47 working days behind baseline.
- 3First synchronisation of Unit 1 (MHU.5.3.1) is dated 18 Oct 2027, 15 working days before the energisation approval on 5 Nov 2027. If the approval comes first (modelled), commercial operations moves from 15 Mar 2028 to 5 Apr 2028.
Schedule outlook
As dated, commercial operations is 15 Mar 2028, 47 working days past baseline. That date assumes Unit 1 synchronises on 18 Oct 2027, before the energisation approval on 5 Nov 2027. If the approval comes first, the date is 5 Apr 2028, 62 working days past baseline (modelled).
Critical pathZero or negative float from Section 3: TBM drive to Commercial operations date
The critical path in the export runs from the Section 3 tunnel drive to commercial operations through 38 activities. Every stage has -47 days of float, so delay passes straight through to the end date.
Delivery roadmapAs at 27 Apr 2026
The tunnel drive (MHU.2.4.17) sits in Civil works, and the grid connection and synchronisation tasks sit in Testing, commissioning and handover. Their effect on commercial operations is shown on the Critical Path tab.
Decisions required
Unit 1 is dated to synchronise before the grid operator has approved energisation
Requested: Decide whether First synchronisation: Unit 1 (MHU.5.3.1) waits for the energisation approval (MHU.5.1.6), or confirm in writing that the overlap is intended and how the connection is protected.
Recommended: Hold synchronisation until the approval is granted, and re-date Unit 1 and the units that follow it.
If not decided: The 15 Mar 2028 commercial operations date is not supported by the schedule's own logic. In the dependency-corrected scenario (modelled) it moves to 5 Apr 2028.
The 330kV transformer purchase is waiting on a design review that is six weeks behind
Requested: Decide whether purchase approval for the 330kV generator transformer (MHU.3.5.4) is released before the electrical design review (MHU.3.1.3) closes, or whether the order waits for it.
Recommended: Set a date for the design review to close and give the Transformer Package Lead authority to place the order on that date.
If not decided: The order was baselined for 31 Mar 2026 and is now dated 14 May 2026. The export shows its float as -15 working days.
What could change the outcome
The top risks that could move this outlook. A preview of the full Risk Analysis tab.
The Section 3 drive is suspended after the machine met a fault zone, so commercial operations is 47 working days behind baseline. A geotechnical variation and an extension of time claim are open.
First synchronisation is dated 15 working days before the grid operator approves energisation, so the commercial operations date is not supported by the schedule's own logic.
The 330kV transformer order is waiting on an electrical design review that is 30 working days behind.
Workstream health
| Workstream | Complete | Position | Status |
|---|---|---|---|
| Approvals and Commercial | 100% | All activities complete | Complete |
| Design | 100% | All activities complete | Complete |
| Civil Works | 67% | 1 delayed | Watch |
| Tunnelling | 49% | 1 delayed, 21 with negative float | At risk |
| Dam Works | 100% | All activities complete | Complete |
| Electrical | 32% | 1 delayed, 9 with negative float | At risk |
| Mechanical | 53% | 3 with negative float | At risk |
| Controls and SCADA | 55% | On plan | On plan |
| Environment and Heritage | 43% | 1 with negative float | At risk |
| Grid Connection | 0% | 10 with negative float | At risk |
| Commissioning | 0% | 27 with negative float | At risk |
- All 292 activities have an owner, and dependency links run through the whole project, so float and the critical path are calculated from schedule logic.
- 1 task is dated to start before the work it depends on has finished. The dates do not follow the schedule's own logic there, so the end date shown may be too early. Re-date First synchronisation: Unit 1 or confirm the overlap is intended.
Pre-construction and approvals are complete. Civil works are 63% complete and carry the delay: the Section 3 tunnel drive is suspended and commercial operations is 47 working days behind baseline.
- 1Pre-construction and approvals are complete.
- 2Civil works are 63% complete. The Section 3 tunnel drive is suspended, a geotechnical variation is under assessment and an extension of time claim is active.
- 3The grid connection pre-application is not lodged and Unit 1 synchronisation is dated before energisation approval, so 15 Mar 2028 may be too early.
PhasesSelect a phase to expand
ScheduleAs at 27 Apr 2026
| WBS | Task | % | Start | Finish | Forecast | Owner | Status | Comments | |
|---|---|---|---|---|---|---|---|---|---|
| MHU | Meridian Hydropower Upgrade | 48% | 07 Jan 2025 | 24 Jan 2028 | 29 Mar 2028 | Project Director | In progress | ||
| MHU.1 | Pre-construction and approvals | 100% | 07 Jan 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | Project Director | Done | ||
| MHU.1.1 | Approvals and consents | 100% | 07 Jan 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.1 | Prepare environmental impact assessment | 100% | 07 Jan 2025 | 04 Mar 2025 | 04 Mar 2025 ✓ | Environmental Manager | Done | ||
| MHU.1.1.2 | Public exhibition of environmental assessment | 100% | 05 Mar 2025 | 01 Apr 2025 | 01 Apr 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.3 | Respond to public submissions | 100% | 02 Apr 2025 | 24 Apr 2025 | 24 Apr 2025 ✓ | Environmental Manager | Done | ||
| MHU.1.1.4 | Milestone: Environmental approval granted | — | 24 Apr 2025 | 24 Apr 2025 | 24 Apr 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.5 | Prepare water licence variation application | 100% | 28 Apr 2025 | 16 May 2025 | 16 May 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.6 | Water regulator determination of licence variation | 100% | 19 May 2025 | 23 Jun 2025 | 23 Jun 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.7 | Milestone: Water licence variation granted | — | 23 Jun 2025 | 23 Jun 2025 | 23 Jun 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.8 | Prepare dam safety regulator application | 100% | 05 Mar 2025 | 01 Apr 2025 | 01 Apr 2025 ✓ | Dam Engineer | Done | ||
| MHU.1.1.9 | Dam safety regulator assessment | 100% | 02 Apr 2025 | 16 May 2025 | 16 May 2025 ✓ | Dam Engineer | Done | ||
| MHU.1.1.10 | Milestone: Dam safety approval granted | — | 16 May 2025 | 16 May 2025 | 16 May 2025 ✓ | Dam Engineer | Done | ||
| MHU.1.1.11 | Lodge development application | 100% | 28 Apr 2025 | 02 May 2025 | 02 May 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.12 | Council assessment of development application | 100% | 05 May 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.13 | Milestone: Development consent granted | — | 30 Jun 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Approvals Lead | Done | ||
| MHU.1.1.14 | Milestone: All statutory approvals obtained | — | 30 Jun 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Project Director | Done | ||
| MHU.1.2 | Investigations and design | 100% | 07 Jan 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Design Manager | Done | ||
| MHU.1.2.1 | Geotechnical investigation: tunnel alignment boreholes | 100% | 07 Jan 2025 | 18 Feb 2025 | 18 Feb 2025 ✓ | Geotechnical Engineer | Done | ||
| MHU.1.2.2 | Geotechnical laboratory testing | 100% | 19 Feb 2025 | 11 Mar 2025 | 11 Mar 2025 ✓ | Geotechnical Engineer | Done | ||
| MHU.1.2.3 | Geotechnical baseline report | 100% | 12 Mar 2025 | 01 Apr 2025 | 01 Apr 2025 ✓ | Geotechnical Engineer | Done | ||
| MHU.1.2.4 | Dam condition assessment | 100% | 07 Jan 2025 | 04 Feb 2025 | 04 Feb 2025 ✓ | Dam Engineer | Done | ||
| MHU.1.2.5 | Concept design | 100% | 07 Jan 2025 | 18 Feb 2025 | 18 Feb 2025 ✓ | Design Manager | Done | ||
| MHU.1.2.6 | Detailed design: civil and tunnel works | 100% | 02 Apr 2025 | 16 Jun 2025 | 16 Jun 2025 ✓ | Design Manager | Done | ||
| MHU.1.2.7 | Detailed design: powerhouse | 100% | 19 Feb 2025 | 15 Apr 2025 | 15 Apr 2025 ✓ | Design Manager | Done | ||
| MHU.1.2.8 | Detailed design: tunnel lining and steel penstock | 100% | 02 Apr 2025 | 23 May 2025 | 23 May 2025 ✓ | Design Manager | Done | ||
| MHU.1.2.9 | Independent design review | 100% | 17 Jun 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Design Manager | Done | ||
| MHU.1.2.10 | Milestone: Civil design issued for construction | — | 30 Jun 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Design Manager | Done | ||
| MHU.1.2.11 | Electrical and mechanical design basis report | 100% | 19 Feb 2025 | 01 Apr 2025 | 01 Apr 2025 ✓ | Mechanical Design Lead | Done | ||
| MHU.1.2.12 | Turbine-generator specification | 100% | 02 Apr 2025 | 09 May 2025 | 09 May 2025 ✓ | Mechanical Design Lead | Done | ||
| MHU.1.2.13 | 330kV transformer specification | 100% | 02 Apr 2025 | 02 May 2025 | 02 May 2025 ✓ | Electrical Design Lead | Done | ||
| MHU.1.2.14 | Switchyard and protection basis of design | 100% | 02 Apr 2025 | 09 May 2025 | 09 May 2025 ✓ | Electrical Design Lead | Done | ||
| MHU.1.2.15 | Milestone: Electrical and mechanical design basis approved | — | 09 May 2025 | 09 May 2025 | 09 May 2025 ✓ | Design Manager | Done | ||
| MHU.1.3 | Procurement and contracts | 100% | 07 Jan 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | Procurement Lead | Done | ||
| MHU.1.3.1 | Civil and tunnelling tender | 100% | 19 Feb 2025 | 08 Apr 2025 | 08 Apr 2025 ✓ | Procurement Lead | Done | ||
| MHU.1.3.2 | Civil and tunnelling tender evaluation | 100% | 09 Apr 2025 | 02 May 2025 | 02 May 2025 ✓ | Procurement Lead | Done | ||
| MHU.1.3.3 | Milestone: Civil and tunnelling contract awarded | — | 16 May 2025 | 16 May 2025 | 16 May 2025 ✓ | Commercial Manager | Done | ||
| MHU.1.3.4 | Electrical and mechanical package tender | 100% | 12 May 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Procurement Lead | Done | ||
| MHU.1.3.5 | Electrical and mechanical tender evaluation | 100% | 01 Jul 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | Procurement Lead | Done | ||
| MHU.1.3.6 | Milestone: Electrical and mechanical contract awarded | — | 21 Jul 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | Commercial Manager | Done | ||
| MHU.1.3.7 | Switchyard and transmission tender | 100% | 12 May 2025 | 23 Jun 2025 | 23 Jun 2025 ✓ | Procurement Lead | Done | ||
| MHU.1.3.8 | Switchyard and transmission tender evaluation | 100% | 24 Jun 2025 | 07 Jul 2025 | 07 Jul 2025 ✓ | Procurement Lead | Done | ||
| MHU.1.3.9 | Milestone: Switchyard and transmission contract awarded | — | 07 Jul 2025 | 07 Jul 2025 | 07 Jul 2025 ✓ | Commercial Manager | Done | ||
| MHU.1.3.10 | Project management plan and controls baseline | 100% | 07 Jan 2025 | 04 Feb 2025 | 04 Feb 2025 ✓ | Project Director | Done | ||
| MHU.1.3.11 | Project safety management plan approved | 100% | 05 Feb 2025 | 25 Feb 2025 | 25 Feb 2025 ✓ | Safety Manager | Done | ||
| MHU.2 | Civil works and dam infrastructure | 63% | 19 May 2025 | 24 May 2027 | 29 Jul 2027 | Civil Package Manager | In progress | ||
| MHU.2.1 | Site establishment and access | 100% | 19 May 2025 | 01 Sep 2025 | 01 Sep 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.1.1 | Mobilise civil contractor | 100% | 19 May 2025 | 30 May 2025 | 30 May 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.1.2 | Construct site access road | 100% | 02 Jun 2025 | 28 Jul 2025 | 28 Jul 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.1.3 | Build site camp and offices | 100% | 02 Jun 2025 | 14 Jul 2025 | 14 Jul 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.1.4 | Install temporary power and water | 100% | 15 Jul 2025 | 04 Aug 2025 | 04 Aug 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.1.5 | Establish concrete batch plant | 100% | 05 Aug 2025 | 01 Sep 2025 | 01 Sep 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.1.6 | Establish survey control network | 100% | 02 Jun 2025 | 16 Jun 2025 | 16 Jun 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.1.7 | Milestone: Site established | — | 01 Sep 2025 | 01 Sep 2025 | 01 Sep 2025 ✓ | Site Superintendent | Done | ||
| MHU.2.2 | River diversion and cofferdam | 100% | 01 Jul 2025 | 29 Sep 2025 | 29 Sep 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.2.1 | Cofferdam design check | 100% | 01 Jul 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | Design Manager | Done | ||
