The integration build is understaffed and running behind, and the dependency chain behind it moves go-live from 15 Mar 2027 to 8 Jul 2027. Recovery is possible if integration capacity is approved now.
- 1Integration build is behind, with 129 of 340 critical integrations unassigned. Third-party integrations are 8% complete and forecast to finish 17 Dec 2026, against a baseline of 26 Aug 2026.
- 2Go-live is dated 8 Jul 2027, 80 working days after the 15 Mar 2027 baseline, because system integration testing, user acceptance and the three month parallel run all follow the integration build.
- 3The immediate decision is whether to approve external integration specialists, estimated in source comments at $4M to $6M, before the integration gap moves go-live further.
Schedule outlook
The integration build is driving the variance. The three month parallel run is fixed, so a late integration build moves go-live rather than shortening the testing behind it. End of hypercare moves from 22 Jun 2027 to 13 Oct 2027.
Critical pathZero or negative float from Integrate third parties: insurance and wealth partners to Hypercare complete
The longest as-dated path runs from the integration build through SIT, UAT and the parallel run to go-live and the end of hypercare, through 18 activities. Every stage carries -80 working days of float.
Delivery roadmapAs at 27 Apr 2026
APRA CPS 234 requires notification before cutover. The notification, the integration build and the three month parallel run all set the go-live date.
Decisions required
Integration capacity shortfall pushes go-live out and needs external specialists
Requested: Approve engagement of external integration specialists (4 to 6 FTE for three months, per the source comment on CBM.2.6.1) to close the 129 integrations with no developer. Third-party integrations finish 17 Dec 2026 at the current velocity of three engineers.
Recommended: Approve this week. Integration build quality gate (CBM.2.6.11) is dated 23 Dec 2026, 80 working days after baseline, and SIT, UAT and the parallel run follow it with no buffer.
If not decided: Go-live stays at 8 Jul 2027 or later, and every further week of delay on integration moves go-live and the end of hypercare (13 Oct 2027) by the same amount.
Proactive APRA engagement needs endorsement ahead of the CPS 234 notification
Requested: Endorse briefing APRA on the delay and recovery plan now. Proactive APRA delay briefing (CBM.5.1.3) is in the schedule at 0% and not yet held, and the CPS 234 pre-cutover notification (CBM.5.1.5) is dated 1 Sep 2026.
Recommended: Endorse early engagement this month, before the notification is prepared (dated to start 1 Jul 2026).
If not decided: The notification would reach APRA without prior context, with less room to discuss timing.
What could change the outcome
The top risks that could move this outlook. A preview of the full Risk Analysis tab.
129 of 340 critical integrations have no developer. Third-party integrations finish 17 Dec 2026, against a baseline of 26 Aug 2026.
The CPS 234 pre-cutover notification is not lodged and is dated 1 Sep 2026. The APRA delay briefing has not been held.
The three month parallel run is fixed, so each week of integration delay moves go-live by a week. Go-live is 80 working days behind baseline.
Workstream health
| Workstream | Complete | Position | Status |
|---|---|---|---|
| Program Management | 83% | 1 with negative float | At risk |
| Integration | 36% | 12 delayed, 13 with negative float | At risk |
| Regulatory and Compliance | 38% | 3 with negative float | At risk |
| Data Migration | 47% | 1 delayed, 1 with negative float | At risk |
| Infrastructure and Security | 82% | On plan | On plan |
| Core Platform | 59% | 1 delayed | Watch |
| Testing | 11% | 19 with negative float | At risk |
| Change and Communications | 0% | 1 with negative float | At risk |
| Cutover and Hypercare | 0% | 15 with negative float | At risk |
- Dependency links run through the whole project, so float and the critical path are calculated from schedule logic. No task is dated before the work it depends on.
- 11 of 182 activities have no owner: the APRA regulatory reporting feeds and the ten third-party integration packages. Source comments say these have no developer assigned, and Cherry reports them as Not assigned.
- The export holds no resource assignments or capacity. The $4M to $6M cost and the 4 to 6 FTE figure come from a source comment and cannot be checked against a plan or budget.
Discovery and vendor selection are complete. Build is 42% complete and the integration build is where the delay sits: third-party integrations are 8% complete with 129 critical integrations unassigned.
- 1Phase 1 is complete. Temenos T24 is selected and contracted.
- 2Phase 2 is understaffed on the integration build, the largest driver of delay. The quality gate is dated 23 Dec 2026, 80 working days after baseline.
- 3Phase 4 follows the integration build with no buffer. The parallel run is fixed at three months, so upstream delay moves go-live (8 Jul 2027) rather than shortening testing.
PhasesSelect a phase to expand
ScheduleAs at 27 Apr 2026
| WBS | Task | % | Start | Finish | Forecast | Owner | Status | Comments | |
|---|---|---|---|---|---|---|---|---|---|
| CBM | Nexus Bank: Core Banking Migration | 41% | 06 Jan 2025 | 22 Jun 2027 | 13 Oct 2027 | S. Okafor | In progress | ||
| CBM.1 | Phase 1: Discovery, Architecture and Vendor Selection | 100% | 06 Jan 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | S. Okafor | Done | ||
| CBM.1.1 | Current state assessment | 100% | 06 Jan 2025 | 14 Apr 2025 | 14 Apr 2025 ✓ | R. Singh | Done | ||
| CBM.1.1.1 | Program mobilisation and governance set-up | 100% | 06 Jan 2025 | 17 Jan 2025 | 17 Jan 2025 ✓ | S. Okafor | Done | ||
| CBM.1.1.2 | Interview business and IT stakeholders | 100% | 20 Jan 2025 | 10 Feb 2025 | 10 Feb 2025 ✓ | R. Singh | Done | ||
| CBM.1.1.3 | Catalogue existing integrations | 100% | 20 Jan 2025 | 10 Mar 2025 | 10 Mar 2025 ✓ | R. Singh | Done | 1,247 integrations catalogued. | |
| CBM.1.1.4 | Classify integrations by criticality | 100% | 11 Mar 2025 | 24 Mar 2025 | 24 Mar 2025 ✓ | R. Singh | Done | 340 classified critical path. 50 classified decommission. 857 standard migration. | |
| CBM.1.1.5 | Current state assessment report | 100% | 25 Mar 2025 | 31 Mar 2025 | 31 Mar 2025 ✓ | R. Singh | Done | ||
| CBM.1.1.6 | Business capability workshops | 100% | 20 Jan 2025 | 10 Feb 2025 | 10 Feb 2025 ✓ | R. Singh | Done | ||
| CBM.1.1.7 | Regulatory obligations mapping (CPS 234 and CPS 230) | 100% | 11 Feb 2025 | 03 Mar 2025 | 03 Mar 2025 ✓ | K. Barrett | Done | ||
| CBM.1.1.8 | Data landscape assessment | 100% | 20 Jan 2025 | 17 Feb 2025 | 17 Feb 2025 ✓ | A. Osei | Done | ||
| CBM.1.1.9 | Infrastructure and security baseline assessment | 100% | 20 Jan 2025 | 10 Feb 2025 | 10 Feb 2025 ✓ | Security Architect | Done | ||
| CBM.1.1.10 | Program business case and funding approval | 100% | 01 Apr 2025 | 14 Apr 2025 | 14 Apr 2025 ✓ | S. Okafor | Done | ||
| CBM.1.1.11 | Program risk and issue register established | 100% | 20 Jan 2025 | 24 Jan 2025 | 24 Jan 2025 ✓ | S. Okafor | Done | ||
| CBM.1.2 | Target architecture | 100% | 11 Feb 2025 | 26 May 2025 | 26 May 2025 ✓ | T. Rao | Done | ||
| CBM.1.2.1 | Define architecture principles and capability map | 100% | 11 Feb 2025 | 26 Feb 2025 | 26 Feb 2025 ✓ | T. Rao | Done | ||
| CBM.1.2.2 | Target architecture design: Temenos T24 on Azure | 100% | 27 Feb 2025 | 05 May 2025 | 05 May 2025 ✓ | Deloitte Digital | Done | ||
| CBM.1.2.3 | Security and resilience review of target architecture | 100% | 06 May 2025 | 21 May 2025 | 21 May 2025 ✓ | Security Architect | Done | Two days late because of the security review. No impact on the program. | |
| CBM.1.2.4 | Architecture board approval | 100% | 22 May 2025 | 26 May 2025 | 26 May 2025 ✓ | T. Rao | Done | ||
| CBM.1.2.5 | Milestone: Target architecture approved | — | 26 May 2025 | 26 May 2025 | 26 May 2025 ✓ | T. Rao | Done | ||
| CBM.1.3 | Vendor selection | 100% | 25 Mar 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | Procurement Lead | Done | ||
| CBM.1.3.1 | Prepare request for proposal | 100% | 25 Mar 2025 | 07 Apr 2025 | 07 Apr 2025 ✓ | Procurement Lead | Done | ||
| CBM.1.3.2 | Vendor responses and demonstrations | 100% | 08 Apr 2025 | 08 May 2025 | 08 May 2025 ✓ | Procurement Lead | Done | ||
| CBM.1.3.3 | Vendor reference checks | 100% | 09 May 2025 | 15 May 2025 | 15 May 2025 ✓ | Procurement Lead | Done | ||
| CBM.1.3.4 | Evaluate vendors and shortlist | 100% | 16 May 2025 | 29 May 2025 | 29 May 2025 ✓ | Procurement Lead | Done | ||
| CBM.1.3.5 | Board decision on core banking platform | 100% | 30 May 2025 | 03 Jun 2025 | 03 Jun 2025 ✓ | S. Okafor | Done | ||
| CBM.1.3.6 | Milestone: Temenos T24 selected | — | 03 Jun 2025 | 03 Jun 2025 | 03 Jun 2025 ✓ | S. Okafor | Done | ||
| CBM.1.3.7 | Contract negotiation with Temenos | 100% | 04 Jun 2025 | 27 Jun 2025 | 27 Jun 2025 ✓ | Procurement Lead | Done | Contract signed 15 Jun 2025. | |
| CBM.1.3.8 | Engage Deloitte Digital as system integration partner | 100% | 04 Jun 2025 | 18 Jun 2025 | 18 Jun 2025 ✓ | Procurement Lead | Done | ||
| CBM.1.3.9 | Milestone: Phase 1 complete | — | 30 Jun 2025 | 30 Jun 2025 | 30 Jun 2025 ✓ | S. Okafor | Done | ||
| CBM.2 | Phase 2: Build, Configure and Integration | 42% | 01 Jul 2025 | 30 Sep 2026 | 23 Dec 2026 | V. Chakraborty | In progress | ||
| CBM.2.1 | Environments and platform foundation | 90% | 01 Jul 2025 | 25 Nov 2025 | 29 May 2026 | Infrastructure Lead | In progress | ||
| CBM.2.1.1 | Provision Azure landing zone | 100% | 01 Jul 2025 | 28 Jul 2025 | 28 Jul 2025 ✓ | Infrastructure Lead | Done | ||
| CBM.2.1.2 | Provision development and build environments | 100% | 29 Jul 2025 | 18 Aug 2025 | 18 Aug 2025 ✓ | Infrastructure Lead | Done | ||
| CBM.2.1.3 | Install Temenos T24 base platform | 100% | 19 Aug 2025 | 15 Sep 2025 | 15 Sep 2025 ✓ | Temenos | Done | ||
| CBM.2.1.4 | Configure continuous integration and delivery pipeline | 100% | 19 Aug 2025 | 15 Sep 2025 | 15 Sep 2025 ✓ | DevOps Lead | Done | ||
| CBM.2.1.5 | Network connectivity to branches, ATMs and data centres | 100% | 29 Jul 2025 | 22 Sep 2025 | 22 Sep 2025 ✓ | Network Lead | Done | ||
| CBM.2.1.6 | Identity, access and privileged access controls | 100% | 19 Aug 2025 | 29 Sep 2025 | 29 Sep 2025 ✓ | Security Architect | Done | ||
| CBM.2.1.7 | Observability and monitoring platform | 0% | 27 Apr 2026 | 21 Oct 2025 | 29 May 2026 | DevOps Lead | Not started | ||
| CBM.2.1.8 | Cloud cost and capacity model | 100% | 29 Jul 2025 | 18 Aug 2025 | 18 Aug 2025 ✓ | Infrastructure Lead | Done | ||
| CBM.2.1.9 | Azure resilience and failover design validation | 100% | 23 Sep 2025 | 21 Oct 2025 | 21 Oct 2025 ✓ | Infrastructure Lead | Done | ||
| CBM.2.1.10 | Security controls testing and CPS 234 evidence pack | 100% | 30 Sep 2025 | 25 Nov 2025 | 25 Nov 2025 ✓ | Security Architect | Done | ||
| CBM.2.2 | Program controls | 70% | 01 Jul 2025 | 07 Jul 2026 | S. Okafor | In progress | |||
| CBM.2.2.1 | Establish change control board | 100% | 01 Jul 2025 | 07 Jul 2025 | 07 Jul 2025 ✓ | S. Okafor | Done | ||
| CBM.2.2.2 | Integrated master schedule baseline approved | 100% | 08 Jul 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | S. Okafor | Done | ||
| CBM.2.2.3 | Resourcing plan and backfill strategy | 100% | 08 Jul 2025 | 04 Aug 2025 | 04 Aug 2025 ✓ | S. Okafor | Done | ||
| CBM.2.2.4 | Benefits baseline and tracking set-up | 100% | 22 Jul 2025 | 11 Aug 2025 | 11 Aug 2025 ✓ | S. Okafor | Done | ||
| CBM.2.2.5 | Board update: Q3 2025 | 100% | 01 Oct 2025 | 08 Oct 2025 | 08 Oct 2025 ✓ | S. Okafor | Done | ||
| CBM.2.2.6 | Board update: Q4 2025 | 100% | 05 Jan 2026 | 09 Jan 2026 | 09 Jan 2026 ✓ | S. Okafor | Done | ||
| CBM.2.2.7 | Board update: Q1 2026 | 100% | 01 Apr 2026 | 09 Apr 2026 | 09 Apr 2026 ✓ | S. Okafor | Done | ||
| CBM.2.2.8 | Board update: Q2 2026 | 0% | 01 Jul 2026 | 07 Jul 2026 | S. Okafor | Not started | |||
| CBM.2.2.9 | Knowledge transfer from departing engineers | 50% | 16 Mar 2026 | 12 May 2026 | V. Chakraborty | In progress | Three senior engineers resigned in Q1. Knowledge transfer is only partly done. | ||
| CBM.2.2.10 | Recruit and onboard two replacement engineers | 50% | 16 Mar 2026 | 12 May 2026 | V. Chakraborty | In progress | Two new hires are onboarding and will not be productive for 6 to 8 weeks. | ||
| CBM.2.3 | Core platform configuration | 59% | 16 Sep 2025 | 23 Sep 2026 | 05 Nov 2026 | Temenos Configuration Lead | In progress | ||
| CBM.2.3.1 | Configure retail banking products | 100% | 16 Sep 2025 | 11 Dec 2025 | 11 Dec 2025 ✓ | Deloitte Digital | Done | Transaction accounts, savings and term deposits are configured and unit tested. | |
| CBM.2.3.2 | Configure business banking products | 85% | 12 Dec 2025 | 15 Jun 2026 | Deloitte Digital | In progress | Business accounts and overdrafts are complete. Trade finance is in final review. | ||
| CBM.2.3.3 | Configure deposits and term deposit processing | 90% | 12 Dec 2025 | 15 Jun 2026 | Deloitte Digital | In progress | Deposits are 90 percent complete. | ||
| CBM.2.3.4 | Configure loans and mortgages: interest calculation logic | 60% | 12 Dec 2025 | 15 Jul 2026 | 26 Aug 2026 | Deloitte Digital | Delayed | Variable rate mortgage interest logic is more complex than estimated. The Temenos configuration consultant has escalated to Temenos headquarters. A six week delay is expected. | |
| CBM.2.3.5 | Configure cards and card scheme interfaces | 55% | 12 Dec 2025 | 06 Jul 2026 | Deloitte Digital | In progress | |||
| CBM.2.3.6 | Configure general ledger and finance posting | 70% | 12 Dec 2025 | 05 Jun 2026 | Finance Systems Lead | In progress | |||
| CBM.2.3.7 | Configure fees, charges and pricing engine | 50% | 12 Dec 2025 | 06 Jul 2026 | Deloitte Digital | In progress | |||
| CBM.2.3.8 | Configure customer onboarding and know your customer | 45% | 12 Dec 2025 | 06 Jul 2026 | Deloitte Digital | In progress | |||
| CBM.2.3.9 | Configure customer limits and risk controls | 0% | 16 Jun 2026 | 10 Aug 2026 | Deloitte Digital | Not started | |||
| CBM.2.3.10 | Configure reporting and statements in T24 | 0% | 09 Jun 2026 | 03 Aug 2026 | Deloitte Digital | Not started | |||
| CBM.2.3.11 | Configure collateral and security management | 0% | 27 Aug 2026 | 09 Sep 2026 | 22 Oct 2026 | Deloitte Digital | Not started | ||
| CBM.2.3.12 | Configure interest and fee accrual engine | 0% | 16 Jun 2026 | 17 Aug 2026 | Deloitte Digital | Not started | |||
| CBM.2.3.13 | Configure batch and end-of-day processing | 80% | 12 Dec 2025 | 05 Jun 2026 | Deloitte Digital | In progress | |||
| CBM.2.3.14 | Core platform configuration review | 0% | 23 Oct 2026 | 23 Sep 2026 | 05 Nov 2026 | Temenos Configuration Lead | Not started | ||
| CBM.2.4 | Integration build: channels and core | 55% | 19 Aug 2025 | 17 Aug 2026 | 24 Sep 2026 | V. Chakraborty | In progress | ||
| CBM.2.4.1 | Integration design standards and review | 100% | 19 Aug 2025 | 15 Sep 2025 | 15 Sep 2025 ✓ | V. Chakraborty | Done | ||
| CBM.2.4.2 | Core banking API layer: T24 REST APIs | 100% | 16 Sep 2025 | 25 Nov 2025 | 25 Nov 2025 ✓ | V. Chakraborty | Done | Core API layer is complete and tested. L. Obi resigned after completion and knowledge transfer was only partly done. | |
| CBM.2.4.3 | Internet banking portal integration | 100% | 26 Nov 2025 | 09 Mar 2026 | 09 Mar 2026 ✓ | Digital Team | Done | Internet banking is integrated with T24 and performance tested to 50,000 concurrent users. | |
| CBM.2.4.4 | Mobile banking app integration: iOS | 75% | 26 Nov 2025 | 02 Jul 2026 | 23 Jul 2026 | T. Ferreira (resigned) | In progress | T. Ferreira was the mobile lead and resigned on 15 Mar. Handover is incomplete and a new developer is onboarding. A three week delay is expected. | |
| CBM.2.4.5 | Mobile banking app integration: Android | 70% | 26 Nov 2025 | 02 Jul 2026 | 23 Jul 2026 | Digital Team | In progress | ||
| CBM.2.4.6 | Payments: New Payments Platform (NPP) | 100% | 26 Nov 2025 | 23 Feb 2026 | 23 Feb 2026 ✓ | V. Chakraborty | Done | ||
| CBM.2.4.7 | Payments: BPAY | 75% | 26 Nov 2025 | 06 May 2026 | 20 May 2026 | V. Chakraborty | In progress | ||
| CBM.2.4.8 | Payments: SWIFT and correspondent banking | 30% | 26 Nov 2025 | 30 Jul 2026 | 08 Sep 2026 | V. Chakraborty | Delayed | SWIFT is 30 percent complete because of complex correspondent banking logic. SWIFT and Direct Debit are on the path to SIT. | |
| CBM.2.4.9 | Payments: Direct Debit | 20% | 26 Nov 2025 | 30 Jul 2026 | 08 Sep 2026 | V. Chakraborty | Delayed | ||
| CBM.2.4.10 | Branch teller interface integration: 42 branches | 40% | 26 Nov 2025 | 02 Jul 2026 | Branch Operations | In progress | Branch teller integration is 40 percent complete on the standard T24 teller interface. | ||
| CBM.2.4.11 | ATM network integration: 180 ATMs | 15% | 26 Nov 2025 | 02 Jul 2026 | IT Operations | In progress | Diebold Nixdorf integration. The ATM network is 15 percent complete. | ||
| CBM.2.4.12 | API gateway and security policies | 100% | 26 Nov 2025 | 23 Jan 2026 | 23 Jan 2026 ✓ | V. Chakraborty | Done | ||
| CBM.2.4.13 | Event streaming and messaging backbone | 100% | 26 Nov 2025 | 23 Feb 2026 | 23 Feb 2026 ✓ | V. Chakraborty | Done | ||
| CBM.2.4.14 | Integration monitoring and alerting | 100% | 27 Jan 2026 | 23 Mar 2026 | 23 Mar 2026 ✓ | DevOps Lead | Done | ||
| CBM.2.4.15 | Open banking data sharing APIs | 45% | 27 Jan 2026 | 03 Jun 2026 | Digital Team | In progress | |||
| CBM.2.4.16 | Integration test harness and service mocks | 100% | 26 Nov 2025 | 09 Feb 2026 | 09 Feb 2026 ✓ | V. Chakraborty | Done | ||
| CBM.2.4.17 | APRA regulatory reporting feeds | 0% | 01 Jun 2026 | 17 Aug 2026 | 24 Sep 2026 | Not assigned | Not started | Regulatory reporting feeds are not started and no developer is assigned. APRA requires uninterrupted regulatory reporting, so these must be ready before go-live. | |
| CBM.2.5 | Integration build: internal systems | 68% | 26 Nov 2025 | 20 May 2026 | Integration Lead | In progress | |||
| CBM.2.5.1 | Integrate Risk and credit decisioning | 85% | 26 Nov 2025 | 20 May 2026 | Risk Systems Lead | In progress | |||
| CBM.2.5.2 | Integrate Anti-money laundering and transaction monitoring | 80% | 26 Nov 2025 | 20 May 2026 | Compliance Systems Lead | In progress | |||
| CBM.2.5.3 | Integrate Fraud detection platform | 75% | 26 Nov 2025 | 20 May 2026 | Fraud Systems Lead | In progress | |||
| CBM.2.5.4 | Integrate Customer relationship management | 70% | 26 Nov 2025 | 20 May 2026 | CRM Lead | In progress | |||
| CBM.2.5.5 | Integrate Data warehouse and management reporting | 65% | 26 Nov 2025 | 20 May 2026 | Data Platform Lead | In progress | |||
| CBM.2.5.6 | Integrate Document management and statements | 60% | 26 Nov 2025 | 20 May 2026 | Digital Team | In progress | |||
| CBM.2.5.7 | Integrate Contact centre and telephony | 55% | 26 Nov 2025 | 20 May 2026 | IT Operations | In progress | |||
| CBM.2.5.8 | Integrate Treasury and markets | 50% | 26 Nov 2025 | 20 May 2026 | Treasury Systems Lead | In progress | |||
| CBM.2.6 | Integration build: third-party | 8% | 01 Sep 2025 | 30 Sep 2026 | 23 Dec 2026 | Vacant | In progress | ||
| CBM.2.6.1 | Integrate third parties: payments and clearing partners | 8% | 01 Sep 2025 | 26 Aug 2026 | 17 Dec 2026 | Not assigned | Understaffed | 211 of 340 critical integrations are assigned. 129 have no developer because A. Park, who owned these, resigned. At current team velocity of three engineers they would complete in Jan 2027. External specialists of 4 to 6 FTE for three months are estimated at $4M to $6M and need board approval. | |
| CBM.2.6.2 | Integrate third parties: credit bureaus and identity services | 8% | 01 Sep 2025 | 26 Aug 2026 | 17 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.3 | Integrate third parties: card scheme and processors | 8% | 01 Sep 2025 | 26 Aug 2026 | 17 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.4 | Integrate third parties: merchant and acquiring partners | 8% | 12 Jan 2026 | 27 Aug 2026 | 18 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.5 | Integrate third parties: government and tax agencies | 8% | 12 Jan 2026 | 27 Aug 2026 | 18 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.6 | Integrate third parties: insurance and wealth partners | 8% | 12 Jan 2026 | 27 Aug 2026 | 18 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.7 | Integrate third parties: broker and aggregator channels | 8% | 30 Mar 2026 | 26 Aug 2026 | 17 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.8 | Integrate third parties: open banking data recipients | 8% | 30 Mar 2026 | 26 Aug 2026 | 17 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.9 | Integrate third parties: fintech and API partners | 8% | 30 Mar 2026 | 26 Aug 2026 | 17 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.10 | Integrate third parties: regional and other partners | 8% | 30 Mar 2026 | 26 Aug 2026 | 17 Dec 2026 | Not assigned | Understaffed | ||
| CBM.2.6.11 | Integration build quality gate | 0% | 21 Dec 2026 | 01 Sep 2026 | 23 Dec 2026 | V. Chakraborty | Not started | ||
| CBM.2.6.12 | Milestone: Phase 2 complete | — | 23 Dec 2026 | 30 Sep 2026 | 23 Dec 2026 | V. Chakraborty | Not started | ||
| CBM.3 | Phase 3: Customer Data Migration | 47% | 01 Jul 2025 | 06 Nov 2026 | A. Osei | In progress | |||
| CBM.3.1 | Data analysis and quality | 91% | 01 Jul 2025 | 11 May 2026 | A. Osei | In progress | |||
| CBM.3.1.1 | Data catalogue and schema mapping: legacy to T24 | 100% | 01 Jul 2025 | 25 Sep 2025 | 25 Sep 2025 ✓ | A. Osei | Done | 847 data entities mapped from legacy to T24 schema. | |
| CBM.3.1.2 | Data quality audit: 2.1M customer records | 100% | 26 Sep 2025 | 07 Jan 2026 | 07 Jan 2026 ✓ | Temenos | Done | 340,000 anomalies found: 180K duplicate or linked, 95K dormant, 65K outdated beneficiary data. | |
| CBM.3.1.3 | Classify anomalies by category and impact | 100% | 08 Jan 2026 | 19 Feb 2026 | 19 Feb 2026 ✓ | A. Osei | Done | ||
| CBM.3.1.4 | Agree dormant account strategy with legal | 100% | 20 Feb 2026 | 02 Apr 2026 | 02 Apr 2026 ✓ | K. Barrett | Done | ||
| CBM.3.1.5 | Anomaly remediation plan | 60% | 20 Feb 2026 | 11 May 2026 | A. Osei | In progress | Duplicate remediation is complex and needs customer outreach. | ||
| CBM.3.2 | Remediation and tooling | 31% | 26 Sep 2025 | 28 Jul 2026 | 08 Sep 2026 | A. Osei | In progress | ||
| CBM.3.2.1 | Duplicate account remediation: 180K accounts | 20% | 20 Feb 2026 | 28 Jul 2026 | 08 Sep 2026 | A. Osei | Delayed | Customer-linked duplicates require manual review. Duplicate remediation is six weeks behind, which puts the migration dry run at risk. | |
| CBM.3.2.2 | Outdated beneficiary data remediation: 65K records | 25% | 20 Feb 2026 | 30 Jun 2026 | A. Osei | In progress | |||
| CBM.3.2.3 | Dormant account remediation: 95K accounts | 0% | 27 Apr 2026 | 30 Jun 2026 | 20 Jul 2026 | A. Osei | Not started | ||
| CBM.3.2.4 | Migration tooling and ETL build | 70% | 26 Sep 2025 | 04 May 2026 | Temenos | In progress | |||
| CBM.3.2.5 | Reconciliation framework and controls | 0% | 05 May 2026 | 28 Jul 2026 | A. Osei | Not started | |||
| CBM.3.3 | Migration rehearsals | 24% | 20 Feb 2026 | 06 Nov 2026 | A. Osei | In progress | |||
| CBM.3.3.1 | Data privacy and consent review for migration | 100% | 20 Feb 2026 | 19 Mar 2026 | 19 Mar 2026 ✓ | K. Barrett | Done | ||
| CBM.3.3.2 | Customer outreach for linked duplicate accounts | 0% | 12 May 2026 | 07 Jul 2026 | Branch Operations | Not started | |||
| CBM.3.3.3 | Data archiving and retention strategy | 56% | 07 Apr 2026 | 11 May 2026 | A. Osei | In progress | |||
| CBM.3.3.4 | Migration cutover runbook | 0% | 05 May 2026 | 16 Jun 2026 | A. Osei | Not started | |||
| CBM.3.3.5 | Migration dry run 1: full data set | 0% | 09 Sep 2026 | 14 Aug 2026 | 22 Sep 2026 | A. Osei | Not started | Requires all anomaly remediation to be complete. A slip in duplicate remediation pushes the dry run into September. | |
| CBM.3.3.6 | Migration dry run 2: full data set and reconciliation | 0% | 23 Sep 2026 | 28 Aug 2026 | 07 Oct 2026 | A. Osei | Not started | ||
| CBM.3.3.7 | Migration dress rehearsal: simulated cutover | 0% | 02 Nov 2026 | 06 Nov 2026 | A. Osei | Not started | Full weekend cutover simulation. Target is completion inside the 62-hour window. | ||
| CBM.4 | Phase 4: Testing and Parallel Run | 10% | 02 Feb 2026 | 09 Mar 2027 | 02 Jul 2027 | L. Ferreira | In progress | ||
| CBM.4.1 | Test preparation | 19% | 02 Feb 2026 | 21 Sep 2026 | L. Ferreira | In progress | |||
| CBM.4.1.1 | Test strategy and plan | 40% | 02 Mar 2026 | 26 May 2026 | L. Ferreira | In progress | Test data approach agreed. | ||
| CBM.4.1.2 | Provision SIT and performance environments | 5% | 13 Apr 2026 | 27 Jul 2026 | IT Operations | In progress | SIT environment is being provisioned on Azure. | ||
| CBM.4.1.3 | Test case design: SIT and UAT scripts | 35% | 02 Feb 2026 | 12 May 2026 | L. Ferreira | In progress | |||
| CBM.4.1.4 | Test data preparation | 0% | 13 May 2026 | 08 Jul 2026 | L. Ferreira | Not started | |||
| CBM.4.1.5 | Disaster recovery environment build | 0% | 28 Jul 2026 | 21 Sep 2026 | Infrastructure Lead | Not started | |||
| CBM.4.1.6 | Test governance and defect triage set-up | 100% | 02 Mar 2026 | 13 Mar 2026 | 13 Mar 2026 ✓ | L. Ferreira | Done | ||
| CBM.4.1.7 | Regression test suite automation | 0% | 13 May 2026 | 08 Jul 2026 | L. Ferreira | Not started | |||
| CBM.4.2 | System integration testing (SIT) | 0% | 24 Dec 2026 | 30 Oct 2026 | 25 Feb 2027 | L. Ferreira | Not started | ||
| CBM.4.2.1 | SIT cycle 1: core platform and channels | 0% | 24 Dec 2026 | 21 Sep 2026 | 15 Jan 2027 | L. Ferreira | Not started | Cannot start until all 340 critical integrations are complete. | |
| CBM.4.2.2 | SIT cycle 2: payments and internal systems | 0% | 18 Jan 2027 | 12 Oct 2026 | 05 Feb 2027 | L. Ferreira | Not started | ||
| CBM.4.2.3 | SIT cycle 3: third parties and regulatory reporting | 0% | 08 Feb 2027 | 30 Oct 2026 | 25 Feb 2027 | L. Ferreira | Not started | Current trajectory: SIT completes in Feb 2027, about 3 months after the SIT target. | |
| CBM.4.2.4 | Performance and volume testing | 0% | 18 Jan 2027 | 08 Oct 2026 | 03 Feb 2027 | L. Ferreira | Not started | ||
| CBM.4.2.5 | Disaster recovery failover test | 0% | 04 Feb 2027 | 16 Oct 2026 | 11 Feb 2027 | IT Operations | Not started | ||
| CBM.4.2.6 | Security penetration test | 0% | 18 Jan 2027 | 13 Oct 2026 | 08 Feb 2027 | Security Architect | Not started | ||
| CBM.4.2.7 | Branch and ATM end-to-end testing | 0% | 08 Feb 2027 | 28 Oct 2026 | 23 Feb 2027 | Branch Operations | Not started | ||
| CBM.4.2.8 | Operational readiness testing | 0% | 04 Feb 2027 | 26 Oct 2026 | 19 Feb 2027 | IT Operations | Not started | ||
| CBM.4.2.9 | Business continuity test | 0% | 12 Feb 2027 | 23 Oct 2026 | 18 Feb 2027 | IT Operations | Not started | ||
| CBM.4.2.10 | Milestone: SIT exit approved | — | 25 Feb 2027 | 30 Oct 2026 | 25 Feb 2027 | L. Ferreira | Not started | ||
| CBM.4.3 | User acceptance testing (UAT) | 0% | 08 Feb 2027 | 14 Dec 2026 | 13 Apr 2027 | L. Ferreira | Not started | ||
| CBM.4.3.1 | UAT preparation and business user training | 0% | 08 Feb 2027 | 02 Nov 2026 | 26 Feb 2027 | Business Teams | Not started | ||
| CBM.4.3.2 | UAT cycle 1: retail banking | 0% | 01 Mar 2027 | 23 Nov 2026 | 19 Mar 2027 | Business Teams | Not started | Six week minimum for UAT. It cannot be compressed for a project of this complexity. | |
| CBM.4.3.3 | UAT cycle 2: business banking and payments | 0% | 22 Mar 2027 | 14 Dec 2026 | 13 Apr 2027 | Business Teams | Not started | ||
| CBM.4.3.4 | Milestone: UAT exit approved | — | 13 Apr 2027 | 14 Dec 2026 | 13 Apr 2027 | L. Ferreira | Not started | ||
| CBM.4.4 | Parallel run | 0% | 14 Apr 2027 | 09 Mar 2027 | 02 Jul 2027 | S. Okafor | Not started | ||
| CBM.4.4.1 | Parallel run: old and new systems running together | 0% | 14 Apr 2027 | 05 Mar 2027 | 30 Jun 2027 | All teams | Not started | Non-negotiable. APRA and internal risk policy require both systems to run simultaneously for 3 months. | |
| CBM.4.4.2 | Parallel run: daily reconciliation reporting | 0% | 14 Apr 2027 | 05 Mar 2027 | 30 Jun 2027 | A. Osei | Not started | ||
| CBM.4.4.3 | Parallel run exit review and reconciliation sign-off | 0% | 01 Jul 2027 | 09 Mar 2027 | 02 Jul 2027 | S. Okafor | Not started | ||
| CBM.4.4.4 | Milestone: Parallel run exit approved | — | 02 Jul 2027 | 09 Mar 2027 | 02 Jul 2027 | S. Okafor | Not started | ||
| CBM.5 | Phase 5: Regulatory and Compliance (APRA CPS 234) | 33% | 15 Jan 2025 | 21 Apr 2027 | 30 Jun 2027 | M. Andersen | In progress | ||
| CBM.5.1 | Notifications | 43% | 15 Jan 2025 | 05 Mar 2027 | 30 Jun 2027 | M. Andersen | In progress | ||
| CBM.5.1.1 | APRA initial project notification | 100% | 15 Jan 2025 | 22 Jan 2025 | 22 Jan 2025 ✓ | M. Andersen | Done | APRA notified. CPS 234 compliance framework engaged. | |
| CBM.5.1.2 | CPS 234 compliance assessment | 100% | 01 Apr 2025 | 27 Jun 2025 | 27 Jun 2025 ✓ | K. Barrett | Done | ||
| CBM.5.1.3 | Proactive APRA delay briefing | 0% | 28 Apr 2026 | 30 Apr 2026 | M. Andersen | Not started | Recommended immediately. APRA responds better to proactive disclosure. The CEO and CRO should attend. It is not yet scheduled. | ||
| CBM.5.1.4 | Prepare CPS 234 pre-cutover notification | 0% | 01 Jul 2026 | 01 Sep 2026 | M. Andersen | Not started | A six month minimum pre-notification applies for a Mar 2027 go-live. Board members carry personal liability. | ||
| CBM.5.1.5 | Milestone: CPS 234 pre-cutover notification lodged | — | 01 Sep 2026 | 01 Sep 2026 | M. Andersen | Not started | Not lodged. The Sep 2026 deadline is at risk. | ||
| CBM.5.1.6 | Privacy impact assessment | 100% | 01 Sep 2025 | 26 Sep 2025 | 26 Sep 2025 ✓ | K. Barrett | Done | ||
| CBM.5.1.7 | CPS 230 operational resilience alignment | 60% | 02 Feb 2026 | 28 Apr 2026 | K. Barrett | In progress | |||
| CBM.5.1.8 | Board risk committee briefing on delay and recovery plan | 0% | 01 May 2026 | 07 May 2026 | M. Andersen | Not started | |||
| CBM.5.1.9 | External audit of CPS 234 controls | 0% | 02 Sep 2026 | 14 Oct 2026 | M. Andersen | Not started | |||
| CBM.5.1.10 | APRA regulatory reporting parallel run | 0% | 14 Apr 2027 | 05 Mar 2027 | 30 Jun 2027 | Compliance Systems Lead | Not started | ||
| CBM.5.2 | Quarterly APRA reporting | 50% | 01 Jul 2025 | 21 Apr 2027 | M. Andersen | In progress | |||
| CBM.5.2.1 | Quarterly APRA progress report: Q2 2025 | 100% | 01 Jul 2025 | 21 Jul 2025 | 21 Jul 2025 ✓ | M. Andersen | Done | ||
| CBM.5.2.2 | Quarterly APRA progress report: Q3 2025 | 100% | 01 Oct 2025 | 22 Oct 2025 | 22 Oct 2025 ✓ | M. Andersen | Done | ||
| CBM.5.2.3 | Quarterly APRA progress report: Q4 2025 | 100% | 05 Jan 2026 | 23 Jan 2026 | 23 Jan 2026 ✓ | M. Andersen | Done | ||
| CBM.5.2.4 | Quarterly APRA progress report: Q1 2026 | 100% | 01 Apr 2026 | 23 Apr 2026 | 23 Apr 2026 ✓ | M. Andersen | Done | ||
| CBM.5.2.5 | Quarterly APRA progress report: Q2 2026 | 0% | 01 Jul 2026 | 21 Jul 2026 | M. Andersen | Not started | Reports have not disclosed the integration delays. Disclosing proactively is recommended. | ||
| CBM.5.2.6 | Quarterly APRA progress report: Q3 2026 | 0% | 01 Oct 2026 | 22 Oct 2026 | M. Andersen | Not started | |||
| CBM.5.2.7 | Quarterly APRA progress report: Q4 2026 | 0% | 04 Jan 2027 | 22 Jan 2027 | M. Andersen | Not started | |||
| CBM.5.2.8 | Quarterly APRA progress report: Q1 2027 | 0% | 01 Apr 2027 | 21 Apr 2027 | M. Andersen | Not started | |||
| CBM.5.3 | Customer regulatory communications | 0% | 04 May 2026 | 11 Dec 2026 | K. Barrett | Not started | |||
| CBM.5.3.1 | Customer communications plan: 2.1M customers | 0% | 04 May 2026 | 29 Jun 2026 | K. Barrett | Not started | The plan needs 8 weeks and should start by May 2026. The communications team is unaware this is assigned to them. | ||
| CBM.5.3.2 | ASIC engagement on customer notices | 0% | 30 Jun 2026 | 13 Jul 2026 | K. Barrett | Not started | |||
| CBM.5.3.3 | Legal review, ASIC alignment and executive approval | 0% | 30 Jun 2026 | 27 Jul 2026 | K. Barrett | Not started | |||
| CBM.5.3.4 | Issue customer notifications about the migration | 0% | 01 Oct 2026 | 05 Nov 2026 | Communications Team | Not started | |||
| CBM.5.3.5 | Branch and contact centre staff briefings | 0% | 02 Nov 2026 | 27 Nov 2026 | Branch Operations | Not started | |||
| CBM.5.3.6 | Customer dispute and complaints handling readiness | 0% | 02 Nov 2026 | 11 Dec 2026 | Customer Care Lead | Not started | |||
| CBM.6 | Phase 6: Cutover and Hypercare | 0% | 14 Apr 2027 | 22 Jun 2027 | 13 Oct 2027 | S. Okafor | Not started | ||
| CBM.6.1 | Cutover preparation | 0% | 14 Apr 2027 | 11 Mar 2027 | 06 Jul 2027 | S. Okafor | Not started | ||
| CBM.6.1.1 | Cutover planning and weekend war room set-up | 0% | 14 Apr 2027 | 15 Feb 2027 | 25 May 2027 | S. Okafor | Not started | Go and no-go criteria, rollback triggers, communications tree, war room roster, vendor on-call (Temenos, Deloitte). | |
| CBM.6.1.2 | Cutover rollback rehearsal | 0% | 26 May 2027 | 22 Feb 2027 | 01 Jun 2027 | S. Okafor | Not started | ||
| CBM.6.1.3 | Hypercare war room roster and shifts | 0% | 26 May 2027 | 01 Mar 2027 | 08 Jun 2027 | S. Okafor | Not started | ||
| CBM.6.1.4 | Vendor on-call agreements: Temenos and Deloitte | 0% | 26 May 2027 | 01 Mar 2027 | 08 Jun 2027 | Procurement Lead | Not started | ||
| CBM.6.1.5 | Cutover customer messaging: day-of communications | 0% | 02 Jun 2027 | 01 Mar 2027 | 08 Jun 2027 | Communications Team | Not started | ||
| CBM.6.1.6 | Branch cutover readiness check: 42 branches | 0% | 02 Jun 2027 | 01 Mar 2027 | 08 Jun 2027 | Branch Operations | Not started | ||
| CBM.6.1.7 | Go and no-go decision | 0% | 05 Jul 2027 | 11 Mar 2027 | 06 Jul 2027 | S. Okafor | Not started | ||
| CBM.6.2 | Cutover and go-live | 0% | 07 Jul 2027 | 15 Mar 2027 | 08 Jul 2027 | S. Okafor | Not started | ||
| CBM.6.2.1 | Cutover weekend: production migration and switch | 0% | 07 Jul 2027 | 15 Mar 2027 | 08 Jul 2027 | All teams | Not started | 72-hour production window. All 2.1M customers. | |
| CBM.6.2.2 | Milestone: GO-LIVE: Core Banking Migration | — | 08 Jul 2027 | 15 Mar 2027 | 08 Jul 2027 | All teams | Not started | ||
| CBM.6.3 | Hypercare | 0% | 09 Jul 2027 | 22 Jun 2027 | 13 Oct 2027 | S. Okafor | Not started | ||
| CBM.6.3.1 | Hypercare: intensive support | 0% | 09 Jul 2027 | 16 Apr 2027 | 09 Aug 2027 | All teams | Not started | ||
| CBM.6.3.2 | Hypercare: standard support and defect burn-down | 0% | 10 Aug 2027 | 21 May 2027 | 13 Sep 2027 | All teams | Not started | ||
| CBM.6.3.3 | Maintain rollback capability | 0% | 09 Jul 2027 | 02 Jun 2027 | 23 Sep 2027 | S. Okafor | Not started | Rollback is maintained for 90 days. | |
| CBM.6.3.4 | Post-migration reconciliation and sign-off | 0% | 10 Aug 2027 | 14 May 2027 | 06 Sep 2027 | A. Osei | Not started | ||
| CBM.6.3.5 | Post go-live defect triage | 0% | 09 Jul 2027 | 16 Apr 2027 | 09 Aug 2027 | L. Ferreira | Not started | ||
| CBM.6.3.6 | Customer complaint monitoring | 0% | 09 Jul 2027 | 12 May 2027 | 02 Sep 2027 | Customer Care Lead | Not started | ||
| CBM.6.3.7 | Knowledge transfer to operations | 0% | 10 Aug 2027 | 28 May 2027 | 20 Sep 2027 | V. Chakraborty | Not started | ||
| CBM.6.3.8 | Post go-live APRA report | 0% | 09 Jul 2027 | 07 Apr 2027 | 29 Jul 2027 | M. Andersen | Not started | ||
| CBM.6.3.9 | Decommission legacy platform | 0% | 24 Sep 2027 | 15 Jun 2027 | 06 Oct 2027 | IT Operations | Not started | ||
| CBM.6.3.10 | Post-implementation review | 0% | 07 Oct 2027 | 22 Jun 2027 | 13 Oct 2027 | S. Okafor | Not started | ||
| CBM.6.3.11 | Milestone: Hypercare complete | — | 13 Oct 2027 | 22 Jun 2027 | 13 Oct 2027 | S. Okafor | Not started |
211 rows from the Nexus Bank demonstration schedule export. Finish dates in red are past plan or forecast beyond plan.
Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal.
129 critical integrations unassigned after three resignations
Third-party integrations (CBM.2.6.1 to CBM.2.6.10, no owner) are 8% complete. The source comment says 211 of 340 critical integrations are assigned, 129 have no developer because A. Park resigned, and the current team of three engineers would finish in Jan 2027. The iOS lead (T. Ferreira) and L. Obi also resigned, and knowledge transfer is only partly done.
The integration build quality gate is dated 23 Dec 2026, 80 working days after its baseline, and it has -80 days of float. SIT, UAT, the parallel run and go-live follow it, so go-live is dated 8 Jul 2027, 80 working days after baseline. Two replacement engineers are onboarding and need 6 to 8 weeks to become productive (source comment).
CPS 234 pre-cutover notification not lodged
The notification is a milestone dated 1 Sep 2026 (CBM.5.1.5). Preparing it (CBM.5.1.4, M. Andersen) starts 1 Jul 2026 and is 0% complete. The proactive APRA delay briefing (CBM.5.1.3) is in the schedule at 0%. Source comments say a six month minimum pre-notification applies and that board members carry personal liability.
The notification date is fixed against the 15 Mar 2027 baseline, while the integration build behind it is running late. The schedule gives the notification 130 working days of float, so the schedule logic does not show it driving go-live. The risk is regulatory: lodging a credible notification while integration status is behind. Whether the date can move is a question for APRA and the CRO, and the export does not say.
The three month parallel run compresses every upstream delay into go-live
APRA and internal risk policy require the old and new systems to run together for three months (CBM.4.4.1, source comment). It follows UAT, which follows SIT, which follows the integration build.
SIT is dated to start 24 Dec 2026, 80 working days after baseline, and the parallel run is dated 14 Apr 2027 to 30 Jun 2027. Every one of these stages carries the same negative float (-80 days), so none has room to absorb a further slip.
Duplicate account remediation is six weeks behind
The data quality audit found 340,000 anomalies: 180K duplicate or linked, 95K dormant and 65K with outdated beneficiary data. Duplicate account remediation (CBM.3.2.1, A. Osei) is 20% complete and finishes 8 Sep 2026, against a baseline of 28 Jul 2026. Customer-linked duplicates need manual review (source comment).
The task has 90 working days of float, so it is not driving go-live in the schedule logic. Migration dry run 1 (CBM.3.3.5) depends on it and is dated 9 Sep 2026, against a baseline start of 3 Aug 2026. Migrating anomalous financial data is not permitted, so the remediation must finish before cutover.
Customer communications plan has not started
The plan for 2.1M customers (CBM.5.3.1, K. Barrett) is dated to start 4 May 2026 and is 0% complete. The source comment says it needs 8 weeks, and that the communications team is unaware it is assigned to them.
Customer notifications (CBM.5.3.3) are dated from 1 Oct 2026, and the plan has 126 working days of float. The risk is a start that slips because the owner team has not been briefed, which would leave less than the 8 weeks the plan needs.
Actions 1 and 2 depend on executive decisions. See Decisions Required on the Executive Overview.
Observed = read directly from the schedule export. Calculated = derived from export values. Modelled = a scenario, not a forecast. Recommended = Cherry's proposal. Owners and due dates are Cherry recommendations. Urgency is measured from the 27 Apr 2026 status date: This week = due within 5 working days, This month = within 20, Monitor = later. The export does not hold action owners or due dates.
Engage external integration specialists to close the 129-integration gap
The gap cannot be closed with internal hires alone in the time available.
Owner: Program Director (S. Okafor), proceeding on approval of Decision 1. Due: 1 May 2026. Engage a specialist integration consultancy under a fixed scope to complete the integrations with no developer. The source comment estimates $4M to $6M for 4 to 6 FTE over three months.
Brief APRA on the delay and the recovery plan
Do not wait for the notification date to raise the timeline risk.
Owner: CRO (M. Andersen), proceeding on endorsement of Decision 2. Due: 29 May 2026. Hold the briefing (CBM.5.1.3) with the current position, the cause of delay and the mitigation under way, before the CPS 234 notification is prepared. Disclose the delay in the Q2 2026 APRA progress report as well.
Brief the communications team and start the customer communications plan
The plan needs 8 weeks and its owner team has not been briefed.
Owner: Legal and Regulatory Lead (K. Barrett). Due: 4 May 2026, the planned start. Brief the communications lead on the cutover timeline, the parallel run window and the 2.1M customer scope, so the plan starts on its dated day.
Recover duplicate account remediation before dry run 1
The task is six weeks behind and customer-linked duplicates need manual review.
Owner: Data Migration Lead (A. Osei). Due: 29 May 2026. Split the 180K duplicates by whether they have active transactions, and add manual review capacity for those first. Report the count remaining weekly against the 28 Jul 2026 baseline finish.
Act on the exit interview findings to keep the remaining integration engineers
Three senior engineers left in Q1, and the build cannot absorb more departures.
Owner: Integration Lead (V. Chakraborty). Due: 29 May 2026. Complete knowledge transfer from the departing engineers (CBM.2.3.x, 50% complete) and agree retention steps for the engineers who remain.
Program Management26 activities · lead: S. Okafor
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Program mobilisation and governance set-up | 06 Jan 2025 | 17 Jan 2025 | S. Okafor | 100% | Done | |
| Interview business and IT stakeholders | 20 Jan 2025 | 10 Feb 2025 | R. Singh | 100% | Done | |
| Current state assessment report | 25 Mar 2025 | 31 Mar 2025 | R. Singh | 100% | Done | |
| Business capability workshops | 20 Jan 2025 | 10 Feb 2025 | R. Singh | 100% | Done | |
| Program business case and funding approval | 01 Apr 2025 | 14 Apr 2025 | S. Okafor | 100% | Done | |
| Program risk and issue register established | 20 Jan 2025 | 24 Jan 2025 | S. Okafor | 100% | Done | |
| Prepare request for proposal | 25 Mar 2025 | 07 Apr 2025 | Procurement Lead | 100% | Done | |
| Vendor responses and demonstrations | 08 Apr 2025 | 08 May 2025 | Procurement Lead | 100% | Done | |
| Vendor reference checks | 09 May 2025 | 15 May 2025 | Procurement Lead | 100% | Done | |
| Evaluate vendors and shortlist | 16 May 2025 | 29 May 2025 | Procurement Lead | 100% | Done | |
| Board decision on core banking platform | 30 May 2025 | 03 Jun 2025 | S. Okafor | 100% | Done | |
| Milestone: Temenos T24 selected | 03 Jun 2025 | 03 Jun 2025 | S. Okafor | — | Done | |
| Contract negotiation with Temenos | 04 Jun 2025 | 27 Jun 2025 | Procurement Lead | 100% | Done | |
| Engage Deloitte Digital as system integration partner | 04 Jun 2025 | 18 Jun 2025 | Procurement Lead | 100% | Done | |
| Milestone: Phase 1 complete | 30 Jun 2025 | 30 Jun 2025 | S. Okafor | — | Done | |
| Establish change control board | 01 Jul 2025 | 07 Jul 2025 | S. Okafor | 100% | Done | |
| Integrated master schedule baseline approved | 08 Jul 2025 | 21 Jul 2025 | S. Okafor | 100% | Done | |
| Resourcing plan and backfill strategy | 08 Jul 2025 | 04 Aug 2025 | S. Okafor | 100% | Done | |
| Benefits baseline and tracking set-up | 22 Jul 2025 | 11 Aug 2025 | S. Okafor | 100% | Done | |
| Board update: Q3 2025 | 01 Oct 2025 | 08 Oct 2025 | S. Okafor | 100% | Done | |
| Board update: Q4 2025 | 05 Jan 2026 | 09 Jan 2026 | S. Okafor | 100% | Done | |
| Board update: Q1 2026 | 01 Apr 2026 | 09 Apr 2026 | S. Okafor | 100% | Done | |
| Board update: Q2 2026 | 01 Jul 2026 | 07 Jul 2026 | S. Okafor | 0% | Not started | |
| Knowledge transfer from departing engineers | 16 Mar 2026 | 12 May 2026 | V. Chakraborty | 50% | In progress | |
| Recruit and onboard two replacement engineers | 16 Mar 2026 | 12 May 2026 | V. Chakraborty | 50% | In progress | |
| Post-implementation review | 07 Oct 2027 | 13 Oct 2027 | S. Okafor | 0% | Not started |
Integration38 activities · lead: V. Chakraborty
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Catalogue existing integrations | 20 Jan 2025 | 10 Mar 2025 | R. Singh | 100% | Done | |
| Classify integrations by criticality | 11 Mar 2025 | 24 Mar 2025 | R. Singh | 100% | Done | |
| Integration design standards and review | 19 Aug 2025 | 15 Sep 2025 | V. Chakraborty | 100% | Done | |
| Core banking API layer: T24 REST APIs | 16 Sep 2025 | 25 Nov 2025 | V. Chakraborty | 100% | Done | |
| Internet banking portal integration | 26 Nov 2025 | 09 Mar 2026 | Digital Team | 100% | Done | |
| Mobile banking app integration: iOS | 26 Nov 2025 | 23 Jul 2026 | T. Ferreira (resigned) | 75% | In progress | |
| Mobile banking app integration: Android | 26 Nov 2025 | 23 Jul 2026 | Digital Team | 70% | In progress | |
| Payments: New Payments Platform (NPP) | 26 Nov 2025 | 23 Feb 2026 | V. Chakraborty | 100% | Done | |
| Payments: BPAY | 26 Nov 2025 | 20 May 2026 | V. Chakraborty | 75% | In progress | |
| Payments: SWIFT and correspondent banking | 26 Nov 2025 | 08 Sep 2026 | V. Chakraborty | 30% | Delayed | |
| Payments: Direct Debit | 26 Nov 2025 | 08 Sep 2026 | V. Chakraborty | 20% | Delayed | |
| Branch teller interface integration: 42 branches | 26 Nov 2025 | 02 Jul 2026 | Branch Operations | 40% | In progress | |
| ATM network integration: 180 ATMs | 26 Nov 2025 | 02 Jul 2026 | IT Operations | 15% | In progress | |
| API gateway and security policies | 26 Nov 2025 | 23 Jan 2026 | V. Chakraborty | 100% | Done | |
| Event streaming and messaging backbone | 26 Nov 2025 | 23 Feb 2026 | V. Chakraborty | 100% | Done | |
| Integration monitoring and alerting | 27 Jan 2026 | 23 Mar 2026 | DevOps Lead | 100% | Done | |
| Open banking data sharing APIs | 27 Jan 2026 | 03 Jun 2026 | Digital Team | 45% | In progress | |
| Integration test harness and service mocks | 26 Nov 2025 | 09 Feb 2026 | V. Chakraborty | 100% | Done | |
| Integrate Risk and credit decisioning | 26 Nov 2025 | 20 May 2026 | Risk Systems Lead | 85% | In progress | |
| Integrate Anti-money laundering and transaction monitoring | 26 Nov 2025 | 20 May 2026 | Compliance Systems Lead | 80% | In progress | |
| Integrate Fraud detection platform | 26 Nov 2025 | 20 May 2026 | Fraud Systems Lead | 75% | In progress | |
| Integrate Customer relationship management | 26 Nov 2025 | 20 May 2026 | CRM Lead | 70% | In progress | |
| Integrate Data warehouse and management reporting | 26 Nov 2025 | 20 May 2026 | Data Platform Lead | 65% | In progress | |
| Integrate Document management and statements | 26 Nov 2025 | 20 May 2026 | Digital Team | 60% | In progress | |
| Integrate Contact centre and telephony | 26 Nov 2025 | 20 May 2026 | IT Operations | 55% | In progress | |
| Integrate Treasury and markets | 26 Nov 2025 | 20 May 2026 | Treasury Systems Lead | 50% | In progress | |
| Integrate third parties: payments and clearing partners | 01 Sep 2025 | 17 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: credit bureaus and identity services | 01 Sep 2025 | 17 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: card scheme and processors | 01 Sep 2025 | 17 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: merchant and acquiring partners | 12 Jan 2026 | 18 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: government and tax agencies | 12 Jan 2026 | 18 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: insurance and wealth partners | 12 Jan 2026 | 18 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: broker and aggregator channels | 30 Mar 2026 | 17 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: open banking data recipients | 30 Mar 2026 | 17 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: fintech and API partners | 30 Mar 2026 | 17 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integrate third parties: regional and other partners | 30 Mar 2026 | 17 Dec 2026 | Not assigned | 8% | Understaffed | |
| Integration build quality gate | 21 Dec 2026 | 23 Dec 2026 | V. Chakraborty | 0% | Not started | |
| Milestone: Phase 2 complete | 23 Dec 2026 | 23 Dec 2026 | V. Chakraborty | — | Not started |
Regulatory and Compliance21 activities · lead: M. Andersen
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Regulatory obligations mapping (CPS 234 and CPS 230) | 11 Feb 2025 | 03 Mar 2025 | K. Barrett | 100% | Done | |
| APRA regulatory reporting feeds | 01 Jun 2026 | 24 Sep 2026 | Not assigned | 0% | Not started | |
| APRA initial project notification | 15 Jan 2025 | 22 Jan 2025 | M. Andersen | 100% | Done | |
| CPS 234 compliance assessment | 01 Apr 2025 | 27 Jun 2025 | K. Barrett | 100% | Done | |
| Proactive APRA delay briefing | 28 Apr 2026 | 30 Apr 2026 | M. Andersen | 0% | Not started | |
| Prepare CPS 234 pre-cutover notification | 01 Jul 2026 | 01 Sep 2026 | M. Andersen | 0% | Not started | |
| Milestone: CPS 234 pre-cutover notification lodged | 01 Sep 2026 | 01 Sep 2026 | M. Andersen | — | Not started | |
| Privacy impact assessment | 01 Sep 2025 | 26 Sep 2025 | K. Barrett | 100% | Done | |
| CPS 230 operational resilience alignment | 02 Feb 2026 | 28 Apr 2026 | K. Barrett | 60% | In progress | |
| Board risk committee briefing on delay and recovery plan | 01 May 2026 | 07 May 2026 | M. Andersen | 0% | Not started | |
| External audit of CPS 234 controls | 02 Sep 2026 | 14 Oct 2026 | M. Andersen | 0% | Not started | |
| APRA regulatory reporting parallel run | 14 Apr 2027 | 30 Jun 2027 | Compliance Systems Lead | 0% | Not started | |
| Quarterly APRA progress report: Q2 2025 | 01 Jul 2025 | 21 Jul 2025 | M. Andersen | 100% | Done | |
| Quarterly APRA progress report: Q3 2025 | 01 Oct 2025 | 22 Oct 2025 | M. Andersen | 100% | Done | |
| Quarterly APRA progress report: Q4 2025 | 05 Jan 2026 | 23 Jan 2026 | M. Andersen | 100% | Done | |
| Quarterly APRA progress report: Q1 2026 | 01 Apr 2026 | 23 Apr 2026 | M. Andersen | 100% | Done | |
| Quarterly APRA progress report: Q2 2026 | 01 Jul 2026 | 21 Jul 2026 | M. Andersen | 0% | Not started | |
| Quarterly APRA progress report: Q3 2026 | 01 Oct 2026 | 22 Oct 2026 | M. Andersen | 0% | Not started | |
| Quarterly APRA progress report: Q4 2026 | 04 Jan 2027 | 22 Jan 2027 | M. Andersen | 0% | Not started | |
| Quarterly APRA progress report: Q1 2027 | 01 Apr 2027 | 21 Apr 2027 | M. Andersen | 0% | Not started | |
| Post go-live APRA report | 09 Jul 2027 | 29 Jul 2027 | M. Andersen | 0% | Not started |
Data Migration19 activities · lead: A. Osei
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Data landscape assessment | 20 Jan 2025 | 17 Feb 2025 | A. Osei | 100% | Done | |
| Data catalogue and schema mapping: legacy to T24 | 01 Jul 2025 | 25 Sep 2025 | A. Osei | 100% | Done | |
| Data quality audit: 2.1M customer records | 26 Sep 2025 | 07 Jan 2026 | Temenos | 100% | Done | |
| Classify anomalies by category and impact | 08 Jan 2026 | 19 Feb 2026 | A. Osei | 100% | Done | |
| Agree dormant account strategy with legal | 20 Feb 2026 | 02 Apr 2026 | K. Barrett | 100% | Done | |
| Anomaly remediation plan | 20 Feb 2026 | 11 May 2026 | A. Osei | 60% | In progress | |
| Duplicate account remediation: 180K accounts | 20 Feb 2026 | 08 Sep 2026 | A. Osei | 20% | Delayed | |
| Outdated beneficiary data remediation: 65K records | 20 Feb 2026 | 30 Jun 2026 | A. Osei | 25% | In progress | |
| Dormant account remediation: 95K accounts | 27 Apr 2026 | 20 Jul 2026 | A. Osei | 0% | Not started | |
| Migration tooling and ETL build | 26 Sep 2025 | 04 May 2026 | Temenos | 70% | In progress | |
| Reconciliation framework and controls | 05 May 2026 | 28 Jul 2026 | A. Osei | 0% | Not started | |
| Data privacy and consent review for migration | 20 Feb 2026 | 19 Mar 2026 | K. Barrett | 100% | Done | |
| Customer outreach for linked duplicate accounts | 12 May 2026 | 07 Jul 2026 | Branch Operations | 0% | Not started | |
| Data archiving and retention strategy | 07 Apr 2026 | 11 May 2026 | A. Osei | 56% | In progress | |
| Migration cutover runbook | 05 May 2026 | 16 Jun 2026 | A. Osei | 0% | Not started | |
| Migration dry run 1: full data set | 09 Sep 2026 | 22 Sep 2026 | A. Osei | 0% | Not started | |
| Migration dry run 2: full data set and reconciliation | 23 Sep 2026 | 07 Oct 2026 | A. Osei | 0% | Not started | |
| Migration dress rehearsal: simulated cutover | 02 Nov 2026 | 06 Nov 2026 | A. Osei | 0% | Not started | |
| Post-migration reconciliation and sign-off | 10 Aug 2027 | 06 Sep 2027 | A. Osei | 0% | Not started |
Infrastructure and Security16 activities · lead: Infrastructure Lead
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Infrastructure and security baseline assessment | 20 Jan 2025 | 10 Feb 2025 | Security Architect | 100% | Done | |
| Define architecture principles and capability map | 11 Feb 2025 | 26 Feb 2025 | T. Rao | 100% | Done | |
| Target architecture design: Temenos T24 on Azure | 27 Feb 2025 | 05 May 2025 | Deloitte Digital | 100% | Done | |
| Security and resilience review of target architecture | 06 May 2025 | 21 May 2025 | Security Architect | 100% | Done | |
| Architecture board approval | 22 May 2025 | 26 May 2025 | T. Rao | 100% | Done | |
| Milestone: Target architecture approved | 26 May 2025 | 26 May 2025 | T. Rao | — | Done | |
| Provision Azure landing zone | 01 Jul 2025 | 28 Jul 2025 | Infrastructure Lead | 100% | Done | |
| Provision development and build environments | 29 Jul 2025 | 18 Aug 2025 | Infrastructure Lead | 100% | Done | |
| Configure continuous integration and delivery pipeline | 19 Aug 2025 | 15 Sep 2025 | DevOps Lead | 100% | Done | |
| Network connectivity to branches, ATMs and data centres | 29 Jul 2025 | 22 Sep 2025 | Network Lead | 100% | Done | |
| Identity, access and privileged access controls | 19 Aug 2025 | 29 Sep 2025 | Security Architect | 100% | Done | |
| Observability and monitoring platform | 27 Apr 2026 | 29 May 2026 | DevOps Lead | 0% | Not started | |
| Cloud cost and capacity model | 29 Jul 2025 | 18 Aug 2025 | Infrastructure Lead | 100% | Done | |
| Azure resilience and failover design validation | 23 Sep 2025 | 21 Oct 2025 | Infrastructure Lead | 100% | Done | |
| Security controls testing and CPS 234 evidence pack | 30 Sep 2025 | 25 Nov 2025 | Security Architect | 100% | Done | |
| Disaster recovery environment build | 28 Jul 2026 | 21 Sep 2026 | Infrastructure Lead | 0% | Not started |
Core Platform15 activities · lead: Deloitte Digital
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Install Temenos T24 base platform | 19 Aug 2025 | 15 Sep 2025 | Temenos | 100% | Done | |
| Configure retail banking products | 16 Sep 2025 | 11 Dec 2025 | Deloitte Digital | 100% | Done | |
| Configure business banking products | 12 Dec 2025 | 15 Jun 2026 | Deloitte Digital | 85% | In progress | |
| Configure deposits and term deposit processing | 12 Dec 2025 | 15 Jun 2026 | Deloitte Digital | 90% | In progress | |
| Configure loans and mortgages: interest calculation logic | 12 Dec 2025 | 26 Aug 2026 | Deloitte Digital | 60% | Delayed | |
| Configure cards and card scheme interfaces | 12 Dec 2025 | 06 Jul 2026 | Deloitte Digital | 55% | In progress | |
| Configure general ledger and finance posting | 12 Dec 2025 | 05 Jun 2026 | Finance Systems Lead | 70% | In progress | |
| Configure fees, charges and pricing engine | 12 Dec 2025 | 06 Jul 2026 | Deloitte Digital | 50% | In progress | |
| Configure customer onboarding and know your customer | 12 Dec 2025 | 06 Jul 2026 | Deloitte Digital | 45% | In progress | |
| Configure customer limits and risk controls | 16 Jun 2026 | 10 Aug 2026 | Deloitte Digital | 0% | Not started | |
| Configure reporting and statements in T24 | 09 Jun 2026 | 03 Aug 2026 | Deloitte Digital | 0% | Not started | |
| Configure collateral and security management | 27 Aug 2026 | 22 Oct 2026 | Deloitte Digital | 0% | Not started | |
| Configure interest and fee accrual engine | 16 Jun 2026 | 17 Aug 2026 | Deloitte Digital | 0% | Not started | |
| Configure batch and end-of-day processing | 12 Dec 2025 | 05 Jun 2026 | Deloitte Digital | 80% | In progress | |
| Core platform configuration review | 23 Oct 2026 | 05 Nov 2026 | Temenos Configuration Lead | 0% | Not started |
Testing25 activities · lead: L. Ferreira
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Test strategy and plan | 02 Mar 2026 | 26 May 2026 | L. Ferreira | 40% | In progress | |
| Provision SIT and performance environments | 13 Apr 2026 | 27 Jul 2026 | IT Operations | 5% | In progress | |
| Test case design: SIT and UAT scripts | 02 Feb 2026 | 12 May 2026 | L. Ferreira | 35% | In progress | |
| Test data preparation | 13 May 2026 | 08 Jul 2026 | L. Ferreira | 0% | Not started | |
| Test governance and defect triage set-up | 02 Mar 2026 | 13 Mar 2026 | L. Ferreira | 100% | Done | |
| Regression test suite automation | 13 May 2026 | 08 Jul 2026 | L. Ferreira | 0% | Not started | |
| SIT cycle 1: core platform and channels | 24 Dec 2026 | 15 Jan 2027 | L. Ferreira | 0% | Not started | |
| SIT cycle 2: payments and internal systems | 18 Jan 2027 | 05 Feb 2027 | L. Ferreira | 0% | Not started | |
| SIT cycle 3: third parties and regulatory reporting | 08 Feb 2027 | 25 Feb 2027 | L. Ferreira | 0% | Not started | |
| Performance and volume testing | 18 Jan 2027 | 03 Feb 2027 | L. Ferreira | 0% | Not started | |
| Disaster recovery failover test | 04 Feb 2027 | 11 Feb 2027 | IT Operations | 0% | Not started | |
| Security penetration test | 18 Jan 2027 | 08 Feb 2027 | Security Architect | 0% | Not started | |
| Branch and ATM end-to-end testing | 08 Feb 2027 | 23 Feb 2027 | Branch Operations | 0% | Not started | |
| Operational readiness testing | 04 Feb 2027 | 19 Feb 2027 | IT Operations | 0% | Not started | |
| Business continuity test | 12 Feb 2027 | 18 Feb 2027 | IT Operations | 0% | Not started | |
| Milestone: SIT exit approved | 25 Feb 2027 | 25 Feb 2027 | L. Ferreira | — | Not started | |
| UAT preparation and business user training | 08 Feb 2027 | 26 Feb 2027 | Business Teams | 0% | Not started | |
| UAT cycle 1: retail banking | 01 Mar 2027 | 19 Mar 2027 | Business Teams | 0% | Not started | |
| UAT cycle 2: business banking and payments | 22 Mar 2027 | 13 Apr 2027 | Business Teams | 0% | Not started | |
| Milestone: UAT exit approved | 13 Apr 2027 | 13 Apr 2027 | L. Ferreira | — | Not started | |
| Parallel run: old and new systems running together | 14 Apr 2027 | 30 Jun 2027 | All teams | 0% | Not started | |
| Parallel run: daily reconciliation reporting | 14 Apr 2027 | 30 Jun 2027 | A. Osei | 0% | Not started | |
| Parallel run exit review and reconciliation sign-off | 01 Jul 2027 | 02 Jul 2027 | S. Okafor | 0% | Not started | |
| Milestone: Parallel run exit approved | 02 Jul 2027 | 02 Jul 2027 | S. Okafor | — | Not started | |
| Post go-live defect triage | 09 Jul 2027 | 09 Aug 2027 | L. Ferreira | 0% | Not started |
Change and Communications7 activities · lead: K. Barrett
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Customer communications plan: 2.1M customers | 04 May 2026 | 29 Jun 2026 | K. Barrett | 0% | Not started | |
| ASIC engagement on customer notices | 30 Jun 2026 | 13 Jul 2026 | K. Barrett | 0% | Not started | |
| Legal review, ASIC alignment and executive approval | 30 Jun 2026 | 27 Jul 2026 | K. Barrett | 0% | Not started | |
| Issue customer notifications about the migration | 01 Oct 2026 | 05 Nov 2026 | Communications Team | 0% | Not started | |
| Branch and contact centre staff briefings | 02 Nov 2026 | 27 Nov 2026 | Branch Operations | 0% | Not started | |
| Customer dispute and complaints handling readiness | 02 Nov 2026 | 11 Dec 2026 | Customer Care Lead | 0% | Not started | |
| Customer complaint monitoring | 09 Jul 2027 | 02 Sep 2027 | Customer Care Lead | 0% | Not started |
Cutover and Hypercare15 activities · lead: S. Okafor
| Task | Start | Finish | Owner | % | Status | |
|---|---|---|---|---|---|---|
| Cutover planning and weekend war room set-up | 14 Apr 2027 | 25 May 2027 | S. Okafor | 0% | Not started | |
| Cutover rollback rehearsal | 26 May 2027 | 01 Jun 2027 | S. Okafor | 0% | Not started | |
| Hypercare war room roster and shifts | 26 May 2027 | 08 Jun 2027 | S. Okafor | 0% | Not started | |
| Vendor on-call agreements: Temenos and Deloitte | 26 May 2027 | 08 Jun 2027 | Procurement Lead | 0% | Not started | |
| Cutover customer messaging: day-of communications | 02 Jun 2027 | 08 Jun 2027 | Communications Team | 0% | Not started | |
| Branch cutover readiness check: 42 branches | 02 Jun 2027 | 08 Jun 2027 | Branch Operations | 0% | Not started | |
| Go and no-go decision | 05 Jul 2027 | 06 Jul 2027 | S. Okafor | 0% | Not started | |
| Cutover weekend: production migration and switch | 07 Jul 2027 | 08 Jul 2027 | All teams | 0% | Not started | |
| Milestone: GO-LIVE: Core Banking Migration | 08 Jul 2027 | 08 Jul 2027 | All teams | — | Not started | |
| Hypercare: intensive support | 09 Jul 2027 | 09 Aug 2027 | All teams | 0% | Not started | |
| Hypercare: standard support and defect burn-down | 10 Aug 2027 | 13 Sep 2027 | All teams | 0% | Not started | |
| Maintain rollback capability | 09 Jul 2027 | 23 Sep 2027 | S. Okafor | 0% | Not started | |
| Knowledge transfer to operations | 10 Aug 2027 | 20 Sep 2027 | V. Chakraborty | 0% | Not started | |
| Decommission legacy platform | 24 Sep 2027 | 06 Oct 2027 | IT Operations | 0% | Not started | |
| Milestone: Hypercare complete | 13 Oct 2027 | 13 Oct 2027 | S. Okafor | — | Not started |
Critical pathFrom the schedule export
The critical path in the export runs from the third-party integrations through the integration build quality gate, SIT, UAT, the three month parallel run, the go and no-go decision and the cutover weekend to Go-live, then hypercare, with -80 working days of float at each stage. The negative float is the gap between the dated finish (13 Oct 2027) and the baseline finish (22 Jun 2027) of the last milestone. APRA regulatory reporting feeds (CBM.2.4.17) have no developer and float of -20 days, so they are close behind. No task is dated before the work it depends on, so there is no dependency-corrected scenario.
Sequence: 18 stages, read left to right and top to bottom. Critical activities are counted separately, as the longest path covers more tasks than the stages shown.
Critical path sequence
Critical task detail
| WBS | Task | Duration | Planned finish | Forecast | Owner | |
|---|---|---|---|---|---|---|
| CBM.2.4.8 | Payments: SWIFT and correspondent banking Alert | 198d | 30 Jul 2026 | 08 Sep 2026 | -8d | V. Chakraborty |
| CBM.2.4.9 | Payments: Direct Debit Alert | 198d | 30 Jul 2026 | 08 Sep 2026 | -8d | V. Chakraborty |
| CBM.2.4.17 | APRA regulatory reporting feeds Alert | 83d | 17 Aug 2026 | 24 Sep 2026 | -20d | Not assigned |
| CBM.2.6.1 | Integrate third parties: payments and clearing partners Alert | 330d | 26 Aug 2026 | 17 Dec 2026 | -79d | Not assigned |
| CBM.2.6.2 | Integrate third parties: credit bureaus and identity services Alert | 330d | 26 Aug 2026 | 17 Dec 2026 | -79d | Not assigned |
| CBM.2.6.3 | Integrate third parties: card scheme and processors Alert | 330d | 26 Aug 2026 | 17 Dec 2026 | -79d | Not assigned |
| CBM.2.6.4 | Integrate third parties: merchant and acquiring partners Alert | 240d | 27 Aug 2026 | 18 Dec 2026 | -80d | Not assigned |
| CBM.2.6.5 | