CherryProject Intelligence

Nexus Bank: Core Banking Migration

CRITICAL: Integration build is understaffed and go-live is dated 80 working days after baseline
ProAs at 27 Apr 2026
Executive snapshot · Critical

The integration build is understaffed and running behind, and the dependency chain behind it moves go-live from 15 Mar 2027 to 8 Jul 2027. Recovery is possible if integration capacity is approved now.

  • 1Integration build is behind, with 129 of 340 critical integrations unassigned. Third-party integrations are 8% complete and forecast to finish 17 Dec 2026, against a baseline of 26 Aug 2026.
  • 2Go-live is dated 8 Jul 2027, 80 working days after the 15 Mar 2027 baseline, because system integration testing, user acceptance and the three month parallel run all follow the integration build.
  • 3The immediate decision is whether to approve external integration specialists, estimated in source comments at $4M to $6M, before the integration gap moves go-live further.
80d
Go-live behind baseline
15 Mar 2027 baseline, 8 Jul 2027 as dated · working days
129
Integrations unassigned
Of 340 on the critical path · three engineers resigned in Q1
41%
Overall progress
58% planned at the status date

Schedule outlook

Go-live baseline
15 Mar 2027
Go-live as dated
8 Jul 2027
Variance
80 working days

The integration build is driving the variance. The three month parallel run is fixed, so a late integration build moves go-live rather than shortening the testing behind it. End of hypercare moves from 22 Jun 2027 to 13 Oct 2027.

Critical pathZero or negative float from Integrate third parties: insurance and wealth partners to Hypercare complete

CBM.2.6.6Integrate third parties: insurance and wealth partners-80d float
→
CBM.2.6.11Integration build quality gate-80d float
→
CBM.4.2.1SIT cycle 1: core platform and channels-80d float
→
CBM.4.2.2SIT cycle 2: payments and internal systems-80d float
→
CBM.4.3.1UAT preparation and business user training-80d float
→
CBM.4.3.2UAT cycle 1: retail banking-80d float
→
CBM.4.3.3UAT cycle 2: business banking and payments-80d float
→
CBM.4.3.4UAT exit approved-80d float
→
CBM.4.4.2Parallel run: daily reconciliation reporting-80d float
→
CBM.4.4.3Parallel run exit review and reconciliation sign-off-80d float
→
CBM.4.4.4Parallel run exit approved-80d float
→
CBM.6.1.7Go and no-go decision-80d float
→
CBM.6.2.1Cutover weekend: production migration and switch-80d float
→
CBM.6.2.2GO-LIVE: Core Banking Migration-80d float
→
CBM.6.3.3Maintain rollback capability-80d float
→
CBM.6.3.9Decommission legacy platform-80d float
→
CBM.6.3.10Post-implementation review-80d float
→
CBM.6.3.11Hypercare complete-80d float

The longest as-dated path runs from the integration build through SIT, UAT and the parallel run to go-live and the end of hypercare, through 18 activities. Every stage carries -80 working days of float.

Delivery roadmapAs at 27 Apr 2026

Jan 2025 to Dec 2027 · schedule exportOpenGo-live
Q1 2025
Q3 2025
Q1 2026
Q3 2026
Q1 2027
Q3 2027
TODAY
CPS 234 pre-cutover notification lodged

01 Sep 2026
SIT exit approved

25 Feb 2027
GO-LIVE: Core Banking Migration

08 Jul 2027
Hypercare complete

13 Oct 2027
P1
Discovery, Architecture and Vendor Selection
06 Jan 2025 to 30 Jun 2025 · 100% complete
Complete. Temenos T24 contracted and Deloitte Digital engaged. 1,247 integrations catalogued, 340 classified critical path.
100%
P2
Build, Configure and IntegrationAT RISK
01 Jul 2025 to 23 Dec 2026 · 42% complete
Integration build behind · 129 of 340 critical integrations unassigned
42% complete. Integration build is behind. Third-party integrations are 8% complete and 129 of 340 critical integrations have no developer. Dated finish 23 Dec 2026 against a baseline of 30 Sep 2026.
42%
P3
Customer Data Migration
01 Jul 2025 to 06 Nov 2026 · 47% complete
47% complete. 340,000 data anomalies were found in the quality audit. Duplicate account remediation is six weeks behind.
47%
P4
Testing and Parallel RunAT RISK
02 Feb 2026 to 02 Jul 2027 · 10% complete
SIT start 80 working days after baseline
10% complete. Test planning is under way. System integration testing is dated to start 24 Dec 2026, against a baseline of 2 Sep 2026, because it follows the integration build.
10%
P5
Regulatory and Compliance (APRA CPS 234)AT RISK
15 Jan 2025 to 30 Jun 2027 · 33% complete
Pre-cutover notification not lodged
33% complete. The CPS 234 pre-cutover notification is not lodged and is dated 1 Sep 2026.
33%
P6
Cutover and Hypercare
14 Apr 2027 to 13 Oct 2027 · 0% complete
Not started. Begins 14 Apr 2027. Go-live is dated 8 Jul 2027.
0%

APRA CPS 234 requires notification before cutover. The notification, the integration build and the three month parallel run all set the go-live date.

Decisions required

Decision 1

Integration capacity shortfall pushes go-live out and needs external specialists

Requested: Approve engagement of external integration specialists (4 to 6 FTE for three months, per the source comment on CBM.2.6.1) to close the 129 integrations with no developer. Third-party integrations finish 17 Dec 2026 at the current velocity of three engineers.

Recommended: Approve this week. Integration build quality gate (CBM.2.6.11) is dated 23 Dec 2026, 80 working days after baseline, and SIT, UAT and the parallel run follow it with no buffer.

AuthorityBoard / Investment Committee
Needed byThis week

If not decided: Go-live stays at 8 Jul 2027 or later, and every further week of delay on integration moves go-live and the end of hypercare (13 Oct 2027) by the same amount.

Est. $4M to $6M (source comment)Linked: Risk 1Linked: Recommended Action 1Source: CBM.2.6.1 (ID 97), CBM.2.6.11 (ID 107)
Decision 2

Proactive APRA engagement needs endorsement ahead of the CPS 234 notification

Requested: Endorse briefing APRA on the delay and recovery plan now. Proactive APRA delay briefing (CBM.5.1.3) is in the schedule at 0% and not yet held, and the CPS 234 pre-cutover notification (CBM.5.1.5) is dated 1 Sep 2026.

Recommended: Endorse early engagement this month, before the notification is prepared (dated to start 1 Jul 2026).

AuthorityCRO / Board Risk Committee
Needed byThis month

If not decided: The notification would reach APRA without prior context, with less room to discuss timing.

Linked: Risk 2Linked: Recommended Action 2Source: CBM.5.1.3 (ID 164), CBM.5.1.4 (ID 165), CBM.5.1.5 (ID 166)
Upcoming decisionRecovery or rebaseline will be required after the integration capacity decision.

What could change the outcome

The top risks that could move this outlook. A preview of the full Risk Analysis tab.

SeverityRisk
Critical risk
Integration capacity

129 of 340 critical integrations have no developer. Third-party integrations finish 17 Dec 2026, against a baseline of 26 Aug 2026.

High risk
APRA notification

The CPS 234 pre-cutover notification is not lodged and is dated 1 Sep 2026. The APRA delay briefing has not been held.

High risk
Parallel run compresses the schedule

The three month parallel run is fixed, so each week of integration delay moves go-live by a week. Go-live is 80 working days behind baseline.

View all 5 risks →

Workstream health

WorkstreamCompletePositionStatus
Program Management83%1 with negative floatAt risk
Integration36%12 delayed, 13 with negative floatAt risk
Regulatory and Compliance38%3 with negative floatAt risk
Data Migration47%1 delayed, 1 with negative floatAt risk
Infrastructure and Security82%On planOn plan
Core Platform59%1 delayedWatch
Testing11%19 with negative floatAt risk
Change and Communications0%1 with negative floatAt risk
Cutover and Hypercare0%15 with negative floatAt risk
Data confidence: High · Refreshed 27 Apr 2026 · Owners missing on 11 activities
  • Dependency links run through the whole project, so float and the critical path are calculated from schedule logic. No task is dated before the work it depends on.
  • 11 of 182 activities have no owner: the APRA regulatory reporting feeds and the ten third-party integration packages. Source comments say these have no developer assigned, and Cherry reports them as Not assigned.
  • The export holds no resource assignments or capacity. The $4M to $6M cost and the 4 to 6 FTE figure come from a source comment and cannot be checked against a plan or budget.
Delivery overview

Discovery and vendor selection are complete. Build is 42% complete and the integration build is where the delay sits: third-party integrations are 8% complete with 129 critical integrations unassigned.

  • 1Phase 1 is complete. Temenos T24 is selected and contracted.
  • 2Phase 2 is understaffed on the integration build, the largest driver of delay. The quality gate is dated 23 Dec 2026, 80 working days after baseline.
  • 3Phase 4 follows the integration build with no buffer. The parallel run is fixed at three months, so upstream delay moves go-live (8 Jul 2027) rather than shortening testing.
42%
Phase 2 complete
129
Integrations unassigned
340K
Data anomalies to remediate
10%
Phase 4 complete

PhasesSelect a phase to expand

Current state assessment100%
Lead: R. Singh · Jan '25 → Apr '25
Target architecture100%
Lead: T. Rao · Feb '25 → May '25
Vendor selection100%
Lead: Procurement Lead · Mar '25 → Jun '25
All 3 packages complete.
Environments and platform foundation90%
Lead: Infrastructure Lead · Jul '25 → May '26
Program controls70%
Lead: S. Okafor · Jul '25 → Jul '26
Core platform configuration59%
Lead: Temenos Configuration Lead · Sep '25 → Nov '26
Integration build: channels and core55%
Lead: V. Chakraborty · Aug '25 → Sep '26
Integration build: internal systems68%
Lead: Integration Lead · Nov '25 → May '26
Integration build: third-party8%
Lead: Vacant · Sep '25 → Dec '26
Third-party integrations are 8% complete. 129 of 340 critical integrations have no assigned developer, and three senior engineers (L. Obi, T. Ferreira, A. Park) resigned in Q1. The integration build quality gate (CBM.2.6.11) is dated 23 Dec 2026.
Data analysis and quality91%
Lead: A. Osei · Jul '25 → May '26
Remediation and tooling31%
Lead: A. Osei · Sep '25 → Sep '26
Migration rehearsals24%
Lead: A. Osei · Feb '26 → Nov '26
Duplicate account remediation (180K accounts) is six weeks behind and finishes 8 Sep 2026. It has 90 working days of float in the export, so it is not driving go-live today.
Test preparation19%
Lead: L. Ferreira · Feb '26 → Sep '26
System integration testing (SIT)0%
Lead: L. Ferreira · Dec '26 → Feb '27
User acceptance testing (UAT)0%
Lead: L. Ferreira · Feb '27 → Apr '27
Parallel run0%
Lead: S. Okafor · Apr '27 → Jul '27
SIT is dated to start 24 Dec 2026, 80 working days after baseline. SIT, UAT and the three month parallel run follow in sequence, and go-live follows the parallel run.
Notifications43%
Lead: M. Andersen · Jan '25 → Jun '27
Quarterly APRA reporting50%
Lead: M. Andersen · Jul '25 → Apr '27
Customer regulatory communications0%
Lead: K. Barrett · May '26 → Dec '26
The CPS 234 pre-cutover notification is not lodged and is dated 1 Sep 2026. The APRA delay briefing and the customer communications plan (8 weeks) have not started.
Cutover preparation0%
Lead: S. Okafor · Apr '27 → Jul '27
Cutover and go-live0%
Lead: S. Okafor · Jul '27 → Jul '27
Hypercare0%
Lead: S. Okafor · Jul '27 → Oct '27
Not started. Begins 14 Apr 2027. Go-live is dated 8 Jul 2027.

ScheduleAs at 27 Apr 2026

CRITICAL overall. 41% complete against 58% planned. Go-live is dated 8 Jul 2027, 80 working days after baseline. 129 critical integrations are unassigned and the CPS 234 notification is not lodged.
Status
WBSTask%StartFinishForecastOwnerStatusComments
CBMNexus Bank: Core Banking Migration41%06 Jan 202522 Jun 202713 Oct 2027S. OkaforIn progress
CBM.1Phase 1: Discovery, Architecture and Vendor Selection100%06 Jan 202530 Jun 202530 Jun 2025 ✓S. OkaforDone
CBM.1.1Current state assessment100%06 Jan 202514 Apr 202514 Apr 2025 ✓R. SinghDone
CBM.1.1.1Program mobilisation and governance set-up100%06 Jan 202517 Jan 202517 Jan 2025 ✓S. OkaforDone
CBM.1.1.2Interview business and IT stakeholders100%20 Jan 202510 Feb 202510 Feb 2025 ✓R. SinghDone
CBM.1.1.3Catalogue existing integrations100%20 Jan 202510 Mar 202510 Mar 2025 ✓R. SinghDone
1,247 integrations catalogued.
CBM.1.1.4Classify integrations by criticality100%11 Mar 202524 Mar 202524 Mar 2025 ✓R. SinghDone
340 classified critical path. 50 classified decommission. 857 standard migration.
CBM.1.1.5Current state assessment report100%25 Mar 202531 Mar 202531 Mar 2025 ✓R. SinghDone
CBM.1.1.6Business capability workshops100%20 Jan 202510 Feb 202510 Feb 2025 ✓R. SinghDone
CBM.1.1.7Regulatory obligations mapping (CPS 234 and CPS 230)100%11 Feb 202503 Mar 202503 Mar 2025 ✓K. BarrettDone
CBM.1.1.8Data landscape assessment100%20 Jan 202517 Feb 202517 Feb 2025 ✓A. OseiDone
CBM.1.1.9Infrastructure and security baseline assessment100%20 Jan 202510 Feb 202510 Feb 2025 ✓Security ArchitectDone
CBM.1.1.10Program business case and funding approval100%01 Apr 202514 Apr 202514 Apr 2025 ✓S. OkaforDone
CBM.1.1.11Program risk and issue register established100%20 Jan 202524 Jan 202524 Jan 2025 ✓S. OkaforDone
CBM.1.2Target architecture100%11 Feb 202526 May 202526 May 2025 ✓T. RaoDone
CBM.1.2.1Define architecture principles and capability map100%11 Feb 202526 Feb 202526 Feb 2025 ✓T. RaoDone
CBM.1.2.2Target architecture design: Temenos T24 on Azure100%27 Feb 202505 May 202505 May 2025 ✓Deloitte DigitalDone
CBM.1.2.3Security and resilience review of target architecture100%06 May 202521 May 202521 May 2025 ✓Security ArchitectDone
Two days late because of the security review. No impact on the program.
CBM.1.2.4Architecture board approval100%22 May 202526 May 202526 May 2025 ✓T. RaoDone
CBM.1.2.5Milestone: Target architecture approved—26 May 202526 May 202526 May 2025 ✓T. RaoDone
CBM.1.3Vendor selection100%25 Mar 202530 Jun 202530 Jun 2025 ✓Procurement LeadDone
CBM.1.3.1Prepare request for proposal100%25 Mar 202507 Apr 202507 Apr 2025 ✓Procurement LeadDone
CBM.1.3.2Vendor responses and demonstrations100%08 Apr 202508 May 202508 May 2025 ✓Procurement LeadDone
CBM.1.3.3Vendor reference checks100%09 May 202515 May 202515 May 2025 ✓Procurement LeadDone
CBM.1.3.4Evaluate vendors and shortlist100%16 May 202529 May 202529 May 2025 ✓Procurement LeadDone
CBM.1.3.5Board decision on core banking platform100%30 May 202503 Jun 202503 Jun 2025 ✓S. OkaforDone
CBM.1.3.6Milestone: Temenos T24 selected—03 Jun 202503 Jun 202503 Jun 2025 ✓S. OkaforDone
CBM.1.3.7Contract negotiation with Temenos100%04 Jun 202527 Jun 202527 Jun 2025 ✓Procurement LeadDone
Contract signed 15 Jun 2025.
CBM.1.3.8Engage Deloitte Digital as system integration partner100%04 Jun 202518 Jun 202518 Jun 2025 ✓Procurement LeadDone
CBM.1.3.9Milestone: Phase 1 complete—30 Jun 202530 Jun 202530 Jun 2025 ✓S. OkaforDone
CBM.2Phase 2: Build, Configure and Integration42%01 Jul 202530 Sep 202623 Dec 2026V. ChakrabortyIn progress
CBM.2.1Environments and platform foundation90%01 Jul 202525 Nov 202529 May 2026Infrastructure LeadIn progress
CBM.2.1.1Provision Azure landing zone100%01 Jul 202528 Jul 202528 Jul 2025 ✓Infrastructure LeadDone
CBM.2.1.2Provision development and build environments100%29 Jul 202518 Aug 202518 Aug 2025 ✓Infrastructure LeadDone
CBM.2.1.3Install Temenos T24 base platform100%19 Aug 202515 Sep 202515 Sep 2025 ✓TemenosDone
CBM.2.1.4Configure continuous integration and delivery pipeline100%19 Aug 202515 Sep 202515 Sep 2025 ✓DevOps LeadDone
CBM.2.1.5Network connectivity to branches, ATMs and data centres100%29 Jul 202522 Sep 202522 Sep 2025 ✓Network LeadDone
CBM.2.1.6Identity, access and privileged access controls100%19 Aug 202529 Sep 202529 Sep 2025 ✓Security ArchitectDone
CBM.2.1.7Observability and monitoring platform0%27 Apr 202621 Oct 202529 May 2026DevOps LeadNot started
CBM.2.1.8Cloud cost and capacity model100%29 Jul 202518 Aug 202518 Aug 2025 ✓Infrastructure LeadDone
CBM.2.1.9Azure resilience and failover design validation100%23 Sep 202521 Oct 202521 Oct 2025 ✓Infrastructure LeadDone
CBM.2.1.10Security controls testing and CPS 234 evidence pack100%30 Sep 202525 Nov 202525 Nov 2025 ✓Security ArchitectDone
CBM.2.2Program controls70%01 Jul 202507 Jul 2026S. OkaforIn progress
CBM.2.2.1Establish change control board100%01 Jul 202507 Jul 202507 Jul 2025 ✓S. OkaforDone
CBM.2.2.2Integrated master schedule baseline approved100%08 Jul 202521 Jul 202521 Jul 2025 ✓S. OkaforDone
CBM.2.2.3Resourcing plan and backfill strategy100%08 Jul 202504 Aug 202504 Aug 2025 ✓S. OkaforDone
CBM.2.2.4Benefits baseline and tracking set-up100%22 Jul 202511 Aug 202511 Aug 2025 ✓S. OkaforDone
CBM.2.2.5Board update: Q3 2025100%01 Oct 202508 Oct 202508 Oct 2025 ✓S. OkaforDone
CBM.2.2.6Board update: Q4 2025100%05 Jan 202609 Jan 202609 Jan 2026 ✓S. OkaforDone
CBM.2.2.7Board update: Q1 2026100%01 Apr 202609 Apr 202609 Apr 2026 ✓S. OkaforDone
CBM.2.2.8Board update: Q2 20260%01 Jul 202607 Jul 2026S. OkaforNot started
CBM.2.2.9Knowledge transfer from departing engineers50%16 Mar 202612 May 2026V. ChakrabortyIn progress
Three senior engineers resigned in Q1. Knowledge transfer is only partly done.
CBM.2.2.10Recruit and onboard two replacement engineers50%16 Mar 202612 May 2026V. ChakrabortyIn progress
Two new hires are onboarding and will not be productive for 6 to 8 weeks.
CBM.2.3Core platform configuration59%16 Sep 202523 Sep 202605 Nov 2026Temenos Configuration LeadIn progress
CBM.2.3.1Configure retail banking products100%16 Sep 202511 Dec 202511 Dec 2025 ✓Deloitte DigitalDone
Transaction accounts, savings and term deposits are configured and unit tested.
CBM.2.3.2Configure business banking products85%12 Dec 202515 Jun 2026Deloitte DigitalIn progress
Business accounts and overdrafts are complete. Trade finance is in final review.
CBM.2.3.3Configure deposits and term deposit processing90%12 Dec 202515 Jun 2026Deloitte DigitalIn progress
Deposits are 90 percent complete.
CBM.2.3.4Configure loans and mortgages: interest calculation logic60%12 Dec 202515 Jul 202626 Aug 2026Deloitte DigitalDelayed
Variable rate mortgage interest logic is more complex than estimated. The Temenos configuration consultant has escalated to Temenos headquarters. A six week delay is expected.
CBM.2.3.5Configure cards and card scheme interfaces55%12 Dec 202506 Jul 2026Deloitte DigitalIn progress
CBM.2.3.6Configure general ledger and finance posting70%12 Dec 202505 Jun 2026Finance Systems LeadIn progress
CBM.2.3.7Configure fees, charges and pricing engine50%12 Dec 202506 Jul 2026Deloitte DigitalIn progress
CBM.2.3.8Configure customer onboarding and know your customer45%12 Dec 202506 Jul 2026Deloitte DigitalIn progress
CBM.2.3.9Configure customer limits and risk controls0%16 Jun 202610 Aug 2026Deloitte DigitalNot started
CBM.2.3.10Configure reporting and statements in T240%09 Jun 202603 Aug 2026Deloitte DigitalNot started
CBM.2.3.11Configure collateral and security management0%27 Aug 202609 Sep 202622 Oct 2026Deloitte DigitalNot started
CBM.2.3.12Configure interest and fee accrual engine0%16 Jun 202617 Aug 2026Deloitte DigitalNot started
CBM.2.3.13Configure batch and end-of-day processing80%12 Dec 202505 Jun 2026Deloitte DigitalIn progress
CBM.2.3.14Core platform configuration review0%23 Oct 202623 Sep 202605 Nov 2026Temenos Configuration LeadNot started
CBM.2.4Integration build: channels and core55%19 Aug 202517 Aug 202624 Sep 2026V. ChakrabortyIn progress
CBM.2.4.1Integration design standards and review100%19 Aug 202515 Sep 202515 Sep 2025 ✓V. ChakrabortyDone
CBM.2.4.2Core banking API layer: T24 REST APIs100%16 Sep 202525 Nov 202525 Nov 2025 ✓V. ChakrabortyDone
Core API layer is complete and tested. L. Obi resigned after completion and knowledge transfer was only partly done.
CBM.2.4.3Internet banking portal integration100%26 Nov 202509 Mar 202609 Mar 2026 ✓Digital TeamDone
Internet banking is integrated with T24 and performance tested to 50,000 concurrent users.
CBM.2.4.4Mobile banking app integration: iOS75%26 Nov 202502 Jul 202623 Jul 2026T. Ferreira (resigned)In progress
T. Ferreira was the mobile lead and resigned on 15 Mar. Handover is incomplete and a new developer is onboarding. A three week delay is expected.
CBM.2.4.5Mobile banking app integration: Android70%26 Nov 202502 Jul 202623 Jul 2026Digital TeamIn progress
CBM.2.4.6Payments: New Payments Platform (NPP)100%26 Nov 202523 Feb 202623 Feb 2026 ✓V. ChakrabortyDone
CBM.2.4.7Payments: BPAY75%26 Nov 202506 May 202620 May 2026V. ChakrabortyIn progress
CBM.2.4.8Payments: SWIFT and correspondent banking30%26 Nov 202530 Jul 202608 Sep 2026V. ChakrabortyDelayed
SWIFT is 30 percent complete because of complex correspondent banking logic. SWIFT and Direct Debit are on the path to SIT.
CBM.2.4.9Payments: Direct Debit20%26 Nov 202530 Jul 202608 Sep 2026V. ChakrabortyDelayed
CBM.2.4.10Branch teller interface integration: 42 branches40%26 Nov 202502 Jul 2026Branch OperationsIn progress
Branch teller integration is 40 percent complete on the standard T24 teller interface.
CBM.2.4.11ATM network integration: 180 ATMs15%26 Nov 202502 Jul 2026IT OperationsIn progress
Diebold Nixdorf integration. The ATM network is 15 percent complete.
CBM.2.4.12API gateway and security policies100%26 Nov 202523 Jan 202623 Jan 2026 ✓V. ChakrabortyDone
CBM.2.4.13Event streaming and messaging backbone100%26 Nov 202523 Feb 202623 Feb 2026 ✓V. ChakrabortyDone
CBM.2.4.14Integration monitoring and alerting100%27 Jan 202623 Mar 202623 Mar 2026 ✓DevOps LeadDone
CBM.2.4.15Open banking data sharing APIs45%27 Jan 202603 Jun 2026Digital TeamIn progress
CBM.2.4.16Integration test harness and service mocks100%26 Nov 202509 Feb 202609 Feb 2026 ✓V. ChakrabortyDone
CBM.2.4.17APRA regulatory reporting feeds0%01 Jun 202617 Aug 202624 Sep 2026Not assignedNot started
Regulatory reporting feeds are not started and no developer is assigned. APRA requires uninterrupted regulatory reporting, so these must be ready before go-live.
CBM.2.5Integration build: internal systems68%26 Nov 202520 May 2026Integration LeadIn progress
CBM.2.5.1Integrate Risk and credit decisioning85%26 Nov 202520 May 2026Risk Systems LeadIn progress
CBM.2.5.2Integrate Anti-money laundering and transaction monitoring80%26 Nov 202520 May 2026Compliance Systems LeadIn progress
CBM.2.5.3Integrate Fraud detection platform75%26 Nov 202520 May 2026Fraud Systems LeadIn progress
CBM.2.5.4Integrate Customer relationship management70%26 Nov 202520 May 2026CRM LeadIn progress
CBM.2.5.5Integrate Data warehouse and management reporting65%26 Nov 202520 May 2026Data Platform LeadIn progress
CBM.2.5.6Integrate Document management and statements60%26 Nov 202520 May 2026Digital TeamIn progress
CBM.2.5.7Integrate Contact centre and telephony55%26 Nov 202520 May 2026IT OperationsIn progress
CBM.2.5.8Integrate Treasury and markets50%26 Nov 202520 May 2026Treasury Systems LeadIn progress
CBM.2.6Integration build: third-party8%01 Sep 202530 Sep 202623 Dec 2026VacantIn progress
CBM.2.6.1Integrate third parties: payments and clearing partners8%01 Sep 202526 Aug 202617 Dec 2026Not assignedUnderstaffed
211 of 340 critical integrations are assigned. 129 have no developer because A. Park, who owned these, resigned. At current team velocity of three engineers they would complete in Jan 2027. External specialists of 4 to 6 FTE for three months are estimated at $4M to $6M and need board approval.
CBM.2.6.2Integrate third parties: credit bureaus and identity services8%01 Sep 202526 Aug 202617 Dec 2026Not assignedUnderstaffed
CBM.2.6.3Integrate third parties: card scheme and processors8%01 Sep 202526 Aug 202617 Dec 2026Not assignedUnderstaffed
CBM.2.6.4Integrate third parties: merchant and acquiring partners8%12 Jan 202627 Aug 202618 Dec 2026Not assignedUnderstaffed
CBM.2.6.5Integrate third parties: government and tax agencies8%12 Jan 202627 Aug 202618 Dec 2026Not assignedUnderstaffed
CBM.2.6.6Integrate third parties: insurance and wealth partners8%12 Jan 202627 Aug 202618 Dec 2026Not assignedUnderstaffed
CBM.2.6.7Integrate third parties: broker and aggregator channels8%30 Mar 202626 Aug 202617 Dec 2026Not assignedUnderstaffed
CBM.2.6.8Integrate third parties: open banking data recipients8%30 Mar 202626 Aug 202617 Dec 2026Not assignedUnderstaffed
CBM.2.6.9Integrate third parties: fintech and API partners8%30 Mar 202626 Aug 202617 Dec 2026Not assignedUnderstaffed
CBM.2.6.10Integrate third parties: regional and other partners8%30 Mar 202626 Aug 202617 Dec 2026Not assignedUnderstaffed
CBM.2.6.11Integration build quality gate0%21 Dec 202601 Sep 202623 Dec 2026V. ChakrabortyNot started
CBM.2.6.12Milestone: Phase 2 complete—23 Dec 202630 Sep 202623 Dec 2026V. ChakrabortyNot started
CBM.3Phase 3: Customer Data Migration47%01 Jul 202506 Nov 2026A. OseiIn progress
CBM.3.1Data analysis and quality91%01 Jul 202511 May 2026A. OseiIn progress
CBM.3.1.1Data catalogue and schema mapping: legacy to T24100%01 Jul 202525 Sep 202525 Sep 2025 ✓A. OseiDone
847 data entities mapped from legacy to T24 schema.
CBM.3.1.2Data quality audit: 2.1M customer records100%26 Sep 202507 Jan 202607 Jan 2026 ✓TemenosDone
340,000 anomalies found: 180K duplicate or linked, 95K dormant, 65K outdated beneficiary data.
CBM.3.1.3Classify anomalies by category and impact100%08 Jan 202619 Feb 202619 Feb 2026 ✓A. OseiDone
CBM.3.1.4Agree dormant account strategy with legal100%20 Feb 202602 Apr 202602 Apr 2026 ✓K. BarrettDone
CBM.3.1.5Anomaly remediation plan60%20 Feb 202611 May 2026A. OseiIn progress
Duplicate remediation is complex and needs customer outreach.
CBM.3.2Remediation and tooling31%26 Sep 202528 Jul 202608 Sep 2026A. OseiIn progress
CBM.3.2.1Duplicate account remediation: 180K accounts20%20 Feb 202628 Jul 202608 Sep 2026A. OseiDelayed
Customer-linked duplicates require manual review. Duplicate remediation is six weeks behind, which puts the migration dry run at risk.
CBM.3.2.2Outdated beneficiary data remediation: 65K records25%20 Feb 202630 Jun 2026A. OseiIn progress
CBM.3.2.3Dormant account remediation: 95K accounts0%27 Apr 202630 Jun 202620 Jul 2026A. OseiNot started
CBM.3.2.4Migration tooling and ETL build70%26 Sep 202504 May 2026TemenosIn progress
CBM.3.2.5Reconciliation framework and controls0%05 May 202628 Jul 2026A. OseiNot started
CBM.3.3Migration rehearsals24%20 Feb 202606 Nov 2026A. OseiIn progress
CBM.3.3.1Data privacy and consent review for migration100%20 Feb 202619 Mar 202619 Mar 2026 ✓K. BarrettDone
CBM.3.3.2Customer outreach for linked duplicate accounts0%12 May 202607 Jul 2026Branch OperationsNot started
CBM.3.3.3Data archiving and retention strategy56%07 Apr 202611 May 2026A. OseiIn progress
CBM.3.3.4Migration cutover runbook0%05 May 202616 Jun 2026A. OseiNot started
CBM.3.3.5Migration dry run 1: full data set0%09 Sep 202614 Aug 202622 Sep 2026A. OseiNot started
Requires all anomaly remediation to be complete. A slip in duplicate remediation pushes the dry run into September.
CBM.3.3.6Migration dry run 2: full data set and reconciliation0%23 Sep 202628 Aug 202607 Oct 2026A. OseiNot started
CBM.3.3.7Migration dress rehearsal: simulated cutover0%02 Nov 202606 Nov 2026A. OseiNot started
Full weekend cutover simulation. Target is completion inside the 62-hour window.
CBM.4Phase 4: Testing and Parallel Run10%02 Feb 202609 Mar 202702 Jul 2027L. FerreiraIn progress
CBM.4.1Test preparation19%02 Feb 202621 Sep 2026L. FerreiraIn progress
CBM.4.1.1Test strategy and plan40%02 Mar 202626 May 2026L. FerreiraIn progress
Test data approach agreed.
CBM.4.1.2Provision SIT and performance environments5%13 Apr 202627 Jul 2026IT OperationsIn progress
SIT environment is being provisioned on Azure.
CBM.4.1.3Test case design: SIT and UAT scripts35%02 Feb 202612 May 2026L. FerreiraIn progress
CBM.4.1.4Test data preparation0%13 May 202608 Jul 2026L. FerreiraNot started
CBM.4.1.5Disaster recovery environment build0%28 Jul 202621 Sep 2026Infrastructure LeadNot started
CBM.4.1.6Test governance and defect triage set-up100%02 Mar 202613 Mar 202613 Mar 2026 ✓L. FerreiraDone
CBM.4.1.7Regression test suite automation0%13 May 202608 Jul 2026L. FerreiraNot started
CBM.4.2System integration testing (SIT)0%24 Dec 202630 Oct 202625 Feb 2027L. FerreiraNot started
CBM.4.2.1SIT cycle 1: core platform and channels0%24 Dec 202621 Sep 202615 Jan 2027L. FerreiraNot started
Cannot start until all 340 critical integrations are complete.
CBM.4.2.2SIT cycle 2: payments and internal systems0%18 Jan 202712 Oct 202605 Feb 2027L. FerreiraNot started
CBM.4.2.3SIT cycle 3: third parties and regulatory reporting0%08 Feb 202730 Oct 202625 Feb 2027L. FerreiraNot started
Current trajectory: SIT completes in Feb 2027, about 3 months after the SIT target.
CBM.4.2.4Performance and volume testing0%18 Jan 202708 Oct 202603 Feb 2027L. FerreiraNot started
CBM.4.2.5Disaster recovery failover test0%04 Feb 202716 Oct 202611 Feb 2027IT OperationsNot started
CBM.4.2.6Security penetration test0%18 Jan 202713 Oct 202608 Feb 2027Security ArchitectNot started
CBM.4.2.7Branch and ATM end-to-end testing0%08 Feb 202728 Oct 202623 Feb 2027Branch OperationsNot started
CBM.4.2.8Operational readiness testing0%04 Feb 202726 Oct 202619 Feb 2027IT OperationsNot started
CBM.4.2.9Business continuity test0%12 Feb 202723 Oct 202618 Feb 2027IT OperationsNot started
CBM.4.2.10Milestone: SIT exit approved—25 Feb 202730 Oct 202625 Feb 2027L. FerreiraNot started
CBM.4.3User acceptance testing (UAT)0%08 Feb 202714 Dec 202613 Apr 2027L. FerreiraNot started
CBM.4.3.1UAT preparation and business user training0%08 Feb 202702 Nov 202626 Feb 2027Business TeamsNot started
CBM.4.3.2UAT cycle 1: retail banking0%01 Mar 202723 Nov 202619 Mar 2027Business TeamsNot started
Six week minimum for UAT. It cannot be compressed for a project of this complexity.
CBM.4.3.3UAT cycle 2: business banking and payments0%22 Mar 202714 Dec 202613 Apr 2027Business TeamsNot started
CBM.4.3.4Milestone: UAT exit approved—13 Apr 202714 Dec 202613 Apr 2027L. FerreiraNot started
CBM.4.4Parallel run0%14 Apr 202709 Mar 202702 Jul 2027S. OkaforNot started
CBM.4.4.1Parallel run: old and new systems running together0%14 Apr 202705 Mar 202730 Jun 2027All teamsNot started
Non-negotiable. APRA and internal risk policy require both systems to run simultaneously for 3 months.
CBM.4.4.2Parallel run: daily reconciliation reporting0%14 Apr 202705 Mar 202730 Jun 2027A. OseiNot started
CBM.4.4.3Parallel run exit review and reconciliation sign-off0%01 Jul 202709 Mar 202702 Jul 2027S. OkaforNot started
CBM.4.4.4Milestone: Parallel run exit approved—02 Jul 202709 Mar 202702 Jul 2027S. OkaforNot started
CBM.5Phase 5: Regulatory and Compliance (APRA CPS 234)33%15 Jan 202521 Apr 202730 Jun 2027M. AndersenIn progress
CBM.5.1Notifications43%15 Jan 202505 Mar 202730 Jun 2027M. AndersenIn progress
CBM.5.1.1APRA initial project notification100%15 Jan 202522 Jan 202522 Jan 2025 ✓M. AndersenDone
APRA notified. CPS 234 compliance framework engaged.
CBM.5.1.2CPS 234 compliance assessment100%01 Apr 202527 Jun 202527 Jun 2025 ✓K. BarrettDone
CBM.5.1.3Proactive APRA delay briefing0%28 Apr 202630 Apr 2026M. AndersenNot started
Recommended immediately. APRA responds better to proactive disclosure. The CEO and CRO should attend. It is not yet scheduled.
CBM.5.1.4Prepare CPS 234 pre-cutover notification0%01 Jul 202601 Sep 2026M. AndersenNot started
A six month minimum pre-notification applies for a Mar 2027 go-live. Board members carry personal liability.
CBM.5.1.5Milestone: CPS 234 pre-cutover notification lodged—01 Sep 202601 Sep 2026M. AndersenNot started
Not lodged. The Sep 2026 deadline is at risk.
CBM.5.1.6Privacy impact assessment100%01 Sep 202526 Sep 202526 Sep 2025 ✓K. BarrettDone
CBM.5.1.7CPS 230 operational resilience alignment60%02 Feb 202628 Apr 2026K. BarrettIn progress
CBM.5.1.8Board risk committee briefing on delay and recovery plan0%01 May 202607 May 2026M. AndersenNot started
CBM.5.1.9External audit of CPS 234 controls0%02 Sep 202614 Oct 2026M. AndersenNot started
CBM.5.1.10APRA regulatory reporting parallel run0%14 Apr 202705 Mar 202730 Jun 2027Compliance Systems LeadNot started
CBM.5.2Quarterly APRA reporting50%01 Jul 202521 Apr 2027M. AndersenIn progress
CBM.5.2.1Quarterly APRA progress report: Q2 2025100%01 Jul 202521 Jul 202521 Jul 2025 ✓M. AndersenDone
CBM.5.2.2Quarterly APRA progress report: Q3 2025100%01 Oct 202522 Oct 202522 Oct 2025 ✓M. AndersenDone
CBM.5.2.3Quarterly APRA progress report: Q4 2025100%05 Jan 202623 Jan 202623 Jan 2026 ✓M. AndersenDone
CBM.5.2.4Quarterly APRA progress report: Q1 2026100%01 Apr 202623 Apr 202623 Apr 2026 ✓M. AndersenDone
CBM.5.2.5Quarterly APRA progress report: Q2 20260%01 Jul 202621 Jul 2026M. AndersenNot started
Reports have not disclosed the integration delays. Disclosing proactively is recommended.
CBM.5.2.6Quarterly APRA progress report: Q3 20260%01 Oct 202622 Oct 2026M. AndersenNot started
CBM.5.2.7Quarterly APRA progress report: Q4 20260%04 Jan 202722 Jan 2027M. AndersenNot started
CBM.5.2.8Quarterly APRA progress report: Q1 20270%01 Apr 202721 Apr 2027M. AndersenNot started
CBM.5.3Customer regulatory communications0%04 May 202611 Dec 2026K. BarrettNot started
CBM.5.3.1Customer communications plan: 2.1M customers0%04 May 202629 Jun 2026K. BarrettNot started
The plan needs 8 weeks and should start by May 2026. The communications team is unaware this is assigned to them.
CBM.5.3.2ASIC engagement on customer notices0%30 Jun 202613 Jul 2026K. BarrettNot started
CBM.5.3.3Legal review, ASIC alignment and executive approval0%30 Jun 202627 Jul 2026K. BarrettNot started
CBM.5.3.4Issue customer notifications about the migration0%01 Oct 202605 Nov 2026Communications TeamNot started
CBM.5.3.5Branch and contact centre staff briefings0%02 Nov 202627 Nov 2026Branch OperationsNot started
CBM.5.3.6Customer dispute and complaints handling readiness0%02 Nov 202611 Dec 2026Customer Care LeadNot started
CBM.6Phase 6: Cutover and Hypercare0%14 Apr 202722 Jun 202713 Oct 2027S. OkaforNot started
CBM.6.1Cutover preparation0%14 Apr 202711 Mar 202706 Jul 2027S. OkaforNot started
CBM.6.1.1Cutover planning and weekend war room set-up0%14 Apr 202715 Feb 202725 May 2027S. OkaforNot started
Go and no-go criteria, rollback triggers, communications tree, war room roster, vendor on-call (Temenos, Deloitte).
CBM.6.1.2Cutover rollback rehearsal0%26 May 202722 Feb 202701 Jun 2027S. OkaforNot started
CBM.6.1.3Hypercare war room roster and shifts0%26 May 202701 Mar 202708 Jun 2027S. OkaforNot started
CBM.6.1.4Vendor on-call agreements: Temenos and Deloitte0%26 May 202701 Mar 202708 Jun 2027Procurement LeadNot started
CBM.6.1.5Cutover customer messaging: day-of communications0%02 Jun 202701 Mar 202708 Jun 2027Communications TeamNot started
CBM.6.1.6Branch cutover readiness check: 42 branches0%02 Jun 202701 Mar 202708 Jun 2027Branch OperationsNot started
CBM.6.1.7Go and no-go decision0%05 Jul 202711 Mar 202706 Jul 2027S. OkaforNot started
CBM.6.2Cutover and go-live0%07 Jul 202715 Mar 202708 Jul 2027S. OkaforNot started
CBM.6.2.1Cutover weekend: production migration and switch0%07 Jul 202715 Mar 202708 Jul 2027All teamsNot started
72-hour production window. All 2.1M customers.
CBM.6.2.2Milestone: GO-LIVE: Core Banking Migration—08 Jul 202715 Mar 202708 Jul 2027All teamsNot started
CBM.6.3Hypercare0%09 Jul 202722 Jun 202713 Oct 2027S. OkaforNot started
CBM.6.3.1Hypercare: intensive support0%09 Jul 202716 Apr 202709 Aug 2027All teamsNot started
CBM.6.3.2Hypercare: standard support and defect burn-down0%10 Aug 202721 May 202713 Sep 2027All teamsNot started
CBM.6.3.3Maintain rollback capability0%09 Jul 202702 Jun 202723 Sep 2027S. OkaforNot started
Rollback is maintained for 90 days.
CBM.6.3.4Post-migration reconciliation and sign-off0%10 Aug 202714 May 202706 Sep 2027A. OseiNot started
CBM.6.3.5Post go-live defect triage0%09 Jul 202716 Apr 202709 Aug 2027L. FerreiraNot started
CBM.6.3.6Customer complaint monitoring0%09 Jul 202712 May 202702 Sep 2027Customer Care LeadNot started
CBM.6.3.7Knowledge transfer to operations0%10 Aug 202728 May 202720 Sep 2027V. ChakrabortyNot started
CBM.6.3.8Post go-live APRA report0%09 Jul 202707 Apr 202729 Jul 2027M. AndersenNot started
CBM.6.3.9Decommission legacy platform0%24 Sep 202715 Jun 202706 Oct 2027IT OperationsNot started
CBM.6.3.10Post-implementation review0%07 Oct 202722 Jun 202713 Oct 2027S. OkaforNot started
CBM.6.3.11Milestone: Hypercare complete—13 Oct 202722 Jun 202713 Oct 2027S. OkaforNot started

211 rows from the Nexus Bank demonstration schedule export. Finish dates in red are past plan or forecast beyond plan.

0
Blocker
1
Critical
2
High
2
Medium

Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal.

1

129 critical integrations unassigned after three resignations

Critical · Resource

Third-party integrations (CBM.2.6.1 to CBM.2.6.10, no owner) are 8% complete. The source comment says 211 of 340 critical integrations are assigned, 129 have no developer because A. Park resigned, and the current team of three engineers would finish in Jan 2027. The iOS lead (T. Ferreira) and L. Obi also resigned, and knowledge transfer is only partly done.

The integration build quality gate is dated 23 Dec 2026, 80 working days after its baseline, and it has -80 days of float. SIT, UAT, the parallel run and go-live follow it, so go-live is dated 8 Jul 2027, 80 working days after baseline. Two replacement engineers are onboarding and need 6 to 8 weeks to become productive (source comment).

Integration build·Critical path·Source: CBM.2.6.1 (ID 97), CBM.2.6.11 (ID 107), CBM.2.2.9 (ID 52), CBM.2.2.10 (ID 53)
Observed unassigned count, resignations and velocity in source commentsCalculated 80 working days behind, -80 days of float
2

CPS 234 pre-cutover notification not lodged

High · Regulatory

The notification is a milestone dated 1 Sep 2026 (CBM.5.1.5). Preparing it (CBM.5.1.4, M. Andersen) starts 1 Jul 2026 and is 0% complete. The proactive APRA delay briefing (CBM.5.1.3) is in the schedule at 0%. Source comments say a six month minimum pre-notification applies and that board members carry personal liability.

The notification date is fixed against the 15 Mar 2027 baseline, while the integration build behind it is running late. The schedule gives the notification 130 working days of float, so the schedule logic does not show it driving go-live. The risk is regulatory: lodging a credible notification while integration status is behind. Whether the date can move is a question for APRA and the CRO, and the export does not say.

APRA CPS 234·Board liability·Source: CBM.5.1.5 (ID 166), CBM.5.1.4 (ID 165), CBM.5.1.3 (ID 164)
Observed dates, 0% complete and liability statement in source commentsCalculated 130 working days of float
3

The three month parallel run compresses every upstream delay into go-live

High · Schedule

APRA and internal risk policy require the old and new systems to run together for three months (CBM.4.4.1, source comment). It follows UAT, which follows SIT, which follows the integration build.

SIT is dated to start 24 Dec 2026, 80 working days after baseline, and the parallel run is dated 14 Apr 2027 to 30 Jun 2027. Every one of these stages carries the same negative float (-80 days), so none has room to absorb a further slip.

Parallel run·Non-negotiable·Source: CBM.4.2.1 (ID 140), CBM.4.4.1 (ID 156), CBM.6.2.2 (ID 199)
Observed parallel run requirement in source commentCalculated SIT start 80 working days after baseline
4

Duplicate account remediation is six weeks behind

Medium · Data

The data quality audit found 340,000 anomalies: 180K duplicate or linked, 95K dormant and 65K with outdated beneficiary data. Duplicate account remediation (CBM.3.2.1, A. Osei) is 20% complete and finishes 8 Sep 2026, against a baseline of 28 Jul 2026. Customer-linked duplicates need manual review (source comment).

The task has 90 working days of float, so it is not driving go-live in the schedule logic. Migration dry run 1 (CBM.3.3.5) depends on it and is dated 9 Sep 2026, against a baseline start of 3 Aug 2026. Migrating anomalous financial data is not permitted, so the remediation must finish before cutover.

A. Osei·Data migration·Source: CBM.3.2.1 (ID 117), CBM.3.3.5 (ID 127)
Observed anomaly counts and manual review in source commentsCalculated float of 90 working days
5

Customer communications plan has not started

Medium · Regulatory

The plan for 2.1M customers (CBM.5.3.1, K. Barrett) is dated to start 4 May 2026 and is 0% complete. The source comment says it needs 8 weeks, and that the communications team is unaware it is assigned to them.

Customer notifications (CBM.5.3.3) are dated from 1 Oct 2026, and the plan has 126 working days of float. The risk is a start that slips because the owner team has not been briefed, which would leave less than the 8 weeks the plan needs.

K. Barrett·Customers·Source: CBM.5.3.1 (ID 182), CBM.5.3.4 (ID 185)
Observed 8 week requirement and unaware team in source commentCalculated float of 126 working days

Actions 1 and 2 depend on executive decisions. See Decisions Required on the Executive Overview.

Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal. Owners and due dates are Cherry recommendations. Urgency is measured from the 27 Apr 2026 status date: This week = due within 5 working days, This month = within 20, Monitor = later. The export does not hold action owners or due dates.

1

Engage external integration specialists to close the 129-integration gap

This week · due 1 May

The gap cannot be closed with internal hires alone in the time available.

Owner: Program Director (S. Okafor), proceeding on approval of Decision 1. Due: 1 May 2026. Engage a specialist integration consultancy under a fixed scope to complete the integrations with no developer. The source comment estimates $4M to $6M for 4 to 6 FTE over three months.

Board approval·Integration·Source: CBM.2.6.1 (ID 97)
Observed gap, cost and FTE in source commentRecommended owner and due date
Pending decision 1
2

Brief APRA on the delay and the recovery plan

Monitor · due 29 May

Do not wait for the notification date to raise the timeline risk.

Owner: CRO (M. Andersen), proceeding on endorsement of Decision 2. Due: 29 May 2026. Hold the briefing (CBM.5.1.3) with the current position, the cause of delay and the mitigation under way, before the CPS 234 notification is prepared. Disclose the delay in the Q2 2026 APRA progress report as well.

APRA·Proactive·Source: CBM.5.1.3 (ID 164), CBM.5.1.5 (ID 166)
Observed briefing at 0% and not scheduled in the source commentRecommended owner and due date
Pending decision 2
3

Brief the communications team and start the customer communications plan

This week · due 4 May

The plan needs 8 weeks and its owner team has not been briefed.

Owner: Legal and Regulatory Lead (K. Barrett). Due: 4 May 2026, the planned start. Brief the communications lead on the cutover timeline, the parallel run window and the 2.1M customer scope, so the plan starts on its dated day.

Task action·K. Barrett·Source: CBM.5.3.1 (ID 182)
Observed 8 weeks and unaware team in source commentRecommended owner and due date
4

Recover duplicate account remediation before dry run 1

Monitor · due 29 May

The task is six weeks behind and customer-linked duplicates need manual review.

Owner: Data Migration Lead (A. Osei). Due: 29 May 2026. Split the 180K duplicates by whether they have active transactions, and add manual review capacity for those first. Report the count remaining weekly against the 28 Jul 2026 baseline finish.

Task action·A. Osei·Source: CBM.3.2.1 (ID 117), CBM.3.3.5 (ID 127)
Observed six week delay in source commentRecommended owner and due date
5

Act on the exit interview findings to keep the remaining integration engineers

Monitor · due 29 May

Three senior engineers left in Q1, and the build cannot absorb more departures.

Owner: Integration Lead (V. Chakraborty). Due: 29 May 2026. Complete knowledge transfer from the departing engineers (CBM.2.3.x, 50% complete) and agree retention steps for the engineers who remain.

Task action·V. Chakraborty·Source: CBM.2.2.9 (ID 52), CBM.2.2.10 (ID 53)
Observed resignations and handover in source commentsRecommended owner and due date

Program Management26 activities · lead: S. Okafor

83%
1 with negative float
1 open risk sit in this workstream. See Risk Analysis.
Status
TaskStartFinishOwner%Status
Program mobilisation and governance set-up06 Jan 202517 Jan 2025S. Okafor100%Done
Interview business and IT stakeholders20 Jan 202510 Feb 2025R. Singh100%Done
Current state assessment report25 Mar 202531 Mar 2025R. Singh100%Done
Business capability workshops20 Jan 202510 Feb 2025R. Singh100%Done
Program business case and funding approval01 Apr 202514 Apr 2025S. Okafor100%Done
Program risk and issue register established20 Jan 202524 Jan 2025S. Okafor100%Done
Prepare request for proposal25 Mar 202507 Apr 2025Procurement Lead100%Done
Vendor responses and demonstrations08 Apr 202508 May 2025Procurement Lead100%Done
Vendor reference checks09 May 202515 May 2025Procurement Lead100%Done
Evaluate vendors and shortlist16 May 202529 May 2025Procurement Lead100%Done
Board decision on core banking platform30 May 202503 Jun 2025S. Okafor100%Done
Milestone: Temenos T24 selected03 Jun 202503 Jun 2025S. Okafor—Done
Contract negotiation with Temenos04 Jun 202527 Jun 2025Procurement Lead100%Done
Engage Deloitte Digital as system integration partner04 Jun 202518 Jun 2025Procurement Lead100%Done
Milestone: Phase 1 complete30 Jun 202530 Jun 2025S. Okafor—Done
Establish change control board01 Jul 202507 Jul 2025S. Okafor100%Done
Integrated master schedule baseline approved08 Jul 202521 Jul 2025S. Okafor100%Done
Resourcing plan and backfill strategy08 Jul 202504 Aug 2025S. Okafor100%Done
Benefits baseline and tracking set-up22 Jul 202511 Aug 2025S. Okafor100%Done
Board update: Q3 202501 Oct 202508 Oct 2025S. Okafor100%Done
Board update: Q4 202505 Jan 202609 Jan 2026S. Okafor100%Done
Board update: Q1 202601 Apr 202609 Apr 2026S. Okafor100%Done
Board update: Q2 202601 Jul 202607 Jul 2026S. Okafor0%Not started
Knowledge transfer from departing engineers16 Mar 202612 May 2026V. Chakraborty50%In progress
Recruit and onboard two replacement engineers16 Mar 202612 May 2026V. Chakraborty50%In progress
Post-implementation review07 Oct 202713 Oct 2027S. Okafor0%Not started
Linked risks
Risk 1
129 critical integrations unassigned after three resignations
Third-party integrations (CBM.2.6.1 to CBM.2.6.10, no owner) are 8% complete. The source comment says 211 of 340 critical integrations are assigned, ...
Linked actions
Action 1This week · due 1 May
Engage external integration specialists to close the 129-integration gap
The gap cannot be closed with internal hires alone in the time available.
Action 5Monitor · due 29 May
Act on the exit interview findings to keep the remaining integration engineers
Three senior engineers left in Q1, and the build cannot absorb more departures.

Integration38 activities · lead: V. Chakraborty

36%
12 delayed, 13 with negative float
1 open risk sit in this workstream. See Risk Analysis.
Status
TaskStartFinishOwner%Status
Catalogue existing integrations20 Jan 202510 Mar 2025R. Singh100%Done
Classify integrations by criticality11 Mar 202524 Mar 2025R. Singh100%Done
Integration design standards and review19 Aug 202515 Sep 2025V. Chakraborty100%Done
Core banking API layer: T24 REST APIs16 Sep 202525 Nov 2025V. Chakraborty100%Done
Internet banking portal integration26 Nov 202509 Mar 2026Digital Team100%Done
Mobile banking app integration: iOS26 Nov 202523 Jul 2026T. Ferreira (resigned)75%In progress
Mobile banking app integration: Android26 Nov 202523 Jul 2026Digital Team70%In progress
Payments: New Payments Platform (NPP)26 Nov 202523 Feb 2026V. Chakraborty100%Done
Payments: BPAY26 Nov 202520 May 2026V. Chakraborty75%In progress
Payments: SWIFT and correspondent banking26 Nov 202508 Sep 2026V. Chakraborty30%Delayed
Payments: Direct Debit26 Nov 202508 Sep 2026V. Chakraborty20%Delayed
Branch teller interface integration: 42 branches26 Nov 202502 Jul 2026Branch Operations40%In progress
ATM network integration: 180 ATMs26 Nov 202502 Jul 2026IT Operations15%In progress
API gateway and security policies26 Nov 202523 Jan 2026V. Chakraborty100%Done
Event streaming and messaging backbone26 Nov 202523 Feb 2026V. Chakraborty100%Done
Integration monitoring and alerting27 Jan 202623 Mar 2026DevOps Lead100%Done
Open banking data sharing APIs27 Jan 202603 Jun 2026Digital Team45%In progress
Integration test harness and service mocks26 Nov 202509 Feb 2026V. Chakraborty100%Done
Integrate Risk and credit decisioning26 Nov 202520 May 2026Risk Systems Lead85%In progress
Integrate Anti-money laundering and transaction monitoring26 Nov 202520 May 2026Compliance Systems Lead80%In progress
Integrate Fraud detection platform26 Nov 202520 May 2026Fraud Systems Lead75%In progress
Integrate Customer relationship management26 Nov 202520 May 2026CRM Lead70%In progress
Integrate Data warehouse and management reporting26 Nov 202520 May 2026Data Platform Lead65%In progress
Integrate Document management and statements26 Nov 202520 May 2026Digital Team60%In progress
Integrate Contact centre and telephony26 Nov 202520 May 2026IT Operations55%In progress
Integrate Treasury and markets26 Nov 202520 May 2026Treasury Systems Lead50%In progress
Integrate third parties: payments and clearing partners01 Sep 202517 Dec 2026Not assigned8%Understaffed
Integrate third parties: credit bureaus and identity services01 Sep 202517 Dec 2026Not assigned8%Understaffed
Integrate third parties: card scheme and processors01 Sep 202517 Dec 2026Not assigned8%Understaffed
Integrate third parties: merchant and acquiring partners12 Jan 202618 Dec 2026Not assigned8%Understaffed
Integrate third parties: government and tax agencies12 Jan 202618 Dec 2026Not assigned8%Understaffed
Integrate third parties: insurance and wealth partners12 Jan 202618 Dec 2026Not assigned8%Understaffed
Integrate third parties: broker and aggregator channels30 Mar 202617 Dec 2026Not assigned8%Understaffed
Integrate third parties: open banking data recipients30 Mar 202617 Dec 2026Not assigned8%Understaffed
Integrate third parties: fintech and API partners30 Mar 202617 Dec 2026Not assigned8%Understaffed
Integrate third parties: regional and other partners30 Mar 202617 Dec 2026Not assigned8%Understaffed
Integration build quality gate21 Dec 202623 Dec 2026V. Chakraborty0%Not started
Milestone: Phase 2 complete23 Dec 202623 Dec 2026V. Chakraborty—Not started
Linked risks
Risk 1
129 critical integrations unassigned after three resignations
Third-party integrations (CBM.2.6.1 to CBM.2.6.10, no owner) are 8% complete. The source comment says 211 of 340 critical integrations are assigned, ...
Linked actions
Action 1This week · due 1 May
Engage external integration specialists to close the 129-integration gap
The gap cannot be closed with internal hires alone in the time available.
Action 5Monitor · due 29 May
Act on the exit interview findings to keep the remaining integration engineers
Three senior engineers left in Q1, and the build cannot absorb more departures.

Regulatory and Compliance21 activities · lead: M. Andersen

38%
3 with negative float
1 open risk sit in this workstream. See Risk Analysis.
Status
TaskStartFinishOwner%Status
Regulatory obligations mapping (CPS 234 and CPS 230)11 Feb 202503 Mar 2025K. Barrett100%Done
APRA regulatory reporting feeds01 Jun 202624 Sep 2026Not assigned0%Not started
APRA initial project notification15 Jan 202522 Jan 2025M. Andersen100%Done
CPS 234 compliance assessment01 Apr 202527 Jun 2025K. Barrett100%Done
Proactive APRA delay briefing28 Apr 202630 Apr 2026M. Andersen0%Not started
Prepare CPS 234 pre-cutover notification01 Jul 202601 Sep 2026M. Andersen0%Not started
Milestone: CPS 234 pre-cutover notification lodged01 Sep 202601 Sep 2026M. Andersen—Not started
Privacy impact assessment01 Sep 202526 Sep 2025K. Barrett100%Done
CPS 230 operational resilience alignment02 Feb 202628 Apr 2026K. Barrett60%In progress
Board risk committee briefing on delay and recovery plan01 May 202607 May 2026M. Andersen0%Not started
External audit of CPS 234 controls02 Sep 202614 Oct 2026M. Andersen0%Not started
APRA regulatory reporting parallel run14 Apr 202730 Jun 2027Compliance Systems Lead0%Not started
Quarterly APRA progress report: Q2 202501 Jul 202521 Jul 2025M. Andersen100%Done
Quarterly APRA progress report: Q3 202501 Oct 202522 Oct 2025M. Andersen100%Done
Quarterly APRA progress report: Q4 202505 Jan 202623 Jan 2026M. Andersen100%Done
Quarterly APRA progress report: Q1 202601 Apr 202623 Apr 2026M. Andersen100%Done
Quarterly APRA progress report: Q2 202601 Jul 202621 Jul 2026M. Andersen0%Not started
Quarterly APRA progress report: Q3 202601 Oct 202622 Oct 2026M. Andersen0%Not started
Quarterly APRA progress report: Q4 202604 Jan 202722 Jan 2027M. Andersen0%Not started
Quarterly APRA progress report: Q1 202701 Apr 202721 Apr 2027M. Andersen0%Not started
Post go-live APRA report09 Jul 202729 Jul 2027M. Andersen0%Not started
Linked risks
Risk 2
CPS 234 pre-cutover notification not lodged
The notification is a milestone dated 1 Sep 2026 (CBM.5.1.5). Preparing it (CBM.5.1.4, M. Andersen) starts 1 Jul 2026 and is 0% complete. The ...
Linked actions
Action 2Monitor · due 29 May
Brief APRA on the delay and the recovery plan
Do not wait for the notification date to raise the timeline risk.

Data Migration19 activities · lead: A. Osei

47%
1 delayed, 1 with negative float
1 open risk sit in this workstream. See Risk Analysis.
Status
TaskStartFinishOwner%Status
Data landscape assessment20 Jan 202517 Feb 2025A. Osei100%Done
Data catalogue and schema mapping: legacy to T2401 Jul 202525 Sep 2025A. Osei100%Done
Data quality audit: 2.1M customer records26 Sep 202507 Jan 2026Temenos100%Done
Classify anomalies by category and impact08 Jan 202619 Feb 2026A. Osei100%Done
Agree dormant account strategy with legal20 Feb 202602 Apr 2026K. Barrett100%Done
Anomaly remediation plan20 Feb 202611 May 2026A. Osei60%In progress
Duplicate account remediation: 180K accounts20 Feb 202608 Sep 2026A. Osei20%Delayed
Outdated beneficiary data remediation: 65K records20 Feb 202630 Jun 2026A. Osei25%In progress
Dormant account remediation: 95K accounts27 Apr 202620 Jul 2026A. Osei0%Not started
Migration tooling and ETL build26 Sep 202504 May 2026Temenos70%In progress
Reconciliation framework and controls05 May 202628 Jul 2026A. Osei0%Not started
Data privacy and consent review for migration20 Feb 202619 Mar 2026K. Barrett100%Done
Customer outreach for linked duplicate accounts12 May 202607 Jul 2026Branch Operations0%Not started
Data archiving and retention strategy07 Apr 202611 May 2026A. Osei56%In progress
Migration cutover runbook05 May 202616 Jun 2026A. Osei0%Not started
Migration dry run 1: full data set09 Sep 202622 Sep 2026A. Osei0%Not started
Migration dry run 2: full data set and reconciliation23 Sep 202607 Oct 2026A. Osei0%Not started
Migration dress rehearsal: simulated cutover02 Nov 202606 Nov 2026A. Osei0%Not started
Post-migration reconciliation and sign-off10 Aug 202706 Sep 2027A. Osei0%Not started
Linked risks
Risk 4
Duplicate account remediation is six weeks behind
The data quality audit found 340,000 anomalies: 180K duplicate or linked, 95K dormant and 65K with outdated beneficiary data. Duplicate account ...
Linked actions
Action 4Monitor · due 29 May
Recover duplicate account remediation before dry run 1
The task is six weeks behind and customer-linked duplicates need manual review.

Infrastructure and Security16 activities · lead: Infrastructure Lead

82%
On plan
Status
TaskStartFinishOwner%Status
Infrastructure and security baseline assessment20 Jan 202510 Feb 2025Security Architect100%Done
Define architecture principles and capability map11 Feb 202526 Feb 2025T. Rao100%Done
Target architecture design: Temenos T24 on Azure27 Feb 202505 May 2025Deloitte Digital100%Done
Security and resilience review of target architecture06 May 202521 May 2025Security Architect100%Done
Architecture board approval22 May 202526 May 2025T. Rao100%Done
Milestone: Target architecture approved26 May 202526 May 2025T. Rao—Done
Provision Azure landing zone01 Jul 202528 Jul 2025Infrastructure Lead100%Done
Provision development and build environments29 Jul 202518 Aug 2025Infrastructure Lead100%Done
Configure continuous integration and delivery pipeline19 Aug 202515 Sep 2025DevOps Lead100%Done
Network connectivity to branches, ATMs and data centres29 Jul 202522 Sep 2025Network Lead100%Done
Identity, access and privileged access controls19 Aug 202529 Sep 2025Security Architect100%Done
Observability and monitoring platform27 Apr 202629 May 2026DevOps Lead0%Not started
Cloud cost and capacity model29 Jul 202518 Aug 2025Infrastructure Lead100%Done
Azure resilience and failover design validation23 Sep 202521 Oct 2025Infrastructure Lead100%Done
Security controls testing and CPS 234 evidence pack30 Sep 202525 Nov 2025Security Architect100%Done
Disaster recovery environment build28 Jul 202621 Sep 2026Infrastructure Lead0%Not started

Core Platform15 activities · lead: Deloitte Digital

59%
1 delayed
Status
TaskStartFinishOwner%Status
Install Temenos T24 base platform19 Aug 202515 Sep 2025Temenos100%Done
Configure retail banking products16 Sep 202511 Dec 2025Deloitte Digital100%Done
Configure business banking products12 Dec 202515 Jun 2026Deloitte Digital85%In progress
Configure deposits and term deposit processing12 Dec 202515 Jun 2026Deloitte Digital90%In progress
Configure loans and mortgages: interest calculation logic12 Dec 202526 Aug 2026Deloitte Digital60%Delayed
Configure cards and card scheme interfaces12 Dec 202506 Jul 2026Deloitte Digital55%In progress
Configure general ledger and finance posting12 Dec 202505 Jun 2026Finance Systems Lead70%In progress
Configure fees, charges and pricing engine12 Dec 202506 Jul 2026Deloitte Digital50%In progress
Configure customer onboarding and know your customer12 Dec 202506 Jul 2026Deloitte Digital45%In progress
Configure customer limits and risk controls16 Jun 202610 Aug 2026Deloitte Digital0%Not started
Configure reporting and statements in T2409 Jun 202603 Aug 2026Deloitte Digital0%Not started
Configure collateral and security management27 Aug 202622 Oct 2026Deloitte Digital0%Not started
Configure interest and fee accrual engine16 Jun 202617 Aug 2026Deloitte Digital0%Not started
Configure batch and end-of-day processing12 Dec 202505 Jun 2026Deloitte Digital80%In progress
Core platform configuration review23 Oct 202605 Nov 2026Temenos Configuration Lead0%Not started

Testing25 activities · lead: L. Ferreira

11%
19 with negative float
1 open risk sit in this workstream. See Risk Analysis.
Status
TaskStartFinishOwner%Status
Test strategy and plan02 Mar 202626 May 2026L. Ferreira40%In progress
Provision SIT and performance environments13 Apr 202627 Jul 2026IT Operations5%In progress
Test case design: SIT and UAT scripts02 Feb 202612 May 2026L. Ferreira35%In progress
Test data preparation13 May 202608 Jul 2026L. Ferreira0%Not started
Test governance and defect triage set-up02 Mar 202613 Mar 2026L. Ferreira100%Done
Regression test suite automation13 May 202608 Jul 2026L. Ferreira0%Not started
SIT cycle 1: core platform and channels24 Dec 202615 Jan 2027L. Ferreira0%Not started
SIT cycle 2: payments and internal systems18 Jan 202705 Feb 2027L. Ferreira0%Not started
SIT cycle 3: third parties and regulatory reporting08 Feb 202725 Feb 2027L. Ferreira0%Not started
Performance and volume testing18 Jan 202703 Feb 2027L. Ferreira0%Not started
Disaster recovery failover test04 Feb 202711 Feb 2027IT Operations0%Not started
Security penetration test18 Jan 202708 Feb 2027Security Architect0%Not started
Branch and ATM end-to-end testing08 Feb 202723 Feb 2027Branch Operations0%Not started
Operational readiness testing04 Feb 202719 Feb 2027IT Operations0%Not started
Business continuity test12 Feb 202718 Feb 2027IT Operations0%Not started
Milestone: SIT exit approved25 Feb 202725 Feb 2027L. Ferreira—Not started
UAT preparation and business user training08 Feb 202726 Feb 2027Business Teams0%Not started
UAT cycle 1: retail banking01 Mar 202719 Mar 2027Business Teams0%Not started
UAT cycle 2: business banking and payments22 Mar 202713 Apr 2027Business Teams0%Not started
Milestone: UAT exit approved13 Apr 202713 Apr 2027L. Ferreira—Not started
Parallel run: old and new systems running together14 Apr 202730 Jun 2027All teams0%Not started
Parallel run: daily reconciliation reporting14 Apr 202730 Jun 2027A. Osei0%Not started
Parallel run exit review and reconciliation sign-off01 Jul 202702 Jul 2027S. Okafor0%Not started
Milestone: Parallel run exit approved02 Jul 202702 Jul 2027S. Okafor—Not started
Post go-live defect triage09 Jul 202709 Aug 2027L. Ferreira0%Not started
Linked risks
Risk 3
The three month parallel run compresses every upstream delay into go-live
APRA and internal risk policy require the old and new systems to run together for three months (CBM.4.4.1, source comment). It follows UAT, which ...
Linked actions
Action 1This week · due 1 May
Engage external integration specialists to close the 129-integration gap
The gap cannot be closed with internal hires alone in the time available.

Change and Communications7 activities · lead: K. Barrett

0%
1 with negative float
1 open risk sit in this workstream. See Risk Analysis.
Status
TaskStartFinishOwner%Status
Customer communications plan: 2.1M customers04 May 202629 Jun 2026K. Barrett0%Not started
ASIC engagement on customer notices30 Jun 202613 Jul 2026K. Barrett0%Not started
Legal review, ASIC alignment and executive approval30 Jun 202627 Jul 2026K. Barrett0%Not started
Issue customer notifications about the migration01 Oct 202605 Nov 2026Communications Team0%Not started
Branch and contact centre staff briefings02 Nov 202627 Nov 2026Branch Operations0%Not started
Customer dispute and complaints handling readiness02 Nov 202611 Dec 2026Customer Care Lead0%Not started
Customer complaint monitoring09 Jul 202702 Sep 2027Customer Care Lead0%Not started
Linked risks
Risk 5
Customer communications plan has not started
The plan for 2.1M customers (CBM.5.3.1, K. Barrett) is dated to start 4 May 2026 and is 0% complete. The source comment says it needs 8 weeks, and ...
Linked actions
Action 3This week · due 4 May
Brief the communications team and start the customer communications plan
The plan needs 8 weeks and its owner team has not been briefed.

Cutover and Hypercare15 activities · lead: S. Okafor

0%
15 with negative float
1 open risk sit in this workstream. See Risk Analysis.
Status
TaskStartFinishOwner%Status
Cutover planning and weekend war room set-up14 Apr 202725 May 2027S. Okafor0%Not started
Cutover rollback rehearsal26 May 202701 Jun 2027S. Okafor0%Not started
Hypercare war room roster and shifts26 May 202708 Jun 2027S. Okafor0%Not started
Vendor on-call agreements: Temenos and Deloitte26 May 202708 Jun 2027Procurement Lead0%Not started
Cutover customer messaging: day-of communications02 Jun 202708 Jun 2027Communications Team0%Not started
Branch cutover readiness check: 42 branches02 Jun 202708 Jun 2027Branch Operations0%Not started
Go and no-go decision05 Jul 202706 Jul 2027S. Okafor0%Not started
Cutover weekend: production migration and switch07 Jul 202708 Jul 2027All teams0%Not started
Milestone: GO-LIVE: Core Banking Migration08 Jul 202708 Jul 2027All teams—Not started
Hypercare: intensive support09 Jul 202709 Aug 2027All teams0%Not started
Hypercare: standard support and defect burn-down10 Aug 202713 Sep 2027All teams0%Not started
Maintain rollback capability09 Jul 202723 Sep 2027S. Okafor0%Not started
Knowledge transfer to operations10 Aug 202720 Sep 2027V. Chakraborty0%Not started
Decommission legacy platform24 Sep 202706 Oct 2027IT Operations0%Not started
Milestone: Hypercare complete13 Oct 202713 Oct 2027S. Okafor—Not started
Linked risks
Risk 3
The three month parallel run compresses every upstream delay into go-live
APRA and internal risk policy require the old and new systems to run together for three months (CBM.4.4.1, source comment). It follows UAT, which ...
Linked actions
Action 1This week · due 1 May
Engage external integration specialists to close the 129-integration gap
The gap cannot be closed with internal hires alone in the time available.

Critical pathFrom the schedule export

The critical path in the export runs from the third-party integrations through the integration build quality gate, SIT, UAT, the three month parallel run, the go and no-go decision and the cutover weekend to Go-live, then hypercare, with -80 working days of float at each stage. The negative float is the gap between the dated finish (13 Oct 2027) and the baseline finish (22 Jun 2027) of the last milestone. APRA regulatory reporting feeds (CBM.2.4.17) have no developer and float of -20 days, so they are close behind. No task is dated before the work it depends on, so there is no dependency-corrected scenario.

53
Critical activities · 0d or less float
80d
Go-live behind baseline
0
Near-critical · 1 to 10d
18
Activities on the longest path

Sequence: 18 stages, read left to right and top to bottom. Critical activities are counted separately, as the longest path covers more tasks than the stages shown.

Critical path sequence

1CBM.2.6.6Integrate third parties: insurance and wealth partners-80d float
→
2CBM.2.6.11Integration build quality gate-80d float
→
3CBM.4.2.1SIT cycle 1: core platform and channels-80d float
→
4CBM.4.2.2SIT cycle 2: payments and internal systems-80d float
→
5CBM.4.3.1UAT preparation and business user training-80d float
→
6CBM.4.3.2UAT cycle 1: retail banking-80d float
→
7CBM.4.3.3UAT cycle 2: business banking and payments-80d float
→
8CBM.4.3.4UAT exit approved-80d float
→
9CBM.4.4.2Parallel run: daily reconciliation reporting-80d float
→
10CBM.4.4.3Parallel run exit review and reconciliation sign-off-80d float
→
11CBM.4.4.4Parallel run exit approved-80d float
→
12CBM.6.1.7Go and no-go decision-80d float
→
13CBM.6.2.1Cutover weekend: production migration and switch-80d float
→
14CBM.6.2.2GO-LIVE: Core Banking Migration-80d float
→
15CBM.6.3.3Maintain rollback capability-80d float
→
16CBM.6.3.9Decommission legacy platform-80d float
→
17CBM.6.3.10Post-implementation review-80d float
→
18CBM.6.3.11Hypercare complete-80d float

Critical task detail

WBSTaskDurationPlanned finishForecastOwner
CBM.2.4.8Payments: SWIFT and correspondent banking Alert198d30 Jul 202608 Sep 2026-8dV. Chakraborty
CBM.2.4.9Payments: Direct Debit Alert198d30 Jul 202608 Sep 2026-8dV. Chakraborty
CBM.2.4.17APRA regulatory reporting feeds Alert83d17 Aug 202624 Sep 2026-20dNot assigned
CBM.2.6.1Integrate third parties: payments and clearing partners Alert330d26 Aug 202617 Dec 2026-79dNot assigned
CBM.2.6.2Integrate third parties: credit bureaus and identity services Alert330d26 Aug 202617 Dec 2026-79dNot assigned
CBM.2.6.3Integrate third parties: card scheme and processors Alert330d26 Aug 202617 Dec 2026-79dNot assigned
CBM.2.6.4Integrate third parties: merchant and acquiring partners Alert240d27 Aug 202618 Dec 2026-80dNot assigned
CBM.2.6.5Integrate third parties: government and tax agencies Alert240d27 Aug 202618 Dec 2026-80dNot assigned
CBM.2.6.6Integrate third parties: insurance and wealth partners Alert240d27 Aug 202618 Dec 2026-80dNot assigned
CBM.2.6.7Integrate third parties: broker and aggregator channels Alert185d26 Aug 202617 Dec 2026-79dNot assigned
CBM.2.6.8Integrate third parties: open banking data recipients Alert185d26 Aug 202617 Dec 2026-79dNot assigned
CBM.2.6.9Integrate third parties: fintech and API partners Alert185d26 Aug 202617 Dec 2026-79dNot assigned
CBM.2.6.10Integrate third parties: regional and other partners Alert185d26 Aug 202617 Dec 2026-79dNot assigned
CBM.2.6.11Integration build quality gate Alert3d01 Sep 202623 Dec 2026-80dV. Chakraborty
CBM.4.2.1SIT cycle 1: core platform and channels Alert14d21 Sep 202615 Jan 2027-80dL. Ferreira
CBM.4.2.2SIT cycle 2: payments and internal systems14d12 Oct 202605 Feb 2027-80dL. Ferreira
CBM.4.2.3SIT cycle 3: third parties and regulatory reporting14d30 Oct 202625 Feb 2027-79dL. Ferreira
CBM.4.2.4Performance and volume testing12d08 Oct 202603 Feb 2027-75dL. Ferreira
CBM.4.2.5Disaster recovery failover test6d16 Oct 202611 Feb 2027-74dIT Operations
CBM.4.2.6Security penetration test15d13 Oct 202608 Feb 2027-66dSecurity Architect
CBM.4.2.7Branch and ATM end-to-end testing12d28 Oct 202623 Feb 2027-77dBranch Operations
CBM.4.2.8Operational readiness testing12d26 Oct 202619 Feb 2027-75dIT Operations
CBM.4.2.9Business continuity test5d23 Oct 202618 Feb 2027-74dIT Operations
CBM.4.2.10◆ SIT exit approved—30 Oct 202625 Feb 2027-79dL. Ferreira
CBM.4.3.1UAT preparation and business user training15d02 Nov 202626 Feb 2027-80dBusiness Teams
CBM.4.3.2UAT cycle 1: retail banking15d23 Nov 202619 Mar 2027-80dBusiness Teams
CBM.4.3.3UAT cycle 2: business banking and payments15d14 Dec 202613 Apr 2027-80dBusiness Teams
CBM.4.3.4◆ UAT exit approved—14 Dec 202613 Apr 2027-80dL. Ferreira
CBM.4.4.1Parallel run: old and new systems running together Alert55d05 Mar 202730 Jun 2027-80dAll teams
CBM.4.4.2Parallel run: daily reconciliation reporting55d05 Mar 202730 Jun 2027-80dA. Osei
CBM.4.4.3Parallel run exit review and reconciliation sign-off2d09 Mar 202702 Jul 2027-80dS. Okafor
CBM.4.4.4◆ Parallel run exit approved—09 Mar 202702 Jul 2027-80dS. Okafor
CBM.5.1.10APRA regulatory reporting parallel run55d05 Mar 202730 Jun 2027-78dCompliance Systems Lead
CBM.6.1.1Cutover planning and weekend war room set-up30d15 Feb 202725 May 2027-63dS. Okafor
CBM.6.1.2Cutover rollback rehearsal5d22 Feb 202701 Jun 2027-63dS. Okafor
CBM.6.1.3Hypercare war room roster and shifts10d01 Mar 202708 Jun 2027-63dS. Okafor
CBM.6.1.4Vendor on-call agreements: Temenos and Deloitte10d01 Mar 202708 Jun 2027-63dProcurement Lead
CBM.6.1.5Cutover customer messaging: day-of communications5d01 Mar 202708 Jun 2027-63dCommunications Team
CBM.6.1.6Branch cutover readiness check: 42 branches5d01 Mar 202708 Jun 2027-63dBranch Operations
CBM.6.1.7Go and no-go decision2d11 Mar 202706 Jul 2027-80dS. Okafor
CBM.6.2.1Cutover weekend: production migration and switch2d15 Mar 202708 Jul 2027-80dAll teams
CBM.6.2.2◆ GO-LIVE: Core Banking Migration—15 Mar 202708 Jul 2027-80dAll teams
CBM.6.3.1Hypercare: intensive support22d16 Apr 202709 Aug 2027-77dAll teams
CBM.6.3.2Hypercare: standard support and defect burn-down25d21 May 202713 Sep 2027-72dAll teams
CBM.6.3.3Maintain rollback capability55d02 Jun 202723 Sep 2027-80dS. Okafor
CBM.6.3.4Post-migration reconciliation and sign-off20d14 May 202706 Sep 2027-67dA. Osei
CBM.6.3.5Post go-live defect triage22d16 Apr 202709 Aug 2027-47dL. Ferreira
CBM.6.3.6Customer complaint monitoring40d12 May 202702 Sep 2027-65dCustomer Care Lead
CBM.6.3.7Knowledge transfer to operations30d28 May 202720 Sep 2027-77dV. Chakraborty
CBM.6.3.8Post go-live APRA report15d07 Apr 202729 Jul 2027-32dM. Andersen
CBM.6.3.9Decommission legacy platform8d15 Jun 202706 Oct 2027-80dIT Operations
CBM.6.3.10Post-implementation review5d22 Jun 202713 Oct 2027-80dS. Okafor
CBM.6.3.11◆ Hypercare complete—22 Jun 202713 Oct 2027-80dS. Okafor

All 53 critical activities are shown. This table is not curated or capped.

Float distribution

0d or less (critical)53 tasks
1–10d0 tasks
11–30d4 tasks
> 30d62 tasks

How this was calculatedAssumptions and limits

  • Source. Every date, percentage, float and comment comes from the schedule export at the 27 Apr 2026 status date. Cherry adds only labelled calculations and recommendations. Figures such as 129 unassigned integrations and $4M to $6M are quoted from source comments and are not checked against a resource plan or budget.
  • Links. The export lists predecessors by row ID and treats every link as finish-to-start. It has no lag, constraint or link-type column, so none is assumed. A task starts the next working day after its predecessor finishes; a milestone may share its predecessor's date. Cherry found no task dated before the work it depends on.
  • Calendar. Working days are Monday to Friday excluding an illustrative NSW public-holiday list. The export names the list but does not contain it, so Cherry cannot verify it.
  • Float. The export's Total Float is working days to the approved completion date (the baseline finish of Hypercare complete, 22 Jun 2027). Cherry recomputed it independently for the 119 incomplete activities that carry a float value, with no mismatch. Negative float means the activity is forecast to finish after that date.
  • Progress. Overall 41% is duration-weighted across activities (a milestone counts as one day). Planned 58% applies the same weights to baseline dates at the status date. Phase and workstream percentages use the same method.
  • Health rating. Critical, because the dated end of the project moves 80 working days against the baseline, which is 22 percent of the 372 working days remaining, above the 15 percent threshold. Cherry's rating is calculated from the schedule and is independent of any rating entered by the project team.
  • Near-critical. A fixed 1 to 10 working days. At this project's remaining duration a proportional threshold of 5 percent would be about 19 days, so the count is sensitive to the rule.
  • Workstream status. At risk = any incomplete task with negative float. Watch = no negative float but a task marked Delayed or Understaffed. Otherwise Complete, Not started or On plan.
  • Not assessed. Cost, resource capacity, hard constraints, link types and lag. The CPS 234 notification date is treated as a normal milestone; the export holds no constraint for it, and Cherry has not assessed APRA requirements.

Nexus Bank is a fictional organisation and project, built to show how Cherry reads a project schedule export. It does not describe a real bank, and no real project team has used or endorsed Cherry for it.