| MHU.2.2.2 | Construct upstream cofferdam | 100% | 29 Jul 2025 | 08 Sep 2025 | 08 Sep 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.2.3 | Excavate river diversion channel | 100% | 29 Jul 2025 | 01 Sep 2025 | 01 Sep 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.2.4 | Divert river flow | 100% | 09 Sep 2025 | 15 Sep 2025 | 15 Sep 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.2.5 | Dewater the works area | 100% | 16 Sep 2025 | 29 Sep 2025 | 29 Sep 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.2.6 | Milestone: Works area dry | — | 29 Sep 2025 | 29 Sep 2025 | 29 Sep 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.3 | Intake structure | 100% | 30 Sep 2025 | 30 Mar 2026 | 30 Mar 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.3.1 | Excavate intake structure | 100% | 30 Sep 2025 | 11 Nov 2025 | 11 Nov 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.3.2 | Intake foundation preparation | 100% | 12 Nov 2025 | 02 Dec 2025 | 02 Dec 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.3.3 | Intake formwork and reinforcement | 100% | 03 Dec 2025 | 02 Feb 2026 | 02 Feb 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.3.4 | Pour intake walls and roof slab | 100% | 03 Feb 2026 | 09 Mar 2026 | 09 Mar 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.3.5 | Install trash racks | 100% | 10 Mar 2026 | 30 Mar 2026 | 30 Mar 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.4 | Penstock tunnel | 49% | 19 May 2025 | 24 May 2027 | 29 Jul 2027 | Tunnelling Manager | In progress | ||
| MHU.2.4.1 | TBM design and manufacture | 100% | 19 May 2025 | 25 Aug 2025 | 25 Aug 2025 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.2 | TBM shipping and delivery to site | 100% | 26 Aug 2025 | 15 Sep 2025 | 15 Sep 2025 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.3 | TBM assembly and launch-chamber commissioning | 100% | 16 Sep 2025 | 21 Oct 2025 | 21 Oct 2025 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.4 | Construct tunnel portal and launch pit | 100% | 02 Sep 2025 | 07 Oct 2025 | 07 Oct 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.4.5 | Milestone: TBM launched | — | 21 Oct 2025 | 21 Oct 2025 | 21 Oct 2025 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.6 | Section 1: set up and survey | 100% | 22 Oct 2025 | 28 Oct 2025 | 28 Oct 2025 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.7 | Section 1: TBM drive | 100% | 29 Oct 2025 | 09 Dec 2025 | 09 Dec 2025 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.8 | Section 1: ground support and segment lining | 100% | 10 Dec 2025 | 23 Dec 2025 | 23 Dec 2025 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.9 | Section 1: grouting and survey check | 100% | 24 Dec 2025 | 02 Jan 2026 | 02 Jan 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.10 | Milestone: Section 1 complete | — | 02 Jan 2026 | 02 Jan 2026 | 02 Jan 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.11 | Section 2: set up and survey | 100% | 05 Jan 2026 | 09 Jan 2026 | 09 Jan 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.12 | Section 2: TBM drive | 100% | 12 Jan 2026 | 02 Mar 2026 | 02 Mar 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.13 | Section 2: ground support and segment lining | 100% | 03 Mar 2026 | 16 Mar 2026 | 16 Mar 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.14 | Section 2: grouting and survey check | 100% | 17 Mar 2026 | 23 Mar 2026 | 23 Mar 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.15 | Milestone: Section 2 complete | — | 23 Mar 2026 | 23 Mar 2026 | 23 Mar 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.16 | Section 3: set up and survey | 100% | 24 Mar 2026 | 30 Mar 2026 | 30 Mar 2026 ✓ | Tunnelling Manager | Done | ||
| MHU.2.4.17 | Section 3: TBM drive | 60% | 31 Mar 2026 | 27 May 2026 | 03 Aug 2026 | Tunnelling Manager | Delayed | TBM suspended at Section 3 after it met a fault zone. A geotechnical variation is under assessment and an extension of time claim is active. | |
| MHU.2.4.18 | Section 3: ground support and segment lining | 0% | 04 Aug 2026 | 11 Jun 2026 | 17 Aug 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.19 | Section 3: grouting and survey check | 0% | 18 Aug 2026 | 18 Jun 2026 | 24 Aug 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.20 | Milestone: Section 3 complete | — | 24 Aug 2026 | 18 Jun 2026 | 24 Aug 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.21 | Section 4: set up and survey | 0% | 25 Aug 2026 | 25 Jun 2026 | 31 Aug 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.22 | Section 4: TBM drive | 0% | 01 Sep 2026 | 20 Aug 2026 | 27 Oct 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.23 | Section 4: ground support and segment lining | 0% | 28 Oct 2026 | 03 Sep 2026 | 10 Nov 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.24 | Section 4: grouting and survey check | 0% | 11 Nov 2026 | 10 Sep 2026 | 17 Nov 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.25 | Milestone: Section 4 complete | — | 17 Nov 2026 | 10 Sep 2026 | 17 Nov 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.26 | Section 5: set up and survey | 0% | 18 Nov 2026 | 17 Sep 2026 | 24 Nov 2026 | Tunnelling Manager | Not started | ||
| MHU.2.4.27 | Section 5: TBM drive | 0% | 25 Nov 2026 | 06 Nov 2026 | 15 Jan 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.28 | Section 5: ground support and segment lining | 0% | 18 Jan 2027 | 20 Nov 2026 | 01 Feb 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.29 | Section 5: grouting and survey check | 0% | 02 Feb 2027 | 27 Nov 2026 | 08 Feb 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.30 | Milestone: Section 5 complete | — | 08 Feb 2027 | 27 Nov 2026 | 08 Feb 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.31 | Milestone: TBM breakthrough at powerhouse | — | 08 Feb 2027 | 27 Nov 2026 | 08 Feb 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.32 | Tunnel final concrete lining | 0% | 09 Feb 2027 | 13 Jan 2027 | 22 Mar 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.33 | Install steel penstock liner | 0% | 23 Mar 2027 | 18 Mar 2027 | 26 May 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.34 | Penstock pressure test | 0% | 27 May 2027 | 05 Apr 2027 | 09 Jun 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.35 | Penstock flushing, cleaning and inspection | 0% | 10 Jun 2027 | 26 Apr 2027 | 01 Jul 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.36 | Install penstock instrumentation and monitoring | 0% | 02 Jul 2027 | 24 May 2027 | 29 Jul 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.37 | Milestone: Penstock complete | — | 29 Jul 2027 | 24 May 2027 | 29 Jul 2027 | Tunnelling Manager | Not started | ||
| MHU.2.4.38 | Assess geotechnical variation at Section 3 | 35% | 31 Mar 2026 | 27 May 2026 | Geotechnical Engineer | In progress | Variation under assessment. Ground conditions at Section 3 differ from the geotechnical baseline report. | ||
| MHU.2.4.39 | Contractor lodges extension of time claim | 100% | 31 Mar 2026 | 15 Apr 2026 | 15 Apr 2026 ✓ | Commercial Manager | Done | Claim lodged by the civil and tunnelling contractor. | |
| MHU.2.4.40 | Assess extension of time claim | 25% | 16 Apr 2026 | 11 Jun 2026 | Commercial Manager | In progress | Extension of time claim is active. No determination has been made. | ||
| MHU.2.5 | Powerhouse civil works | 51% | 02 Sep 2025 | 27 Nov 2026 | Civil Package Manager | In progress | |||
| MHU.2.5.1 | Excavate powerhouse pit | 100% | 02 Sep 2025 | 25 Nov 2025 | 25 Nov 2025 ✓ | Civil Package Manager | Done | ||
| MHU.2.5.2 | Rock support and drainage | 100% | 26 Nov 2025 | 09 Jan 2026 | 09 Jan 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.5.3 | Foundation and substructure concrete | 100% | 12 Jan 2026 | 23 Mar 2026 | 23 Mar 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.5.4 | Draft tube and scroll case concrete: Unit 1 | 100% | 24 Mar 2026 | 22 Apr 2026 | 22 Apr 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.5.5 | Draft tube and scroll case concrete: Unit 2 | 10% | 23 Apr 2026 | 20 May 2026 | Civil Package Manager | In progress | |||
| MHU.2.5.6 | Draft tube and scroll case concrete: Unit 3 | 0% | 21 May 2026 | 18 Jun 2026 | Civil Package Manager | Not started | |||
| MHU.2.5.7 | Powerhouse structure to roof | 0% | 19 Jun 2026 | 10 Sep 2026 | Civil Package Manager | Not started | |||
| MHU.2.5.8 | Powerhouse roof, cladding and weatherproofing | 0% | 11 Sep 2026 | 23 Oct 2026 | Civil Package Manager | Not started | |||
| MHU.2.5.9 | Milestone: Powerhouse watertight | — | 23 Oct 2026 | 23 Oct 2026 | Civil Package Manager | Not started | |||
| MHU.2.5.10 | Powerhouse internal fit-out | 0% | 26 Oct 2026 | 27 Nov 2026 | Civil Package Manager | Not started | |||
| MHU.2.6 | Tailrace | 27% | 12 Jan 2026 | 07 Sep 2026 | Civil Package Manager | In progress | |||
| MHU.2.6.1 | Excavate tailrace channel: stage 1 | 100% | 12 Jan 2026 | 02 Feb 2026 | 02 Feb 2026 ✓ | Civil Package Manager | Done | ||
| MHU.2.6.2 | Excavate tailrace channel: stage 2 (find location) | 40% | 03 Feb 2026 | 02 Mar 2026 | 06 May 2026 | Civil Package Manager | Delayed | Works at the tailrace are suspended after First Nations artefacts were found. Waiting on the heritage regulator's assessment. | |
| MHU.2.7 | Dam and spillway works | 100% | 02 Sep 2025 | 16 Jan 2026 | 16 Jan 2026 ✓ | Dam Engineer | Done | ||
| MHU.2.7.1 | Dam crest and parapet refurbishment | 100% | 02 Sep 2025 | 04 Nov 2025 | 04 Nov 2025 ✓ | Dam Engineer | Done | ||
| MHU.2.7.2 | Spillway gate refurbishment | 100% | 02 Sep 2025 | 25 Nov 2025 | 25 Nov 2025 ✓ | Dam Engineer | Done | ||
| MHU.2.7.3 | Dam instrumentation upgrade | 100% | 05 Nov 2025 | 16 Dec 2025 | 16 Dec 2025 ✓ | Dam Engineer | Done | ||
| MHU.2.7.4 | Seepage monitoring system | 100% | 17 Dec 2025 | 16 Jan 2026 | 16 Jan 2026 ✓ | Dam Engineer | Done | ||
| MHU.2.7.5 | Reservoir drawdown and refill plan | 100% | 26 Nov 2025 | 16 Dec 2025 | 16 Dec 2025 ✓ | Dam Engineer | Done | ||
| MHU.2.7.6 | Milestone: Dam works complete | — | 16 Jan 2026 | 16 Jan 2026 | 16 Jan 2026 ✓ | Dam Engineer | Done | ||
| MHU.3 | Mechanical and electrical installation | 47% | 05 May 2025 | 27 Jul 2027 | 30 Sep 2027 | Mechanical Design Lead | In progress | ||
| MHU.3.1 | Electrical design and review | 53% | 05 Jan 2026 | 11 Jun 2026 | Electrical Design Lead | In progress | |||
| MHU.3.1.1 | Electrical single line and protection design | 100% | 05 Jan 2026 | 02 Mar 2026 | 02 Mar 2026 ✓ | Electrical Design Lead | Done | ||
| MHU.3.1.2 | Generator protection studies | 60% | 03 Mar 2026 | 13 May 2026 | Electrical Design Lead | In progress | Revised protection studies are not yet complete. | ||
| MHU.3.1.3 | Electrical design review: 330kV and generator protection | 30% | 03 Mar 2026 | 30 Mar 2026 | 13 May 2026 | Electrical Design Lead | Delayed | The review is six weeks behind. It cannot close until the revised protection studies are complete. | |
| MHU.3.1.4 | Issue electrical drawings for construction | 0% | 14 May 2026 | 11 Jun 2026 | Electrical Design Lead | Not started | |||
| MHU.3.1.5 | Milestone: Electrical design approved | — | 11 Jun 2026 | 11 Jun 2026 | Electrical Design Lead | Not started | |||
| MHU.3.2 | Turbine-generator units | 69% | 22 Jul 2025 | 08 Oct 2026 | Mechanical Design Lead | In progress | |||
| MHU.3.2.1 | Final turbine and generator design approval | 100% | 22 Jul 2025 | 18 Aug 2025 | 18 Aug 2025 ✓ | Mechanical Design Lead | Done | ||
| MHU.3.2.2 | Manufacture turbine, runner and spiral case: Unit 1 | 100% | 19 Aug 2025 | 23 Jan 2026 | 23 Jan 2026 ✓ | Mechanical Design Lead | Done | ||
| MHU.3.2.3 | Manufacture generator stator and rotor: Unit 1 | 100% | 19 Aug 2025 | 09 Jan 2026 | 09 Jan 2026 ✓ | Mechanical Design Lead | Done | ||
| MHU.3.2.4 | Factory acceptance test: Unit 1 turbine | 100% | 27 Jan 2026 | 09 Feb 2026 | 09 Feb 2026 ✓ | Quality Manager | Done | ||
| MHU.3.2.5 | Factory acceptance test: Unit 1 generator | 100% | 12 Jan 2026 | 23 Jan 2026 | 23 Jan 2026 ✓ | Quality Manager | Done | ||
| MHU.3.2.6 | Ship Unit 1 to site | 100% | 10 Feb 2026 | 30 Mar 2026 | 30 Mar 2026 ✓ | Procurement Lead | Done | ||
| MHU.3.2.7 | Milestone: Unit 1 delivered to site | — | 30 Mar 2026 | 30 Mar 2026 | 30 Mar 2026 ✓ | Procurement Lead | Done | ||
| MHU.3.2.8 | Manufacture turbine, runner and spiral case: Unit 2 | 90% | 01 Dec 2025 | 11 May 2026 | Mechanical Design Lead | In progress | |||
| MHU.3.2.9 | Manufacture generator stator and rotor: Unit 2 | 99% | 01 Dec 2025 | 27 Apr 2026 | Mechanical Design Lead | In progress | |||
| MHU.3.2.10 | Factory acceptance test: Unit 2 turbine | 0% | 12 May 2026 | 25 May 2026 | Quality Manager | Not started | |||
| MHU.3.2.11 | Factory acceptance test: Unit 2 generator | 0% | 28 Apr 2026 | 11 May 2026 | Quality Manager | Not started | |||
| MHU.3.2.12 | Ship Unit 2 to site | 0% | 26 May 2026 | 14 Jul 2026 | Procurement Lead | Not started | |||
| MHU.3.2.13 | Milestone: Unit 2 delivered to site | — | 14 Jul 2026 | 14 Jul 2026 | Procurement Lead | Not started | |||
| MHU.3.2.14 | Manufacture turbine, runner and spiral case: Unit 3 | 35% | 02 Mar 2026 | 05 Aug 2026 | Mechanical Design Lead | In progress | |||
| MHU.3.2.15 | Manufacture generator stator and rotor: Unit 3 | 38% | 02 Mar 2026 | 22 Jul 2026 | Mechanical Design Lead | In progress | |||
| MHU.3.2.16 | Factory acceptance test: Unit 3 turbine | 0% | 06 Aug 2026 | 19 Aug 2026 | Quality Manager | Not started | |||
| MHU.3.2.17 | Factory acceptance test: Unit 3 generator | 0% | 23 Jul 2026 | 05 Aug 2026 | Quality Manager | Not started | |||
| MHU.3.2.18 | Ship Unit 3 to site | 0% | 20 Aug 2026 | 08 Oct 2026 | Procurement Lead | Not started | |||
| MHU.3.2.19 | Milestone: Unit 3 delivered to site | — | 08 Oct 2026 | 08 Oct 2026 | Procurement Lead | Not started | |||
| MHU.3.3 | Penstock valves, gates and crane | 80% | 22 Jul 2025 | 27 Jul 2027 | 30 Sep 2027 | Mechanical Design Lead | In progress | ||
| MHU.3.3.1 | Manufacture intake gates | 100% | 22 Jul 2025 | 28 Oct 2025 | 28 Oct 2025 ✓ | Mechanical Design Lead | Done | ||
| MHU.3.3.2 | Deliver intake gates to site | 100% | 29 Oct 2025 | 18 Nov 2025 | 18 Nov 2025 ✓ | Procurement Lead | Done | ||
| MHU.3.3.3 | Install intake gates | 85% | 31 Mar 2026 | 29 Apr 2026 | Site Superintendent | In progress | |||
| MHU.3.3.4 | Manufacture main inlet valves (three) | 100% | 22 Jul 2025 | 25 Nov 2025 | 25 Nov 2025 ✓ | Mechanical Design Lead | Done | ||
| MHU.3.3.5 | Deliver main inlet valves to site | 100% | 26 Nov 2025 | 02 Jan 2026 | 02 Jan 2026 ✓ | Procurement Lead | Done | ||
| MHU.3.3.6 | Install main inlet valve: Unit 1 | 0% | 30 Jul 2027 | 15 Jun 2027 | 19 Aug 2027 | Site Superintendent | Not started | ||
| MHU.3.3.7 | Install main inlet valve: Unit 2 | 0% | 20 Aug 2027 | 06 Jul 2027 | 09 Sep 2027 | Site Superintendent | Not started | ||
| MHU.3.3.8 | Install main inlet valve: Unit 3 | 0% | 10 Sep 2027 | 27 Jul 2027 | 30 Sep 2027 | Site Superintendent | Not started | ||
| MHU.3.3.9 | Manufacture and deliver powerhouse overhead crane | 100% | 22 Jul 2025 | 04 Nov 2025 | 04 Nov 2025 ✓ | Mechanical Design Lead | Done | ||
| MHU.3.3.10 | Install and load test overhead crane | 0% | 11 Sep 2026 | 16 Oct 2026 | Site Superintendent | Not started | |||
| MHU.3.4 | Turbine-generator installation | 0% | 26 Oct 2026 | 20 Jul 2027 | Site Superintendent | Not started | |||
| MHU.3.4.1 | Install draft tube liner and embedded parts: Unit 1 | 0% | 26 Oct 2026 | 13 Nov 2026 | Site Superintendent | Not started | |||
| MHU.3.4.2 | Install spiral case: Unit 1 | 0% | 16 Nov 2026 | 11 Dec 2026 | Site Superintendent | Not started | |||
| MHU.3.4.3 | Install turbine runner and shaft: Unit 1 | 0% | 14 Dec 2026 | 20 Jan 2027 | Site Superintendent | Not started | |||
| MHU.3.4.4 | Install generator stator and rotor: Unit 1 | 0% | 21 Jan 2027 | 04 Mar 2027 | Site Superintendent | Not started | |||
| MHU.3.4.5 | Install auxiliary piping and systems: Unit 1 | 0% | 21 Jan 2027 | 04 Mar 2027 | Site Superintendent | Not started | |||
| MHU.3.4.6 | Install power and control cabling: Unit 1 | 0% | 05 Mar 2027 | 12 Apr 2027 | Site Superintendent | Not started | |||
| MHU.3.4.7 | Milestone: Unit 1 mechanically complete | — | 12 Apr 2027 | 12 Apr 2027 | Site Superintendent | Not started | |||
| MHU.3.4.8 | Install draft tube liner and embedded parts: Unit 2 | 0% | 14 Dec 2026 | 06 Jan 2027 | Site Superintendent | Not started | |||
| MHU.3.4.9 | Install spiral case: Unit 2 | 0% | 07 Jan 2027 | 04 Feb 2027 | Site Superintendent | Not started | |||
| MHU.3.4.10 | Install turbine runner and shaft: Unit 2 | 0% | 05 Feb 2027 | 11 Mar 2027 | Site Superintendent | Not started | |||
| MHU.3.4.11 | Install generator stator and rotor: Unit 2 | 0% | 12 Mar 2027 | 26 Apr 2027 | Site Superintendent | Not started | |||
| MHU.3.4.12 | Install auxiliary piping and systems: Unit 2 | 0% | 12 Mar 2027 | 26 Apr 2027 | Site Superintendent | Not started | |||
| MHU.3.4.13 | Install power and control cabling: Unit 2 | 0% | 27 Apr 2027 | 31 May 2027 | Site Superintendent | Not started | |||
| MHU.3.4.14 | Milestone: Unit 2 mechanically complete | — | 31 May 2027 | 31 May 2027 | Site Superintendent | Not started | |||
| MHU.3.4.15 | Install draft tube liner and embedded parts: Unit 3 | 0% | 05 Feb 2027 | 25 Feb 2027 | Site Superintendent | Not started | |||
| MHU.3.4.16 | Install spiral case: Unit 3 | 0% | 26 Feb 2027 | 25 Mar 2027 | Site Superintendent | Not started | |||
| MHU.3.4.17 | Install turbine runner and shaft: Unit 3 | 0% | 30 Mar 2027 | 03 May 2027 | Site Superintendent | Not started | |||
| MHU.3.4.18 | Install generator stator and rotor: Unit 3 | 0% | 04 May 2027 | 15 Jun 2027 | Site Superintendent | Not started | |||
| MHU.3.4.19 | Install auxiliary piping and systems: Unit 3 | 0% | 04 May 2027 | 15 Jun 2027 | Site Superintendent | Not started | |||
| MHU.3.4.20 | Install power and control cabling: Unit 3 | 0% | 16 Jun 2027 | 20 Jul 2027 | Site Superintendent | Not started | |||
| MHU.3.4.21 | Milestone: Unit 3 mechanically complete | — | 20 Jul 2027 | 20 Jul 2027 | Site Superintendent | Not started | |||
| MHU.3.5 | 330kV generator transformer | 14% | 05 May 2025 | 22 Jun 2027 | 03 Aug 2027 | Transformer Package Lead | In progress | ||
| MHU.3.5.1 | Prepare transformer purchase specification | 100% | 05 May 2025 | 23 May 2025 | 23 May 2025 ✓ | Transformer Package Lead | Done | ||
| MHU.3.5.2 | Transformer tender | 100% | 26 May 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Procurement Lead | Done | ||
| MHU.3.5.3 | Transformer tender evaluation and recommendation | 100% | 01 Jul 2025 | 14 Jul 2025 | 14 Jul 2025 ✓ | Procurement Lead | Done | ||
| MHU.3.5.4 | Place order for 330kV generator transformer | 0% | 14 May 2026 | 08 Apr 2026 | 20 May 2026 | Transformer Package Lead | Not started | Order has not been placed. Purchase approval is waiting on the electrical design review. | |
| MHU.3.5.5 | Manufacture 330kV generator transformer | 0% | 21 May 2026 | 20 Jan 2027 | 04 Mar 2027 | Transformer Package Lead | Not started | ||
| MHU.3.5.6 | Transformer factory acceptance test | 0% | 05 Mar 2027 | 11 Feb 2027 | 25 Mar 2027 | Quality Manager | Not started | ||
| MHU.3.5.7 | Ship transformer to site | 0% | 30 Mar 2027 | 25 Mar 2027 | 10 May 2027 | Procurement Lead | Not started | ||
| MHU.3.5.8 | Deliver and position transformer on plinth | 0% | 11 May 2027 | 12 Apr 2027 | 24 May 2027 | Site Superintendent | Not started | ||
| MHU.3.5.9 | Transformer installation, oil fill and settling | 0% | 25 May 2027 | 24 May 2027 | 06 Jul 2027 | Site Superintendent | Not started | ||
| MHU.3.5.10 | Transformer site tests | 0% | 07 Jul 2027 | 22 Jun 2027 | 03 Aug 2027 | Electrical Design Lead | Not started | ||
| MHU.3.5.11 | Milestone: Transformer ready for energisation | — | 03 Aug 2027 | 22 Jun 2027 | 03 Aug 2027 | Transformer Package Lead | Not started | ||
| MHU.3.6 | Switchyard and transmission | 71% | 02 Sep 2025 | 13 Aug 2026 | Electrical Design Lead | In progress | |||
| MHU.3.6.1 | Switchyard civil works | 100% | 02 Sep 2025 | 28 Oct 2025 | 28 Oct 2025 ✓ | Civil Package Manager | Done | ||
| MHU.3.6.2 | Erect switchyard steel structures | 100% | 29 Oct 2025 | 09 Dec 2025 | 09 Dec 2025 ✓ | Site Superintendent | Done | ||
| MHU.3.6.3 | Install circuit breakers and disconnectors | 100% | 10 Dec 2025 | 23 Jan 2026 | 23 Jan 2026 ✓ | Site Superintendent | Done | ||
| MHU.3.6.4 | Install protection and control panels | 0% | 12 Jun 2026 | 16 Jul 2026 | Electrical Design Lead | Not started | |||
| MHU.3.6.5 | Terminate high-voltage lines and cables | 0% | 17 Jul 2026 | 13 Aug 2026 | Electrical Design Lead | Not started | |||
| MHU.3.6.6 | Earthing and lightning protection | 100% | 10 Dec 2025 | 02 Jan 2026 | 02 Jan 2026 ✓ | Site Superintendent | Done | ||
| MHU.3.6.7 | Milestone: Switchyard complete | — | 13 Aug 2026 | 13 Aug 2026 | Electrical Design Lead | Not started | |||
| MHU.3.7 | Control systems and auxiliaries | 38% | 22 Jul 2025 | 18 Mar 2027 | Controls Lead | In progress | |||
| MHU.3.7.1 | Control system detailed design | 100% | 22 Jul 2025 | 01 Sep 2025 | 01 Sep 2025 ✓ | Controls Lead | Done | ||
| MHU.3.7.2 | Control system hardware manufacture | 100% | 02 Sep 2025 | 25 Nov 2025 | 25 Nov 2025 ✓ | Controls Lead | Done | ||
| MHU.3.7.3 | Control system factory acceptance test | 100% | 26 Nov 2025 | 09 Dec 2025 | 09 Dec 2025 ✓ | Quality Manager | Done | ||
| MHU.3.7.4 | Deliver control system to site | 100% | 10 Dec 2025 | 09 Jan 2026 | 09 Jan 2026 ✓ | Procurement Lead | Done | ||
| MHU.3.7.5 | Install control cabinets and operator room | 0% | 26 Oct 2026 | 27 Nov 2026 | Controls Lead | Not started | |||
| MHU.3.7.6 | Cable installation: control and instrumentation | 0% | 30 Nov 2026 | 04 Feb 2027 | Controls Lead | Not started | |||
| MHU.3.7.7 | Connect SCADA to remote operations centre | 0% | 05 Feb 2027 | 18 Mar 2027 | Controls Lead | Not started | |||
| MHU.3.7.8 | Auxiliary AC and DC supplies | 0% | 26 Oct 2026 | 11 Dec 2026 | Electrical Design Lead | Not started | |||
| MHU.3.7.9 | Fire detection and protection systems | 0% | 26 Oct 2026 | 27 Nov 2026 | Site Superintendent | Not started | |||
| MHU.3.7.10 | Cooling water and drainage systems | 0% | 26 Oct 2026 | 18 Dec 2026 | Site Superintendent | Not started | |||
| MHU.4 | Environmental and heritage management | 43% | 05 Mar 2025 | 24 Jan 2028 | Environmental Manager | In progress | |||
| MHU.4.1 | Environmental management | 46% | 28 Apr 2025 | 24 Jan 2028 | Environmental Manager | In progress | |||
| MHU.4.1.1 | Environmental management plan approved | 100% | 28 Apr 2025 | 16 May 2025 | 16 May 2025 ✓ | Environmental Manager | Done | ||
| MHU.4.1.2 | Water quality monitoring and report: Q2 2025 | 100% | 19 May 2025 | 06 Jun 2025 | 06 Jun 2025 ✓ | Environmental Manager | Done | ||
| MHU.4.1.3 | Water quality monitoring and report: Q3 2025 | 100% | 01 Jul 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | Environmental Manager | Done | ||
| MHU.4.1.4 | Water quality monitoring and report: Q4 2025 | 100% | 01 Oct 2025 | 22 Oct 2025 | 22 Oct 2025 ✓ | Environmental Manager | Done | ||
| MHU.4.1.5 | Water quality monitoring and report: Q1 2026 | 100% | 02 Jan 2026 | 22 Jan 2026 | 22 Jan 2026 ✓ | Environmental Manager | Done | ||
| MHU.4.1.6 | Water quality monitoring and report: Q2 2026 | 100% | 01 Apr 2026 | 23 Apr 2026 | 23 Apr 2026 ✓ | Environmental Manager | Done | ||
| MHU.4.1.7 | Water quality monitoring and report: Q3 2026 | 0% | 01 Jul 2026 | 21 Jul 2026 | Environmental Manager | Not started | |||
| MHU.4.1.8 | Water quality monitoring and report: Q4 2026 | 0% | 01 Oct 2026 | 22 Oct 2026 | Environmental Manager | Not started | |||
| MHU.4.1.9 | Water quality monitoring and report: Q1 2027 | 0% | 04 Jan 2027 | 22 Jan 2027 | Environmental Manager | Not started | |||
| MHU.4.1.10 | Water quality monitoring and report: Q2 2027 | 0% | 01 Apr 2027 | 21 Apr 2027 | Environmental Manager | Not started | |||
| MHU.4.1.11 | Water quality monitoring and report: Q3 2027 | 0% | 01 Jul 2027 | 21 Jul 2027 | Environmental Manager | Not started | |||
| MHU.4.1.12 | Water quality monitoring and report: Q4 2027 | 0% | 01 Oct 2027 | 22 Oct 2027 | Environmental Manager | Not started | |||
| MHU.4.1.13 | Water quality monitoring and report: Q1 2028 | 0% | 04 Jan 2028 | 24 Jan 2028 | Environmental Manager | Not started | |||
| MHU.4.1.14 | Erosion and sediment control audit: Q2 2026 | 100% | 01 Apr 2026 | 14 Apr 2026 | 14 Apr 2026 ✓ | Environmental Manager | Done | ||
| MHU.4.1.15 | Erosion and sediment control audit: Q3 2026 | 0% | 01 Jul 2026 | 10 Jul 2026 | Environmental Manager | Not started | |||
| MHU.4.1.16 | Erosion and sediment control audit: Q4 2026 | 0% | 01 Oct 2026 | 13 Oct 2026 | Environmental Manager | Not started | |||
| MHU.4.1.17 | Erosion and sediment control audit: Q1 2027 | 0% | 04 Jan 2027 | 13 Jan 2027 | Environmental Manager | Not started | |||
| MHU.4.1.18 | Erosion and sediment control audit: Q2 2027 | 0% | 01 Apr 2027 | 12 Apr 2027 | Environmental Manager | Not started | |||
| MHU.4.1.19 | Erosion and sediment control audit: Q3 2027 | 0% | 01 Jul 2027 | 12 Jul 2027 | Environmental Manager | Not started | |||
| MHU.4.1.20 | Erosion and sediment control audit: Q4 2027 | 0% | 01 Oct 2027 | 13 Oct 2027 | Environmental Manager | Not started | |||
| MHU.4.1.21 | Fish passage design | 100% | 28 Apr 2025 | 06 Jun 2025 | 06 Jun 2025 ✓ | Environmental Manager | Done | ||
| MHU.4.1.22 | Construct fish passage | 71% | 10 Mar 2026 | 13 May 2026 | Civil Package Manager | In progress | |||
| MHU.4.1.23 | Fish passage testing and sign-off | 0% | 14 May 2026 | 03 Jun 2026 | Environmental Manager | Not started | |||
| MHU.4.1.24 | Revegetation plan | 100% | 19 May 2025 | 30 May 2025 | 30 May 2025 ✓ | Environmental Manager | Done | ||
| MHU.4.1.25 | Revegetation stage 1: construction areas | 100% | 02 Sep 2025 | 29 Sep 2025 | 29 Sep 2025 ✓ | Environmental Manager | Done | ||
| MHU.4.1.26 | Revegetation stage 2: spoil areas | 0% | 09 Feb 2027 | 29 Dec 2026 | 08 Mar 2027 | Environmental Manager | Not started | ||
| MHU.4.1.27 | Final site stabilisation and rehabilitation | 0% | 09 Mar 2027 | 04 Feb 2027 | 14 Apr 2027 | Environmental Manager | Not started | ||
| MHU.4.2 | Heritage management | 38% | 05 Mar 2025 | 13 Jul 2026 | Heritage Advisor | In progress | |||
| MHU.4.2.1 | Pre-construction heritage survey | 100% | 05 Mar 2025 | 01 Apr 2025 | 01 Apr 2025 ✓ | Heritage Advisor | Done | ||
| MHU.4.2.2 | Heritage management plan approved | 100% | 28 Apr 2025 | 09 May 2025 | 09 May 2025 ✓ | Heritage Advisor | Done | ||
| MHU.4.2.3 | Record artefacts found at tailrace and secure the area | 100% | 16 Mar 2026 | 18 Mar 2026 | 18 Mar 2026 ✓ | Heritage Advisor | Done | First Nations artefacts were found during tailrace excavation. The area is fenced and works have stopped. | |
| MHU.4.2.4 | Heritage regulator assessment of tailrace find | 25% | 19 Mar 2026 | 15 May 2026 | Heritage Advisor | In progress | Assessment is under way. Tailrace works stay suspended until the regulator advises. | ||
| MHU.4.2.5 | Consult First Nations representatives on management of the find | 40% | 19 Mar 2026 | 15 May 2026 | Heritage Advisor | In progress | |||
| MHU.4.2.6 | Update heritage management plan | 0% | 18 May 2026 | 29 May 2026 | Heritage Advisor | Not started | |||
| MHU.4.2.7 | Milestone: Heritage clearance for tailrace works | — | 29 May 2026 | 29 May 2026 | Heritage Advisor | Not started | |||
| MHU.4.2.8 | Heritage monitoring during remaining tailrace excavation | 0% | 01 Jun 2026 | 13 Jul 2026 | Heritage Advisor | Not started | |||
| MHU.4.3 | Community and stakeholders | 33% | 05 May 2025 | 05 Nov 2027 | Community Liaison Lead | In progress | |||
| MHU.4.3.1 | Community liaison committee meeting and update 1 | 100% | 05 May 2025 | 09 May 2025 | 09 May 2025 ✓ | Community Liaison Lead | Done | ||
| MHU.4.3.2 | Community liaison committee meeting and update 2 | 100% | 03 Nov 2025 | 07 Nov 2025 | 07 Nov 2025 ✓ | Community Liaison Lead | Done | ||
| MHU.4.3.3 | Community liaison committee meeting and update 3 | 0% | 04 May 2026 | 08 May 2026 | Community Liaison Lead | Not started | |||
| MHU.4.3.4 | Community liaison committee meeting and update 4 | 0% | 02 Nov 2026 | 06 Nov 2026 | Community Liaison Lead | Not started | |||
| MHU.4.3.5 | Community liaison committee meeting and update 5 | 0% | 03 May 2027 | 07 May 2027 | Community Liaison Lead | Not started | |||
| MHU.4.3.6 | Community liaison committee meeting and update 6 | 0% | 01 Nov 2027 | 05 Nov 2027 | Community Liaison Lead | Not started | |||
| MHU.2.6.3 | Excavate remaining tailrace channel after heritage clearance | 0% | 01 Jun 2026 | 22 Jun 2026 | Civil Package Manager | Not started | |||
| MHU.2.6.4 | Tailrace concrete lining | 0% | 23 Jun 2026 | 03 Aug 2026 | Civil Package Manager | Not started | |||
| MHU.2.6.5 | Tailrace outlet structure | 0% | 04 Aug 2026 | 07 Sep 2026 | Civil Package Manager | Not started | |||
| MHU.2.6.6 | Milestone: Tailrace complete | — | 07 Sep 2026 | 07 Sep 2026 | Civil Package Manager | Not started | |||
| MHU.5 | Testing, commissioning and handover | 0% | 27 Apr 2026 | 21 Jan 2028 | 29 Mar 2028 | Commissioning Manager | Not started | ||
| MHU.5.1 | Grid connection | 0% | 27 Apr 2026 | 05 Jul 2027 | 05 Nov 2027 | Grid Connection Lead | Not started | ||
| MHU.5.1.1 | Lodge AEMO grid connection pre-application | 0% | 27 Apr 2026 | 13 Feb 2026 | 08 May 2026 | Grid Connection Lead | Not started | The pre-application has not been lodged. | |
| MHU.5.1.2 | AEMO and network provider pre-application response | 0% | 11 May 2026 | 08 Jul 2026 | 28 Sep 2026 | Grid Connection Lead | Not started | ||
| MHU.5.1.3 | Prepare and submit full connection application | 0% | 29 Sep 2026 | 15 Oct 2026 | 08 Jan 2027 | Grid Connection Lead | Not started | ||
| MHU.5.1.4 | Connection agreement negotiation | 0% | 11 Jan 2027 | 05 Jul 2027 | 05 Nov 2027 | Grid Connection Lead | Not started | Connection agreement negotiation is running behind plan. | |
| MHU.5.1.5 | Generator performance standards agreed | 0% | 11 Jan 2027 | 09 Apr 2027 | 01 Jul 2027 | Grid Connection Lead | Not started | ||
| MHU.5.1.6 | Milestone: Connection agreement executed | — | 05 Nov 2027 | 05 Jul 2027 | 05 Nov 2027 | Grid Connection Lead | Not started | ||
| MHU.5.1.7 | Power system model validation | 0% | 11 Jan 2027 | 12 Jan 2027 | 07 Apr 2027 | Grid Connection Lead | Not started | ||
| MHU.5.1.8 | Milestone: Energisation approval granted | — | 05 Nov 2027 | 05 Jul 2027 | 05 Nov 2027 | Grid Connection Lead | Not started | Cherry note First synchronisation: Unit 1 (MHU.5.3.1) is dated to start before this is granted. | |
| MHU.5.2 | Pre-commissioning | 0% | 12 Jun 2026 | 21 Sep 2027 | 26 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.1 | Prepare commissioning plan and test procedures | 0% | 12 Jun 2026 | 06 Aug 2026 | Commissioning Manager | Not started | |||
| MHU.5.2.2 | Commission switchyard and transformer | 0% | 04 Aug 2027 | 20 Jul 2027 | 31 Aug 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.3 | Commission auxiliary systems | 0% | 21 Dec 2026 | 28 Jan 2027 | Commissioning Manager | Not started | |||
| MHU.5.2.4 | Commission control and SCADA systems | 0% | 19 Mar 2027 | 03 May 2027 | Commissioning Manager | Not started | |||
| MHU.5.2.5 | Inspection and dry checks: Unit 1 | 0% | 20 Aug 2027 | 06 Jul 2027 | 09 Sep 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.6 | Insulation and protection tests: Unit 1 | 0% | 10 Sep 2027 | 20 Jul 2027 | 23 Sep 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.7 | Wet commissioning without load: Unit 1 | 0% | 24 Sep 2027 | 10 Aug 2027 | 15 Oct 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.8 | Inspection and dry checks: Unit 2 | 0% | 10 Sep 2027 | 27 Jul 2027 | 30 Sep 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.9 | Insulation and protection tests: Unit 2 | 0% | 01 Oct 2027 | 10 Aug 2027 | 15 Oct 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.10 | Wet commissioning without load: Unit 2 | 0% | 18 Oct 2027 | 31 Aug 2027 | 05 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.11 | Inspection and dry checks: Unit 3 | 0% | 01 Oct 2027 | 17 Aug 2027 | 22 Oct 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.12 | Insulation and protection tests: Unit 3 | 0% | 25 Oct 2027 | 31 Aug 2027 | 05 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.2.13 | Wet commissioning without load: Unit 3 | 0% | 08 Nov 2027 | 21 Sep 2027 | 26 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.3 | Hot commissioning | 0% | 18 Oct 2027 | 08 Dec 2027 | 17 Feb 2028 | Commissioning Manager | Not started | ||
| MHU.5.3.1 | First synchronisation: Unit 1 | 0% | 18 Oct 2027 | 17 Aug 2027 | 22 Oct 2027 | Commissioning Manager | Not started | Cherry note Dated to start 15 working days before Energisation approval granted (MHU.5.1.6) on 5 Nov 2027. | |
| MHU.5.3.2 | Load rejection and trip tests: Unit 1 | 0% | 25 Oct 2027 | 31 Aug 2027 | 05 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.3.3 | Performance and efficiency tests: Unit 1 | 0% | 08 Nov 2027 | 14 Sep 2027 | 19 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.3.4 | Grid code compliance tests: Unit 1 | 0% | 22 Nov 2027 | 28 Sep 2027 | 03 Dec 2027 | Grid Connection Lead | Not started | ||
| MHU.5.3.5 | Unit 1 reliability run | 0% | 06 Dec 2027 | 27 Oct 2027 | 05 Jan 2028 | Commissioning Manager | Not started | ||
| MHU.5.3.6 | Milestone: Unit 1 accepted | — | 05 Jan 2028 | 27 Oct 2027 | 05 Jan 2028 | Commissioning Manager | Not started | ||
| MHU.5.3.7 | First synchronisation: Unit 2 | 0% | 08 Nov 2027 | 07 Sep 2027 | 12 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.3.8 | Load rejection and trip tests: Unit 2 | 0% | 15 Nov 2027 | 21 Sep 2027 | 26 Nov 2027 | Commissioning Manager | Not started | ||
| MHU.5.3.9 | Performance and efficiency tests: Unit 2 | 0% | 29 Nov 2027 | 06 Oct 2027 | 10 Dec 2027 | Commissioning Manager | Not started | ||
| MHU.5.3.10 | Grid code compliance tests: Unit 2 | 0% | 13 Dec 2027 | 20 Oct 2027 | 24 Dec 2027 | Grid Connection Lead | Not started | ||
| MHU.5.3.11 | Unit 2 reliability run | 0% | 29 Dec 2027 | 17 Nov 2027 | 27 Jan 2028 | Commissioning Manager | Not started | ||
| MHU.5.3.12 | Milestone: Unit 2 accepted | — | 27 Jan 2028 | 17 Nov 2027 | 27 Jan 2028 | Commissioning Manager | Not started | ||
| MHU.5.3.13 | First synchronisation: Unit 3 | 0% | 29 Nov 2027 | 28 Sep 2027 | 03 Dec 2027 | Commissioning Manager | Not started | ||
| MHU.5.3.14 | Load rejection and trip tests: Unit 3 | 0% | 06 Dec 2027 | 13 Oct 2027 | 17 Dec 2027 | Commissioning Manager | Not started | ||
| MHU.5.3.15 | Performance and efficiency tests: Unit 3 | 0% | 20 Dec 2027 | 27 Oct 2027 | 05 Jan 2028 | Commissioning Manager | Not started | ||
| MHU.5.3.16 | Grid code compliance tests: Unit 3 | 0% | 06 Jan 2028 | 10 Nov 2027 | 19 Jan 2028 | Grid Connection Lead | Not started | ||
| MHU.5.3.17 | Unit 3 reliability run | 0% | 20 Jan 2028 | 08 Dec 2027 | 17 Feb 2028 | Commissioning Manager | Not started | ||
| MHU.5.3.18 | Milestone: Unit 3 accepted | — | 17 Feb 2028 | 08 Dec 2027 | 17 Feb 2028 | Commissioning Manager | Not started | ||
| MHU.5.4 | Commercial operations | 0% | 18 Feb 2028 | 21 Jan 2028 | 29 Mar 2028 | Commissioning Manager | Not started | ||
| MHU.5.4.1 | Whole-station reliability run | 0% | 18 Feb 2028 | 22 Dec 2027 | 02 Mar 2028 | Commissioning Manager | Not started | ||
| MHU.5.4.2 | Final compliance report to the market operator | 0% | 03 Mar 2028 | 07 Jan 2028 | 15 Mar 2028 | Grid Connection Lead | Not started | ||
| MHU.5.4.3 | Milestone: Commercial operations date | — | 15 Mar 2028 | 07 Jan 2028 | 15 Mar 2028 | Project Director | Not started | ||
| MHU.5.4.4 | Final handover and close-out | 0% | 16 Mar 2028 | 21 Jan 2028 | 29 Mar 2028 | Project Director | Not started | ||
| MHU.5.4.5 | Milestone: Defects liability period starts | — | 29 Mar 2028 | 21 Jan 2028 | 29 Mar 2028 | Project Director | Not started | ||
| MHU.5.5 | Handover readiness | 0% | 01 Mar 2027 | 13 Oct 2027 | 17 Dec 2027 | Commissioning Manager | Not started | ||
| MHU.5.5.1 | Operations and maintenance manuals | 0% | 01 Mar 2027 | 25 May 2027 | Commissioning Manager | Not started | |||
| MHU.5.5.2 | Final as-built drawings | 0% | 25 Oct 2027 | 13 Oct 2027 | 17 Dec 2027 | Design Manager | Not started | ||
| MHU.5.5.3 | Operator training | 0% | 18 Oct 2027 | 06 Oct 2027 | 10 Dec 2027 | Commissioning Manager | Not started | ||
| MHU.5.5.4 | Spares and special tools delivered | 0% | 21 Jul 2027 | 31 Aug 2027 | Procurement Lead | Not started |
323 rows from the Meridian demonstration schedule export. Finish dates in red are past plan or forecast beyond plan.
Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal.
Tunnelling is suspended at Section 3 and drives the commercial operations date
Section 3: TBM drive (MHU.2.4.17, Tunnelling Manager) is 60% complete and now finishes 3 Aug 2026, against a baseline of 27 May 2026. Source comment: TBM suspended at Section 3 after it met a fault zone. A geotechnical variation is under assessment and an extension of time claim is active.
Every tunnel section, the lining, the penstock and the unit installations follow it, and the critical path in the export runs through them to commercial operations (38 activities, each at -47 days of float). Commercial operations is 47 working days behind baseline. The variation (MHU.2.4.38) finishes 27 May 2026 and the claim assessment (MHU.2.4.40) 11 Jun 2026, with no determination made.
Unit 1 synchronises before the grid operator approves energisation
First synchronisation: Unit 1 (MHU.5.3.1, Commissioning Manager) is dated to start 18 Oct 2027, but Energisation approval granted (MHU.5.1.6, Grid Connection Lead) is dated 5 Nov 2027.
The overlap is 15 working days. The TBM chain is the critical path as dated, so this link is not visible in the headline float. If energisation comes first (modelled), commercial operations moves from 15 Mar 2028 to 5 Apr 2028: 15 more working days, or 3% of the time remaining, and 62 behind baseline. If it does not, a unit is synchronised to the grid without approval.
The 330kV transformer order is waiting on a delayed design review
Place order for 330kV generator transformer (MHU.3.5.4, Transformer Package Lead) is not placed and is now dated 14 May 2026 to 20 May 2026, against a baseline of 31 Mar 2026. Source comment: purchase approval is waiting on the electrical design review.
The electrical design review (MHU.3.1.3) is 30 working days behind and cannot close until the revised protection studies (MHU.3.1.2) are complete on 13 May 2026. The export shows the order's float as -15 days. The transformer must then be manufactured and shipped before Unit 1 can be commissioned.
The AEMO grid connection pre-application has not been lodged
Lodge AEMO grid connection pre-application (MHU.5.1.1, Grid Connection Lead) is 0% complete and dated 27 Apr 2026, against a baseline of 2 Feb 2026. Source comment: the pre-application has not been lodged. Connection agreement negotiation (MHU.5.1.4) is also running behind plan.
The grid connection tasks lead to the energisation approval and carry -62 days of float in the export, 15 working days more negative than the tunnelling chain. That is 62 working days of slip measured to the approved completion date, which is the corrected-scenario variance, because the float honours the energisation link that the dates do not.
First Nations artefacts have suspended work at the tailrace
Excavate tailrace channel: stage 2 (MHU.2.6.2, Civil Package Manager) is suspended after First Nations artefacts were found. The heritage regulator's assessment (MHU.4.2.4, Heritage Advisor) is 25% complete and finishes 15 May 2026.
Stage 2 now finishes 6 May 2026, 45 working days after baseline. The export shows 354 days of float, so it is not on the critical path today, but the tailrace works stay suspended until the regulator advises.
Actions 1 and 3 depend on executive decisions. See Decisions Required on the Executive Overview.
Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal. Owners and due dates are Cherry recommendations. Urgency is measured from the 27 Apr 2026 status date: This week = due within 5 working days, This month = within 20, Monitor = later. The export does not hold action owners or due dates.
Decide whether Unit 1 synchronisation waits for the energisation approval, and re-date to match
First synchronisation is dated 15 working days before the approval.
Owner: Commissioning Manager, with the Grid Connection Lead. Due: 15 Oct 2027, the last working day before synchronisation is dated. If it waits, move MHU.5.3.1 to start after 5 Nov 2027 and re-date the units, acceptance and commercial operations behind it. If it does not wait, record in writing that the overlap is intended and how the connection is protected. Without a decision the date stays at 15 Mar 2028 when the logic puts it at 5 Apr 2028 (modelled).
Lodge the AEMO grid connection pre-application
It was baselined for 2 Feb 2026 and has not been lodged.
Owner: Grid Connection Lead. Due: 1 May 2026. Every working day it stays unlodged moves the connection agreement, the energisation approval and the grid-dependent commissioning later by the same amount, because the grid chain sits at -62 days of float in the export.
Release the 330kV transformer purchase approval on a fixed date
The order waits on a design review that is 30 working days behind.
Owner: Transformer Package Lead, with the Electrical Design Lead. Due: 13 May 2026, when the design review is dated to finish. Confirm that the revised protection studies finish 13 May 2026 and that the order can be placed the next working day.
Get determinations on the geotechnical variation and the extension of time claim
The tunnel drive is suspended while both are open.
Owner: Commercial Manager, with the Geotechnical Engineer. Due: 27 May 2026, when the variation assessment is dated to finish, with the claim assessment to follow on 11 Jun 2026. A restart date for the Section 3 drive is the input the schedule needs to re-date the 38 activities behind it.
Obtain the heritage regulator's advice and plan the tailrace restart
Tailrace works stay suspended until the regulator advises.
Owner: Heritage Advisor, with the Civil Package Manager. Due: 15 May 2026, when the assessment is dated to finish. The tailrace has 354 working days of float in the export, so there is time to re-sequence, but only if the advice is not late.
Approvals and Commercial25 activities · lead: Approvals Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Prepare environmental impact assessment | 07 Jan 2025 | 04 Mar 2025 | Environmental Manager | 100% | Done | |
| Public exhibition of environmental assessment | 05 Mar 2025 | 01 Apr 2025 | Approvals Lead | 100% | Done | |
| Respond to public submissions | 02 Apr 2025 | 24 Apr 2025 | Environmental Manager | 100% | Done | |
| Milestone: Environmental approval granted | 24 Apr 2025 | 24 Apr 2025 | Approvals Lead | — | Done | |
| Prepare water licence variation application | 28 Apr 2025 | 16 May 2025 | Approvals Lead | 100% | Done | |
| Water regulator determination of licence variation | 19 May 2025 | 23 Jun 2025 | Approvals Lead | 100% | Done | |
| Milestone: Water licence variation granted | 23 Jun 2025 | 23 Jun 2025 | Approvals Lead | — | Done | |
| Prepare dam safety regulator application | 05 Mar 2025 | 01 Apr 2025 | Dam Engineer | 100% | Done | |
| Dam safety regulator assessment | 02 Apr 2025 | 16 May 2025 | Dam Engineer | 100% | Done | |
| Milestone: Dam safety approval granted | 16 May 2025 | 16 May 2025 | Dam Engineer | — | Done | |
| Lodge development application | 28 Apr 2025 | 02 May 2025 | Approvals Lead | 100% | Done | |
| Council assessment of development application | 05 May 2025 | 30 Jun 2025 | Approvals Lead | 100% | Done | |
| Milestone: Development consent granted | 30 Jun 2025 | 30 Jun 2025 | Approvals Lead | — | Done | |
| Milestone: All statutory approvals obtained | 30 Jun 2025 | 30 Jun 2025 | Project Director | — | Done | |
| Civil and tunnelling tender | 19 Feb 2025 | 08 Apr 2025 | Procurement Lead | 100% | Done | |
| Civil and tunnelling tender evaluation | 09 Apr 2025 | 02 May 2025 | Procurement Lead | 100% | Done | |
| Milestone: Civil and tunnelling contract awarded | 16 May 2025 | 16 May 2025 | Commercial Manager | — | Done | |
| Electrical and mechanical package tender | 12 May 2025 | 30 Jun 2025 | Procurement Lead | 100% | Done | |
| Electrical and mechanical tender evaluation | 01 Jul 2025 | 21 Jul 2025 | Procurement Lead | 100% | Done | |
| Milestone: Electrical and mechanical contract awarded | 21 Jul 2025 | 21 Jul 2025 | Commercial Manager | — | Done | |
| Switchyard and transmission tender | 12 May 2025 | 23 Jun 2025 | Procurement Lead | 100% | Done | |
| Switchyard and transmission tender evaluation | 24 Jun 2025 | 07 Jul 2025 | Procurement Lead | 100% | Done | |
| Milestone: Switchyard and transmission contract awarded | 07 Jul 2025 | 07 Jul 2025 | Commercial Manager | — | Done | |
| Project management plan and controls baseline | 07 Jan 2025 | 04 Feb 2025 | Project Director | 100% | Done | |
| Project safety management plan approved | 05 Feb 2025 | 25 Feb 2025 | Safety Manager | 100% | Done |
Design15 activities · lead: Design Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Geotechnical investigation: tunnel alignment boreholes | 07 Jan 2025 | 18 Feb 2025 | Geotechnical Engineer | 100% | Done | |
| Geotechnical laboratory testing | 19 Feb 2025 | 11 Mar 2025 | Geotechnical Engineer | 100% | Done | |
| Geotechnical baseline report | 12 Mar 2025 | 01 Apr 2025 | Geotechnical Engineer | 100% | Done | |
| Dam condition assessment | 07 Jan 2025 | 04 Feb 2025 | Dam Engineer | 100% | Done | |
| Concept design | 07 Jan 2025 | 18 Feb 2025 | Design Manager | 100% | Done | |
| Detailed design: civil and tunnel works | 02 Apr 2025 | 16 Jun 2025 | Design Manager | 100% | Done | |
| Detailed design: powerhouse | 19 Feb 2025 | 15 Apr 2025 | Design Manager | 100% | Done | |
| Detailed design: tunnel lining and steel penstock | 02 Apr 2025 | 23 May 2025 | Design Manager | 100% | Done | |
| Independent design review | 17 Jun 2025 | 30 Jun 2025 | Design Manager | 100% | Done | |
| Milestone: Civil design issued for construction | 30 Jun 2025 | 30 Jun 2025 | Design Manager | — | Done | |
| Electrical and mechanical design basis report | 19 Feb 2025 | 01 Apr 2025 | Mechanical Design Lead | 100% | Done | |
| Turbine-generator specification | 02 Apr 2025 | 09 May 2025 | Mechanical Design Lead | 100% | Done | |
| 330kV transformer specification | 02 Apr 2025 | 02 May 2025 | Electrical Design Lead | 100% | Done | |
| Switchyard and protection basis of design | 02 Apr 2025 | 09 May 2025 | Electrical Design Lead | 100% | Done | |
| Milestone: Electrical and mechanical design basis approved | 09 May 2025 | 09 May 2025 | Design Manager | — | Done |
Civil Works34 activities · lead: Civil Package Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Mobilise civil contractor | 19 May 2025 | 30 May 2025 | Site Superintendent | 100% | Done | |
| Construct site access road | 02 Jun 2025 | 28 Jul 2025 | Site Superintendent | 100% | Done | |
| Build site camp and offices | 02 Jun 2025 | 14 Jul 2025 | Site Superintendent | 100% | Done | |
| Install temporary power and water | 15 Jul 2025 | 04 Aug 2025 | Site Superintendent | 100% | Done | |
| Establish concrete batch plant | 05 Aug 2025 | 01 Sep 2025 | Site Superintendent | 100% | Done | |
| Establish survey control network | 02 Jun 2025 | 16 Jun 2025 | Site Superintendent | 100% | Done | |
| Milestone: Site established | 01 Sep 2025 | 01 Sep 2025 | Site Superintendent | — | Done | |
| Cofferdam design check | 01 Jul 2025 | 21 Jul 2025 | Design Manager | 100% | Done | |
| Construct upstream cofferdam | 29 Jul 2025 | 08 Sep 2025 | Civil Package Manager | 100% | Done | |
| Excavate river diversion channel | 29 Jul 2025 | 01 Sep 2025 | Civil Package Manager | 100% | Done | |
| Divert river flow | 09 Sep 2025 | 15 Sep 2025 | Civil Package Manager | 100% | Done | |
| Dewater the works area | 16 Sep 2025 | 29 Sep 2025 | Civil Package Manager | 100% | Done | |
| Milestone: Works area dry | 29 Sep 2025 | 29 Sep 2025 | Civil Package Manager | — | Done | |
| Excavate intake structure | 30 Sep 2025 | 11 Nov 2025 | Civil Package Manager | 100% | Done | |
| Intake foundation preparation | 12 Nov 2025 | 02 Dec 2025 | Civil Package Manager | 100% | Done | |
| Intake formwork and reinforcement | 03 Dec 2025 | 02 Feb 2026 | Civil Package Manager | 100% | Done | |
| Pour intake walls and roof slab | 03 Feb 2026 | 09 Mar 2026 | Civil Package Manager | 100% | Done | |
| Install trash racks | 10 Mar 2026 | 30 Mar 2026 | Civil Package Manager | 100% | Done | |
| Excavate powerhouse pit | 02 Sep 2025 | 25 Nov 2025 | Civil Package Manager | 100% | Done | |
| Rock support and drainage | 26 Nov 2025 | 09 Jan 2026 | Civil Package Manager | 100% | Done | |
| Foundation and substructure concrete | 12 Jan 2026 | 23 Mar 2026 | Civil Package Manager | 100% | Done | |
| Draft tube and scroll case concrete: Unit 1 | 24 Mar 2026 | 22 Apr 2026 | Civil Package Manager | 100% | Done | |
| Draft tube and scroll case concrete: Unit 2 | 23 Apr 2026 | 20 May 2026 | Civil Package Manager | 10% | In progress | |
| Draft tube and scroll case concrete: Unit 3 | 21 May 2026 | 18 Jun 2026 | Civil Package Manager | 0% | Not started | |
| Powerhouse structure to roof | 19 Jun 2026 | 10 Sep 2026 | Civil Package Manager | 0% | Not started | |
| Powerhouse roof, cladding and weatherproofing | 11 Sep 2026 | 23 Oct 2026 | Civil Package Manager | 0% | Not started | |
| Milestone: Powerhouse watertight | 23 Oct 2026 | 23 Oct 2026 | Civil Package Manager | — | Not started | |
| Powerhouse internal fit-out | 26 Oct 2026 | 27 Nov 2026 | Civil Package Manager | 0% | Not started | |
| Excavate tailrace channel: stage 1 | 12 Jan 2026 | 02 Feb 2026 | Civil Package Manager | 100% | Done | |
| Excavate tailrace channel: stage 2 (find location) | 03 Feb 2026 | 06 May 2026 | Civil Package Manager | 40% | Delayed | |
| Excavate remaining tailrace channel after heritage clearance | 01 Jun 2026 | 22 Jun 2026 | Civil Package Manager | 0% | Not started | |
| Tailrace concrete lining | 23 Jun 2026 | 03 Aug 2026 | Civil Package Manager | 0% | Not started | |
| Tailrace outlet structure | 04 Aug 2026 | 07 Sep 2026 | Civil Package Manager | 0% | Not started | |
| Milestone: Tailrace complete | 07 Sep 2026 | 07 Sep 2026 | Civil Package Manager | — | Not started |
Tunnelling40 activities · lead: Tunnelling Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| TBM design and manufacture | 19 May 2025 | 25 Aug 2025 | Tunnelling Manager | 100% | Done | |
| TBM shipping and delivery to site | 26 Aug 2025 | 15 Sep 2025 | Tunnelling Manager | 100% | Done | |
| TBM assembly and launch-chamber commissioning | 16 Sep 2025 | 21 Oct 2025 | Tunnelling Manager | 100% | Done | |
| Construct tunnel portal and launch pit | 02 Sep 2025 | 07 Oct 2025 | Civil Package Manager | 100% | Done | |
| Milestone: TBM launched | 21 Oct 2025 | 21 Oct 2025 | Tunnelling Manager | — | Done | |
| Section 1: set up and survey | 22 Oct 2025 | 28 Oct 2025 | Tunnelling Manager | 100% | Done | |
| Section 1: TBM drive | 29 Oct 2025 | 09 Dec 2025 | Tunnelling Manager | 100% | Done | |
| Section 1: ground support and segment lining | 10 Dec 2025 | 23 Dec 2025 | Tunnelling Manager | 100% | Done | |
| Section 1: grouting and survey check | 24 Dec 2025 | 02 Jan 2026 | Tunnelling Manager | 100% | Done | |
| Milestone: Section 1 complete | 02 Jan 2026 | 02 Jan 2026 | Tunnelling Manager | — | Done | |
| Section 2: set up and survey | 05 Jan 2026 | 09 Jan 2026 | Tunnelling Manager | 100% | Done | |
| Section 2: TBM drive | 12 Jan 2026 | 02 Mar 2026 | Tunnelling Manager | 100% | Done | |
| Section 2: ground support and segment lining | 03 Mar 2026 | 16 Mar 2026 | Tunnelling Manager | 100% | Done | |
| Section 2: grouting and survey check | 17 Mar 2026 | 23 Mar 2026 | Tunnelling Manager | 100% | Done | |
| Milestone: Section 2 complete | 23 Mar 2026 | 23 Mar 2026 | Tunnelling Manager | — | Done | |
| Section 3: set up and survey | 24 Mar 2026 | 30 Mar 2026 | Tunnelling Manager | 100% | Done | |
| Section 3: TBM drive | 31 Mar 2026 | 03 Aug 2026 | Tunnelling Manager | 60% | Delayed | |
| Section 3: ground support and segment lining | 04 Aug 2026 | 17 Aug 2026 | Tunnelling Manager | 0% | Not started | |
| Section 3: grouting and survey check | 18 Aug 2026 | 24 Aug 2026 | Tunnelling Manager | 0% | Not started | |
| Milestone: Section 3 complete | 24 Aug 2026 | 24 Aug 2026 | Tunnelling Manager | — | Not started | |
| Section 4: set up and survey | 25 Aug 2026 | 31 Aug 2026 | Tunnelling Manager | 0% | Not started | |
| Section 4: TBM drive | 01 Sep 2026 | 27 Oct 2026 | Tunnelling Manager | 0% | Not started | |
| Section 4: ground support and segment lining | 28 Oct 2026 | 10 Nov 2026 | Tunnelling Manager | 0% | Not started | |
| Section 4: grouting and survey check | 11 Nov 2026 | 17 Nov 2026 | Tunnelling Manager | 0% | Not started | |
| Milestone: Section 4 complete | 17 Nov 2026 | 17 Nov 2026 | Tunnelling Manager | — | Not started | |
| Section 5: set up and survey | 18 Nov 2026 | 24 Nov 2026 | Tunnelling Manager | 0% | Not started | |
| Section 5: TBM drive | 25 Nov 2026 | 15 Jan 2027 | Tunnelling Manager | 0% | Not started | |
| Section 5: ground support and segment lining | 18 Jan 2027 | 01 Feb 2027 | Tunnelling Manager | 0% | Not started | |
| Section 5: grouting and survey check | 02 Feb 2027 | 08 Feb 2027 | Tunnelling Manager | 0% | Not started | |
| Milestone: Section 5 complete | 08 Feb 2027 | 08 Feb 2027 | Tunnelling Manager | — | Not started | |
| Milestone: TBM breakthrough at powerhouse | 08 Feb 2027 | 08 Feb 2027 | Tunnelling Manager | — | Not started | |
| Tunnel final concrete lining | 09 Feb 2027 | 22 Mar 2027 | Tunnelling Manager | 0% | Not started | |
| Install steel penstock liner | 23 Mar 2027 | 26 May 2027 | Tunnelling Manager | 0% | Not started | |
| Penstock pressure test | 27 May 2027 | 09 Jun 2027 | Tunnelling Manager | 0% | Not started | |
| Penstock flushing, cleaning and inspection | 10 Jun 2027 | 01 Jul 2027 | Tunnelling Manager | 0% | Not started | |
| Install penstock instrumentation and monitoring | 02 Jul 2027 | 29 Jul 2027 | Tunnelling Manager | 0% | Not started | |
| Milestone: Penstock complete | 29 Jul 2027 | 29 Jul 2027 | Tunnelling Manager | — | Not started | |
| Assess geotechnical variation at Section 3 | 31 Mar 2026 | 27 May 2026 | Geotechnical Engineer | 35% | In progress | |
| Contractor lodges extension of time claim | 31 Mar 2026 | 15 Apr 2026 | Commercial Manager | 100% | Done | |
| Assess extension of time claim | 16 Apr 2026 | 11 Jun 2026 | Commercial Manager | 25% | In progress |
Dam Works6 activities · lead: Dam Engineer
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Dam crest and parapet refurbishment | 02 Sep 2025 | 04 Nov 2025 | Dam Engineer | 100% | Done | |
| Spillway gate refurbishment | 02 Sep 2025 | 25 Nov 2025 | Dam Engineer | 100% | Done | |
| Dam instrumentation upgrade | 05 Nov 2025 | 16 Dec 2025 | Dam Engineer | 100% | Done | |
| Seepage monitoring system | 17 Dec 2025 | 16 Jan 2026 | Dam Engineer | 100% | Done | |
| Reservoir drawdown and refill plan | 26 Nov 2025 | 16 Dec 2025 | Dam Engineer | 100% | Done | |
| Milestone: Dam works complete | 16 Jan 2026 | 16 Jan 2026 | Dam Engineer | — | Done |
Electrical27 activities · lead: Electrical Design Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Electrical single line and protection design | 05 Jan 2026 | 02 Mar 2026 | Electrical Design Lead | 100% | Done | |
| Generator protection studies | 03 Mar 2026 | 13 May 2026 | Electrical Design Lead | 60% | In progress | |
| Electrical design review: 330kV and generator protection | 03 Mar 2026 | 13 May 2026 | Electrical Design Lead | 30% | Delayed | |
| Issue electrical drawings for construction | 14 May 2026 | 11 Jun 2026 | Electrical Design Lead | 0% | Not started | |
| Milestone: Electrical design approved | 11 Jun 2026 | 11 Jun 2026 | Electrical Design Lead | — | Not started | |
| Install power and control cabling: Unit 1 | 05 Mar 2027 | 12 Apr 2027 | Site Superintendent | 0% | Not started | |
| Install power and control cabling: Unit 2 | 27 Apr 2027 | 31 May 2027 | Site Superintendent | 0% | Not started | |
| Install power and control cabling: Unit 3 | 16 Jun 2027 | 20 Jul 2027 | Site Superintendent | 0% | Not started | |
| Prepare transformer purchase specification | 05 May 2025 | 23 May 2025 | Transformer Package Lead | 100% | Done | |
| Transformer tender | 26 May 2025 | 30 Jun 2025 | Procurement Lead | 100% | Done | |
| Transformer tender evaluation and recommendation | 01 Jul 2025 | 14 Jul 2025 | Procurement Lead | 100% | Done | |
| Place order for 330kV generator transformer | 14 May 2026 | 20 May 2026 | Transformer Package Lead | 0% | Not started | |
| Manufacture 330kV generator transformer | 21 May 2026 | 04 Mar 2027 | Transformer Package Lead | 0% | Not started | |
| Transformer factory acceptance test | 05 Mar 2027 | 25 Mar 2027 | Quality Manager | 0% | Not started | |
| Ship transformer to site | 30 Mar 2027 | 10 May 2027 | Procurement Lead | 0% | Not started | |
| Deliver and position transformer on plinth | 11 May 2027 | 24 May 2027 | Site Superintendent | 0% | Not started | |
| Transformer installation, oil fill and settling | 25 May 2027 | 06 Jul 2027 | Site Superintendent | 0% | Not started | |
| Transformer site tests | 07 Jul 2027 | 03 Aug 2027 | Electrical Design Lead | 0% | Not started | |
| Milestone: Transformer ready for energisation | 03 Aug 2027 | 03 Aug 2027 | Transformer Package Lead | — | Not started | |
| Switchyard civil works | 02 Sep 2025 | 28 Oct 2025 | Civil Package Manager | 100% | Done | |
| Erect switchyard steel structures | 29 Oct 2025 | 09 Dec 2025 | Site Superintendent | 100% | Done | |
| Install circuit breakers and disconnectors | 10 Dec 2025 | 23 Jan 2026 | Site Superintendent | 100% | Done | |
| Install protection and control panels | 12 Jun 2026 | 16 Jul 2026 | Electrical Design Lead | 0% | Not started | |
| Terminate high-voltage lines and cables | 17 Jul 2026 | 13 Aug 2026 | Electrical Design Lead | 0% | Not started | |
| Earthing and lightning protection | 10 Dec 2025 | 02 Jan 2026 | Site Superintendent | 100% | Done | |
| Milestone: Switchyard complete | 13 Aug 2026 | 13 Aug 2026 | Electrical Design Lead | — | Not started | |
| Auxiliary AC and DC supplies | 26 Oct 2026 | 11 Dec 2026 | Electrical Design Lead | 0% | Not started |
Mechanical49 activities · lead: Site Superintendent
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Final turbine and generator design approval | 22 Jul 2025 | 18 Aug 2025 | Mechanical Design Lead | 100% | Done | |
| Manufacture turbine, runner and spiral case: Unit 1 | 19 Aug 2025 | 23 Jan 2026 | Mechanical Design Lead | 100% | Done | |
| Manufacture generator stator and rotor: Unit 1 | 19 Aug 2025 | 09 Jan 2026 | Mechanical Design Lead | 100% | Done | |
| Factory acceptance test: Unit 1 turbine | 27 Jan 2026 | 09 Feb 2026 | Quality Manager | 100% | Done | |
| Factory acceptance test: Unit 1 generator | 12 Jan 2026 | 23 Jan 2026 | Quality Manager | 100% | Done | |
| Ship Unit 1 to site | 10 Feb 2026 | 30 Mar 2026 | Procurement Lead | 100% | Done | |
| Milestone: Unit 1 delivered to site | 30 Mar 2026 | 30 Mar 2026 | Procurement Lead | — | Done | |
| Manufacture turbine, runner and spiral case: Unit 2 | 01 Dec 2025 | 11 May 2026 | Mechanical Design Lead | 90% | In progress | |
| Manufacture generator stator and rotor: Unit 2 | 01 Dec 2025 | 27 Apr 2026 | Mechanical Design Lead | 99% | In progress | |
| Factory acceptance test: Unit 2 turbine | 12 May 2026 | 25 May 2026 | Quality Manager | 0% | Not started | |
| Factory acceptance test: Unit 2 generator | 28 Apr 2026 | 11 May 2026 | Quality Manager | 0% | Not started | |
| Ship Unit 2 to site | 26 May 2026 | 14 Jul 2026 | Procurement Lead | 0% | Not started | |
| Milestone: Unit 2 delivered to site | 14 Jul 2026 | 14 Jul 2026 | Procurement Lead | — | Not started | |
| Manufacture turbine, runner and spiral case: Unit 3 | 02 Mar 2026 | 05 Aug 2026 | Mechanical Design Lead | 35% | In progress | |
| Manufacture generator stator and rotor: Unit 3 | 02 Mar 2026 | 22 Jul 2026 | Mechanical Design Lead | 38% | In progress | |
| Factory acceptance test: Unit 3 turbine | 06 Aug 2026 | 19 Aug 2026 | Quality Manager | 0% | Not started | |
| Factory acceptance test: Unit 3 generator | 23 Jul 2026 | 05 Aug 2026 | Quality Manager | 0% | Not started | |
| Ship Unit 3 to site | 20 Aug 2026 | 08 Oct 2026 | Procurement Lead | 0% | Not started | |
| Milestone: Unit 3 delivered to site | 08 Oct 2026 | 08 Oct 2026 | Procurement Lead | — | Not started | |
| Manufacture intake gates | 22 Jul 2025 | 28 Oct 2025 | Mechanical Design Lead | 100% | Done | |
| Deliver intake gates to site | 29 Oct 2025 | 18 Nov 2025 | Procurement Lead | 100% | Done | |
| Install intake gates | 31 Mar 2026 | 29 Apr 2026 | Site Superintendent | 85% | In progress | |
| Manufacture main inlet valves (three) | 22 Jul 2025 | 25 Nov 2025 | Mechanical Design Lead | 100% | Done | |
| Deliver main inlet valves to site | 26 Nov 2025 | 02 Jan 2026 | Procurement Lead | 100% | Done | |
| Install main inlet valve: Unit 1 | 30 Jul 2027 | 19 Aug 2027 | Site Superintendent | 0% | Not started | |
| Install main inlet valve: Unit 2 | 20 Aug 2027 | 09 Sep 2027 | Site Superintendent | 0% | Not started | |
| Install main inlet valve: Unit 3 | 10 Sep 2027 | 30 Sep 2027 | Site Superintendent | 0% | Not started | |
| Manufacture and deliver powerhouse overhead crane | 22 Jul 2025 | 04 Nov 2025 | Mechanical Design Lead | 100% | Done | |
| Install and load test overhead crane | 11 Sep 2026 | 16 Oct 2026 | Site Superintendent | 0% | Not started | |
| Install draft tube liner and embedded parts: Unit 1 | 26 Oct 2026 | 13 Nov 2026 | Site Superintendent | 0% | Not started | |
| Install spiral case: Unit 1 | 16 Nov 2026 | 11 Dec 2026 | Site Superintendent | 0% | Not started | |
| Install turbine runner and shaft: Unit 1 | 14 Dec 2026 | 20 Jan 2027 | Site Superintendent | 0% | Not started | |
| Install generator stator and rotor: Unit 1 | 21 Jan 2027 | 04 Mar 2027 | Site Superintendent | 0% | Not started | |
| Install auxiliary piping and systems: Unit 1 | 21 Jan 2027 | 04 Mar 2027 | Site Superintendent | 0% | Not started | |
| Milestone: Unit 1 mechanically complete | 12 Apr 2027 | 12 Apr 2027 | Site Superintendent | — | Not started | |
| Install draft tube liner and embedded parts: Unit 2 | 14 Dec 2026 | 06 Jan 2027 | Site Superintendent | 0% | Not started | |
| Install spiral case: Unit 2 | 07 Jan 2027 | 04 Feb 2027 | Site Superintendent | 0% | Not started | |
| Install turbine runner and shaft: Unit 2 | 05 Feb 2027 | 11 Mar 2027 | Site Superintendent | 0% | Not started | |
| Install generator stator and rotor: Unit 2 | 12 Mar 2027 | 26 Apr 2027 | Site Superintendent | 0% | Not started | |
| Install auxiliary piping and systems: Unit 2 | 12 Mar 2027 | 26 Apr 2027 | Site Superintendent | 0% | Not started | |
| Milestone: Unit 2 mechanically complete | 31 May 2027 | 31 May 2027 | Site Superintendent | — | Not started | |
| Install draft tube liner and embedded parts: Unit 3 | 05 Feb 2027 | 25 Feb 2027 | Site Superintendent | 0% | Not started | |
| Install spiral case: Unit 3 | 26 Feb 2027 | 25 Mar 2027 | Site Superintendent | 0% | Not started | |
| Install turbine runner and shaft: Unit 3 | 30 Mar 2027 | 03 May 2027 | Site Superintendent | 0% | Not started | |
| Install generator stator and rotor: Unit 3 | 04 May 2027 | 15 Jun 2027 | Site Superintendent | 0% | Not started | |
| Install auxiliary piping and systems: Unit 3 | 04 May 2027 | 15 Jun 2027 | Site Superintendent | 0% | Not started | |
| Milestone: Unit 3 mechanically complete | 20 Jul 2027 | 20 Jul 2027 | Site Superintendent | — | Not started | |
| Fire detection and protection systems | 26 Oct 2026 | 27 Nov 2026 | Site Superintendent | 0% | Not started | |
| Cooling water and drainage systems | 26 Oct 2026 | 18 Dec 2026 | Site Superintendent | 0% | Not started |
Controls and SCADA7 activities · lead: Controls Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Control system detailed design | 22 Jul 2025 | 01 Sep 2025 | Controls Lead | 100% | Done | |
| Control system hardware manufacture | 02 Sep 2025 | 25 Nov 2025 | Controls Lead | 100% | Done | |
| Control system factory acceptance test | 26 Nov 2025 | 09 Dec 2025 | Quality Manager | 100% | Done | |
| Deliver control system to site | 10 Dec 2025 | 09 Jan 2026 | Procurement Lead | 100% | Done | |
| Install control cabinets and operator room | 26 Oct 2026 | 27 Nov 2026 | Controls Lead | 0% | Not started | |
| Cable installation: control and instrumentation | 30 Nov 2026 | 04 Feb 2027 | Controls Lead | 0% | Not started | |
| Connect SCADA to remote operations centre | 05 Feb 2027 | 18 Mar 2027 | Controls Lead | 0% | Not started |
Environment and Heritage41 activities · lead: Environmental Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Environmental management plan approved | 28 Apr 2025 | 16 May 2025 | Environmental Manager | 100% | Done | |
| Water quality monitoring and report: Q2 2025 | 19 May 2025 | 06 Jun 2025 | Environmental Manager | 100% | Done | |
| Water quality monitoring and report: Q3 2025 | 01 Jul 2025 | 21 Jul 2025 | Environmental Manager | 100% | Done | |
| Water quality monitoring and report: Q4 2025 | 01 Oct 2025 | 22 Oct 2025 | Environmental Manager | 100% | Done | |
| Water quality monitoring and report: Q1 2026 | 02 Jan 2026 | 22 Jan 2026 | Environmental Manager | 100% | Done | |
| Water quality monitoring and report: Q2 2026 | 01 Apr 2026 | 23 Apr 2026 | Environmental Manager | 100% | Done | |
| Water quality monitoring and report: Q3 2026 | 01 Jul 2026 | 21 Jul 2026 | Environmental Manager | 0% | Not started | |
| Water quality monitoring and report: Q4 2026 | 01 Oct 2026 | 22 Oct 2026 | Environmental Manager | 0% | Not started | |
| Water quality monitoring and report: Q1 2027 | 04 Jan 2027 | 22 Jan 2027 | Environmental Manager | 0% | Not started | |
| Water quality monitoring and report: Q2 2027 | 01 Apr 2027 | 21 Apr 2027 | Environmental Manager | 0% | Not started | |
| Water quality monitoring and report: Q3 2027 | 01 Jul 2027 | 21 Jul 2027 | Environmental Manager | 0% | Not started | |
| Water quality monitoring and report: Q4 2027 | 01 Oct 2027 | 22 Oct 2027 | Environmental Manager | 0% | Not started | |
| Water quality monitoring and report: Q1 2028 | 04 Jan 2028 | 24 Jan 2028 | Environmental Manager | 0% | Not started | |
| Erosion and sediment control audit: Q2 2026 | 01 Apr 2026 | 14 Apr 2026 | Environmental Manager | 100% | Done | |
| Erosion and sediment control audit: Q3 2026 | 01 Jul 2026 | 10 Jul 2026 | Environmental Manager | 0% | Not started | |
| Erosion and sediment control audit: Q4 2026 | 01 Oct 2026 | 13 Oct 2026 | Environmental Manager | 0% | Not started | |
| Erosion and sediment control audit: Q1 2027 | 04 Jan 2027 | 13 Jan 2027 | Environmental Manager | 0% | Not started | |
| Erosion and sediment control audit: Q2 2027 | 01 Apr 2027 | 12 Apr 2027 | Environmental Manager | 0% | Not started | |
| Erosion and sediment control audit: Q3 2027 | 01 Jul 2027 | 12 Jul 2027 | Environmental Manager | 0% | Not started | |
| Erosion and sediment control audit: Q4 2027 | 01 Oct 2027 | 13 Oct 2027 | Environmental Manager | 0% | Not started | |
| Fish passage design | 28 Apr 2025 | 06 Jun 2025 | Environmental Manager | 100% | Done | |
| Construct fish passage | 10 Mar 2026 | 13 May 2026 | Civil Package Manager | 71% | In progress | |
| Fish passage testing and sign-off | 14 May 2026 | 03 Jun 2026 | Environmental Manager | 0% | Not started | |
| Revegetation plan | 19 May 2025 | 30 May 2025 | Environmental Manager | 100% | Done | |
| Revegetation stage 1: construction areas | 02 Sep 2025 | 29 Sep 2025 | Environmental Manager | 100% | Done | |
| Revegetation stage 2: spoil areas | 09 Feb 2027 | 08 Mar 2027 | Environmental Manager | 0% | Not started | |
| Final site stabilisation and rehabilitation | 09 Mar 2027 | 14 Apr 2027 | Environmental Manager | 0% | Not started | |
| Pre-construction heritage survey | 05 Mar 2025 | 01 Apr 2025 | Heritage Advisor | 100% | Done | |
| Heritage management plan approved | 28 Apr 2025 | 09 May 2025 | Heritage Advisor | 100% | Done | |
| Record artefacts found at tailrace and secure the area | 16 Mar 2026 | 18 Mar 2026 | Heritage Advisor | 100% | Done | |
| Heritage regulator assessment of tailrace find | 19 Mar 2026 | 15 May 2026 | Heritage Advisor | 25% | In progress | |
| Consult First Nations representatives on management of the find | 19 Mar 2026 | 15 May 2026 | Heritage Advisor | 40% | In progress | |
| Update heritage management plan | 18 May 2026 | 29 May 2026 | Heritage Advisor | 0% | Not started | |
| Milestone: Heritage clearance for tailrace works | 29 May 2026 | 29 May 2026 | Heritage Advisor | — | Not started | |
| Heritage monitoring during remaining tailrace excavation | 01 Jun 2026 | 13 Jul 2026 | Heritage Advisor | 0% | Not started | |
| Community liaison committee meeting and update 1 | 05 May 2025 | 09 May 2025 | Community Liaison Lead | 100% | Done | |
| Community liaison committee meeting and update 2 | 03 Nov 2025 | 07 Nov 2025 | Community Liaison Lead | 100% | Done | |
| Community liaison committee meeting and update 3 | 04 May 2026 | 08 May 2026 | Community Liaison Lead | 0% | Not started | |
| Community liaison committee meeting and update 4 | 02 Nov 2026 | 06 Nov 2026 | Community Liaison Lead | 0% | Not started | |
| Community liaison committee meeting and update 5 | 03 May 2027 | 07 May 2027 | Community Liaison Lead | 0% | Not started | |
| Community liaison committee meeting and update 6 | 01 Nov 2027 | 05 Nov 2027 | Community Liaison Lead | 0% | Not started |
Grid Connection12 activities · lead: Grid Connection Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Lodge AEMO grid connection pre-application | 27 Apr 2026 | 08 May 2026 | Grid Connection Lead | 0% | Not started | |
| AEMO and network provider pre-application response | 11 May 2026 | 28 Sep 2026 | Grid Connection Lead | 0% | Not started | |
| Prepare and submit full connection application | 29 Sep 2026 | 08 Jan 2027 | Grid Connection Lead | 0% | Not started | |
| Connection agreement negotiation | 11 Jan 2027 | 05 Nov 2027 | Grid Connection Lead | 0% | Not started | |
| Generator performance standards agreed | 11 Jan 2027 | 01 Jul 2027 | Grid Connection Lead | 0% | Not started | |
| Milestone: Connection agreement executed | 05 Nov 2027 | 05 Nov 2027 | Grid Connection Lead | — | Not started | |
| Power system model validation | 11 Jan 2027 | 07 Apr 2027 | Grid Connection Lead | 0% | Not started | |
| Milestone: Energisation approval granted | 05 Nov 2027 | 05 Nov 2027 | Grid Connection Lead | — | Not started | |
| Grid code compliance tests: Unit 1 | 22 Nov 2027 | 03 Dec 2027 | Grid Connection Lead | 0% | Not started | |
| Grid code compliance tests: Unit 2 | 13 Dec 2027 | 24 Dec 2027 | Grid Connection Lead | 0% | Not started | |
| Grid code compliance tests: Unit 3 | 06 Jan 2028 | 19 Jan 2028 | Grid Connection Lead | 0% | Not started | |
| Final compliance report to the market operator | 03 Mar 2028 | 15 Mar 2028 | Grid Connection Lead | 0% | Not started |
Commissioning36 activities · lead: Commissioning Manager
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Prepare commissioning plan and test procedures | 12 Jun 2026 | 06 Aug 2026 | Commissioning Manager | 0% | Not started | |
| Commission switchyard and transformer | 04 Aug 2027 | 31 Aug 2027 | Commissioning Manager | 0% | Not started | |
| Commission auxiliary systems | 21 Dec 2026 | 28 Jan 2027 | Commissioning Manager | 0% | Not started | |
| Commission control and SCADA systems | 19 Mar 2027 | 03 May 2027 | Commissioning Manager | 0% | Not started | |
| Inspection and dry checks: Unit 1 | 20 Aug 2027 | 09 Sep 2027 | Commissioning Manager | 0% | Not started | |
| Insulation and protection tests: Unit 1 | 10 Sep 2027 | 23 Sep 2027 | Commissioning Manager | 0% | Not started | |
| Wet commissioning without load: Unit 1 | 24 Sep 2027 | 15 Oct 2027 | Commissioning Manager | 0% | Not started | |
| Inspection and dry checks: Unit 2 | 10 Sep 2027 | 30 Sep 2027 | Commissioning Manager | 0% | Not started | |
| Insulation and protection tests: Unit 2 | 01 Oct 2027 | 15 Oct 2027 | Commissioning Manager | 0% | Not started | |
| Wet commissioning without load: Unit 2 | 18 Oct 2027 | 05 Nov 2027 | Commissioning Manager | 0% | Not started | |
| Inspection and dry checks: Unit 3 | 01 Oct 2027 | 22 Oct 2027 | Commissioning Manager | 0% | Not started | |
| Insulation and protection tests: Unit 3 | 25 Oct 2027 | 05 Nov 2027 | Commissioning Manager | 0% | Not started | |
| Wet commissioning without load: Unit 3 | 08 Nov 2027 | 26 Nov 2027 | Commissioning Manager | 0% | Not started | |
| First synchronisation: Unit 1 | 18 Oct 2027 | 22 Oct 2027 | Commissioning Manager | 0% | Not started | |
| Load rejection and trip tests: Unit 1 | 25 Oct 2027 | 05 Nov 2027 | Commissioning Manager | 0% | Not started | |
| Performance and efficiency tests: Unit 1 | 08 Nov 2027 | 19 Nov 2027 | Commissioning Manager | 0% | Not started | |
| Unit 1 reliability run | 06 Dec 2027 | 05 Jan 2028 | Commissioning Manager | 0% | Not started | |
| Milestone: Unit 1 accepted | 05 Jan 2028 | 05 Jan 2028 | Commissioning Manager | — | Not started | |
| First synchronisation: Unit 2 | 08 Nov 2027 | 12 Nov 2027 | Commissioning Manager | 0% | Not started | |
| Load rejection and trip tests: Unit 2 | 15 Nov 2027 | 26 Nov 2027 | Commissioning Manager | 0% | Not started | |
| Performance and efficiency tests: Unit 2 | 29 Nov 2027 | 10 Dec 2027 | Commissioning Manager | 0% | Not started | |
| Unit 2 reliability run | 29 Dec 2027 | 27 Jan 2028 | Commissioning Manager | 0% | Not started | |
| Milestone: Unit 2 accepted | 27 Jan 2028 | 27 Jan 2028 | Commissioning Manager | — | Not started | |
| First synchronisation: Unit 3 | 29 Nov 2027 | 03 Dec 2027 | Commissioning Manager | 0% | Not started | |
| Load rejection and trip tests: Unit 3 | 06 Dec 2027 | 17 Dec 2027 | Commissioning Manager | 0% | Not started | |
| Performance and efficiency tests: Unit 3 | 20 Dec 2027 | 05 Jan 2028 | Commissioning Manager | 0% | Not started | |
| Unit 3 reliability run | 20 Jan 2028 | 17 Feb 2028 | Commissioning Manager | 0% | Not started | |
| Milestone: Unit 3 accepted | 17 Feb 2028 | 17 Feb 2028 | Commissioning Manager | — | Not started | |
| Whole-station reliability run | 18 Feb 2028 | 02 Mar 2028 | Commissioning Manager | 0% | Not started | |
| Milestone: Commercial operations date | 15 Mar 2028 | 15 Mar 2028 | Project Director | — | Not started | |
| Final handover and close-out | 16 Mar 2028 | 29 Mar 2028 | Project Director | 0% | Not started | |
| Milestone: Defects liability period starts | 29 Mar 2028 | 29 Mar 2028 | Project Director | — | Not started | |
| Operations and maintenance manuals | 01 Mar 2027 | 25 May 2027 | Commissioning Manager | 0% | Not started | |
| Final as-built drawings | 25 Oct 2027 | 17 Dec 2027 | Design Manager | 0% | Not started | |
| Operator training | 18 Oct 2027 | 10 Dec 2027 | Commissioning Manager | 0% | Not started | |
| Spares and special tools delivered | 21 Jul 2027 | 31 Aug 2027 | Procurement Lead | 0% | Not started |
Critical pathFrom the schedule export
The critical path in the export runs from Section 3: TBM drive through the remaining tunnel sections, lining, penstock and unit installations, then commissioning and acceptance of each unit, to Commercial operations date, with negative float at every stage (-47 days). The grid connection chain (MHU.5.1) is not drawn into it because the dates do not respect the link from the energisation approval to Unit 1 synchronisation. The corrected scenario below honours that link and moves commercial operations to 5 Apr 2028. It is a model, not the source schedule.
Sequence: 38 stages, read left to right and top to bottom. Critical activities are counted separately, as the longest path covers more tasks than the stages shown.
Critical path sequence
Critical task detail
| WBS | Task | Duration | Planned finish | Forecast | Owner | |
|---|---|---|---|---|---|---|
| MHU.2.4.17 | Section 3: TBM drive Alert | 87d | 27 May 2026 | 03 Aug 2026 | -47d | Tunnelling Manager |
| MHU.2.4.18 | Section 3: ground support and segment lining | 10d | 11 Jun 2026 | 17 Aug 2026 | -47d | Tunnelling Manager |
| MHU.2.4.19 | Section 3: grouting and survey check | 5d | 18 Jun 2026 | 24 Aug 2026 | -47d | Tunnelling Manager |
| MHU.2.4.20 | ◆ Section 3 complete | — | 18 Jun 2026 | 24 Aug 2026 | -47d | Tunnelling Manager |
| MHU.2.4.21 | Section 4: set up and survey | 5d | 25 Jun 2026 | 31 Aug 2026 | -47d | Tunnelling Manager |
| MHU.2.4.22 | Section 4: TBM drive | 40d | 20 Aug 2026 | 27 Oct 2026 | -47d | Tunnelling Manager |
| MHU.2.4.23 | Section 4: ground support and segment lining | 10d | 03 Sep 2026 | 10 Nov 2026 | -47d | Tunnelling Manager |
| MHU.2.4.24 | Section 4: grouting and survey check | 5d | 10 Sep 2026 | 17 Nov 2026 | -47d | Tunnelling Manager |
| MHU.2.4.25 | ◆ Section 4 complete | — | 10 Sep 2026 | 17 Nov 2026 | -47d | Tunnelling Manager |
| MHU.2.4.26 | Section 5: set up and survey | 5d | 17 Sep 2026 | 24 Nov 2026 | -47d | Tunnelling Manager |
| MHU.2.4.27 | Section 5: TBM drive | 35d | 06 Nov 2026 | 15 Jan 2027 | -47d | Tunnelling Manager |
| MHU.2.4.28 | Section 5: ground support and segment lining | 10d | 20 Nov 2026 | 01 Feb 2027 | -47d | Tunnelling Manager |
| MHU.2.4.29 | Section 5: grouting and survey check | 5d | 27 Nov 2026 | 08 Feb 2027 | -47d | Tunnelling Manager |
| MHU.2.4.30 | ◆ Section 5 complete | — | 27 Nov 2026 | 08 Feb 2027 | -47d | Tunnelling Manager |
| MHU.2.4.31 | ◆ TBM breakthrough at powerhouse | — | 27 Nov 2026 | 08 Feb 2027 | -47d | Tunnelling Manager |
| MHU.2.4.32 | Tunnel final concrete lining | 30d | 13 Jan 2027 | 22 Mar 2027 | -47d | Tunnelling Manager |
| MHU.2.4.33 | Install steel penstock liner | 45d | 18 Mar 2027 | 26 May 2027 | -47d | Tunnelling Manager |
| MHU.2.4.34 | Penstock pressure test | 10d | 05 Apr 2027 | 09 Jun 2027 | -47d | Tunnelling Manager |
| MHU.2.4.35 | Penstock flushing, cleaning and inspection | 15d | 26 Apr 2027 | 01 Jul 2027 | -47d | Tunnelling Manager |
| MHU.2.4.36 | Install penstock instrumentation and monitoring | 20d | 24 May 2027 | 29 Jul 2027 | -47d | Tunnelling Manager |
| MHU.2.4.37 | ◆ Penstock complete | — | 24 May 2027 | 29 Jul 2027 | -47d | Tunnelling Manager |
| MHU.3.1.3 | Electrical design review: 330kV and generator protection | 50d | 30 Mar 2026 | 13 May 2026 | -15d | Electrical Design Lead |
| MHU.3.3.6 | Install main inlet valve: Unit 1 | 15d | 15 Jun 2027 | 19 Aug 2027 | -47d | Site Superintendent |
| MHU.3.3.7 | Install main inlet valve: Unit 2 | 15d | 06 Jul 2027 | 09 Sep 2027 | -47d | Site Superintendent |
| MHU.3.3.8 | Install main inlet valve: Unit 3 | 15d | 27 Jul 2027 | 30 Sep 2027 | -47d | Site Superintendent |
| MHU.3.5.4 | Place order for 330kV generator transformer | 5d | 08 Apr 2026 | 20 May 2026 | -15d | Transformer Package Lead |
| MHU.3.5.5 | Manufacture 330kV generator transformer | 200d | 20 Jan 2027 | 04 Mar 2027 | -15d | Transformer Package Lead |
| MHU.3.5.6 | Transformer factory acceptance test | 15d | 11 Feb 2027 | 25 Mar 2027 | -15d | Quality Manager |
| MHU.3.5.7 | Ship transformer to site | 30d | 25 Mar 2027 | 10 May 2027 | -15d | Procurement Lead |
| MHU.3.5.8 | Deliver and position transformer on plinth | 10d | 12 Apr 2027 | 24 May 2027 | -15d | Site Superintendent |
| MHU.3.5.9 | Transformer installation, oil fill and settling | 30d | 24 May 2027 | 06 Jul 2027 | -15d | Site Superintendent |
| MHU.3.5.10 | Transformer site tests | 20d | 22 Jun 2027 | 03 Aug 2027 | -15d | Electrical Design Lead |
| MHU.3.5.11 | ◆ Transformer ready for energisation | — | 22 Jun 2027 | 03 Aug 2027 | -15d | Transformer Package Lead |
| MHU.4.1.13 | Water quality monitoring and report: Q1 2028 | 15d | 24 Jan 2028 | 24 Jan 2028 | -11d | Environmental Manager |
| MHU.5.1.1 | Lodge AEMO grid connection pre-application | 10d | 13 Feb 2026 | 08 May 2026 | -62d | Grid Connection Lead |
| MHU.5.1.2 | AEMO and network provider pre-application response | 100d | 08 Jul 2026 | 28 Sep 2026 | -62d | Grid Connection Lead |
| MHU.5.1.3 | Prepare and submit full connection application | 70d | 15 Oct 2026 | 08 Jan 2027 | -62d | Grid Connection Lead |
| MHU.5.1.4 | Connection agreement negotiation | 210d | 05 Jul 2027 | 05 Nov 2027 | -62d | Grid Connection Lead |
| MHU.5.1.6 | ◆ Connection agreement executed | — | 05 Jul 2027 | 05 Nov 2027 | -62d | Grid Connection Lead |
| MHU.5.1.8 | ◆ Energisation approval granted Alert | — | 05 Jul 2027 | 05 Nov 2027 | -62d | Grid Connection Lead |
| MHU.5.2.2 | Commission switchyard and transformer | 20d | 20 Jul 2027 | 31 Aug 2027 | -15d | Commissioning Manager |
| MHU.5.2.5 | Inspection and dry checks: Unit 1 | 15d | 06 Jul 2027 | 09 Sep 2027 | -47d | Commissioning Manager |
| MHU.5.2.6 | Insulation and protection tests: Unit 1 | 10d | 20 Jul 2027 | 23 Sep 2027 | -47d | Commissioning Manager |
| MHU.5.2.7 | Wet commissioning without load: Unit 1 | 15d | 10 Aug 2027 | 15 Oct 2027 | -47d | Commissioning Manager |
| MHU.5.2.8 | Inspection and dry checks: Unit 2 | 15d | 27 Jul 2027 | 30 Sep 2027 | -47d | Commissioning Manager |
| MHU.5.2.9 | Insulation and protection tests: Unit 2 | 10d | 10 Aug 2027 | 15 Oct 2027 | -47d | Commissioning Manager |
| MHU.5.2.10 | Wet commissioning without load: Unit 2 | 15d | 31 Aug 2027 | 05 Nov 2027 | -47d | Commissioning Manager |
| MHU.5.2.11 | Inspection and dry checks: Unit 3 | 15d | 17 Aug 2027 | 22 Oct 2027 | -47d | Commissioning Manager |
| MHU.5.2.12 | Insulation and protection tests: Unit 3 | 10d | 31 Aug 2027 | 05 Nov 2027 | -47d | Commissioning Manager |
| MHU.5.2.13 | Wet commissioning without load: Unit 3 | 15d | 21 Sep 2027 | 26 Nov 2027 | -47d | Commissioning Manager |
| MHU.5.3.1 | First synchronisation: Unit 1 Alert | 5d | 17 Aug 2027 | 22 Oct 2027 | -47d | Commissioning Manager |
| MHU.5.3.2 | Load rejection and trip tests: Unit 1 | 10d | 31 Aug 2027 | 05 Nov 2027 | -47d | Commissioning Manager |
| MHU.5.3.3 | Performance and efficiency tests: Unit 1 | 10d | 14 Sep 2027 | 19 Nov 2027 | -17d | Commissioning Manager |
| MHU.5.3.4 | Grid code compliance tests: Unit 1 | 10d | 28 Sep 2027 | 03 Dec 2027 | -17d | Grid Connection Lead |
| MHU.5.3.5 | Unit 1 reliability run | 20d | 27 Oct 2027 | 05 Jan 2028 | -17d | Commissioning Manager |
| MHU.5.3.6 | ◆ Unit 1 accepted | — | 27 Oct 2027 | 05 Jan 2028 | -17d | Commissioning Manager |
| MHU.5.3.7 | First synchronisation: Unit 2 | 5d | 07 Sep 2027 | 12 Nov 2027 | -47d | Commissioning Manager |
| MHU.5.3.8 | Load rejection and trip tests: Unit 2 | 10d | 21 Sep 2027 | 26 Nov 2027 | -47d | Commissioning Manager |
| MHU.5.3.9 | Performance and efficiency tests: Unit 2 | 10d | 06 Oct 2027 | 10 Dec 2027 | -32d | Commissioning Manager |
| MHU.5.3.10 | Grid code compliance tests: Unit 2 | 10d | 20 Oct 2027 | 24 Dec 2027 | -32d | Grid Connection Lead |
| MHU.5.3.11 | Unit 2 reliability run | 20d | 17 Nov 2027 | 27 Jan 2028 | -32d | Commissioning Manager |
| MHU.5.3.12 | ◆ Unit 2 accepted | — | 17 Nov 2027 | 27 Jan 2028 | -32d | Commissioning Manager |
| MHU.5.3.13 | First synchronisation: Unit 3 | 5d | 28 Sep 2027 | 03 Dec 2027 | -47d | Commissioning Manager |
| MHU.5.3.14 | Load rejection and trip tests: Unit 3 | 10d | 13 Oct 2027 | 17 Dec 2027 | -47d | Commissioning Manager |
| MHU.5.3.15 | Performance and efficiency tests: Unit 3 | 10d | 27 Oct 2027 | 05 Jan 2028 | -47d | Commissioning Manager |
| MHU.5.3.16 | Grid code compliance tests: Unit 3 | 10d | 10 Nov 2027 | 19 Jan 2028 | -47d | Grid Connection Lead |
| MHU.5.3.17 | Unit 3 reliability run | 20d | 08 Dec 2027 | 17 Feb 2028 | -47d | Commissioning Manager |
| MHU.5.3.18 | ◆ Unit 3 accepted | — | 08 Dec 2027 | 17 Feb 2028 | -47d | Commissioning Manager |
| MHU.5.4.1 | Whole-station reliability run | 10d | 22 Dec 2027 | 02 Mar 2028 | -47d | Commissioning Manager |
| MHU.5.4.2 | Final compliance report to the market operator | 9d | 07 Jan 2028 | 15 Mar 2028 | -47d | Grid Connection Lead |
| MHU.5.4.3 | ◆ Commercial operations date | — | 07 Jan 2028 | 15 Mar 2028 | -47d | Project Director |
All 71 critical activities are shown. This table is not curated or capped.
Dependency-corrected scenarioModelled, not a forecast
If First synchronisation: Unit 1 waits for the energisation approval (MHU.5.1.6, 5 Nov 2027), synchronisation starts 8 Nov 2027 instead of 18 Oct 2027. Commercial operations moves 15 working days to 5 Apr 2028, which is 62 working days after the approved baseline (7 Jan 2028).
| WBS | Driving chain | In the export | Corrected | Shift (working days) |
|---|---|---|---|---|
| MHU.5.1.8 | ◆ Energisation approval granted | 2027-11-05 | 2027-11-05 | no change |
| MHU.5.3.1 | First synchronisation: Unit 1 | 2027-10-22 | 2027-11-12 | +15d |
| MHU.5.3.2 | Load rejection and trip tests: Unit 1 | 2027-11-05 | 2027-11-26 | +15d |
| MHU.5.3.7 | First synchronisation: Unit 2 | 2027-11-12 | 2027-12-03 | +15d |
| MHU.5.3.8 | Load rejection and trip tests: Unit 2 | 2027-11-26 | 2027-12-17 | +15d |
| MHU.5.3.13 | First synchronisation: Unit 3 | 2027-12-03 | 2027-12-24 | +15d |
| MHU.5.3.14 | Load rejection and trip tests: Unit 3 | 2027-12-17 | 2028-01-12 | +15d |
| MHU.5.3.15 | Performance and efficiency tests: Unit 3 | 2028-01-05 | 2028-01-27 | +15d |
| MHU.5.3.16 | Grid code compliance tests: Unit 3 | 2028-01-19 | 2028-02-10 | +15d |
| MHU.5.3.17 | Unit 3 reliability run | 2028-02-17 | 2028-03-09 | +15d |
| MHU.5.3.18 | ◆ Unit 3 accepted | 2028-02-17 | 2028-03-09 | +15d |
| MHU.5.4.1 | Whole-station reliability run | 2028-03-02 | 2028-03-23 | +15d |
| MHU.5.4.2 | Final compliance report to the market operator | 2028-03-15 | 2028-04-05 | +15d |
| MHU.5.4.3 | ◆ Commercial operations date | 2028-03-15 | 2028-04-05 | +15d |
Modelled. Only the energisation-to-synchronisation link is honoured. 24 of 292 activities move, all downstream of Unit 1 synchronisation. Finish-to-start, no lag, no pulling earlier, no resource or contingency changes. The 15 working days equal the 15-day overlap, because the duration of the work behind synchronisation is unchanged.
Near-critical tasks
Draft tube and scroll case concrete: Unit 25 working days of float
Draft tube and scroll case concrete: Unit 35 working days of float
Powerhouse structure to roof5 working days of float
Powerhouse roof, cladding and weatherproofing5 working days of float
Milestone: Powerhouse watertight5 working days of float
Install draft tube liner and embedded parts: Unit 15 working days of float
Install spiral case: Unit 15 working days of float
Install draft tube liner and embedded parts: Unit 25 working days of float
Install spiral case: Unit 25 working days of float
Install draft tube liner and embedded parts: Unit 35 working days of float
Install spiral case: Unit 35 working days of float
Install turbine runner and shaft: Unit 35 working days of float
Install generator stator and rotor: Unit 35 working days of float
Install auxiliary piping and systems: Unit 35 working days of float
Install power and control cabling: Unit 35 working days of float
Milestone: Unit 3 mechanically complete5 working days of float
Install and load test overhead crane10 working days of float
Float distribution
How this was calculatedAssumptions and limits
- Source. Every date, percentage, float and comment comes from the schedule export at the 27 Apr 2026 status date. Cherry adds only labelled calculations, scenarios and recommendations.
- Links. The export lists predecessors by row ID and treats every link as finish-to-start. It has no lag, constraint or link-type column, so none is assumed. A task starts the next working day after its predecessor finishes; a milestone may share its predecessor's date.
- Calendar. Working days are Monday to Friday excluding an illustrative NSW public-holiday list. The export names the list but does not contain it, so Cherry cannot verify it.
- Float. The export's Total Float is working days to the approved completion date (the baseline finish of Commercial operations date). Cherry recomputed it independently for the 165 incomplete activities that carry a float value. It is a hybrid: the backward pass honours the violated link while the dates do not re-propagate, which is why the grid chain reads -62 and the tunnelling chain -47.
- Corrected scenario. Honours the violated link, pushes the successor later, recomputes finishes from working-day durations and propagates. It never pulls work earlier and does not model resources, contingency or acceleration.
- % of time remaining. Modelled shift (15 working days) divided by 478 working days from the status date to the as-dated commercial operations date.
- Progress. Overall 48% is duration-weighted across activities (a milestone counts as one day). Planned 51% applies the same weights to baseline dates at the status date. Phase and workstream percentages use the same method.
- Near-critical. A fixed 1 to 10 working days. At this project's remaining duration a proportional threshold of 5 percent would be about 24 days, so the count is sensitive to the rule.
- Workstream status. At risk = any incomplete task with negative float. Watch = no negative float but a task marked Delayed. Otherwise Complete, Not started or On plan.
- Not assessed. Cost, resources, hard constraints, link types and lag.
Meridian Hydropower Upgrade is a fictional project, built to show how Cherry reads a project schedule export. It does not describe a real project, regulator, utility or project team, and no real organisation has used or endorsed Cherry for it.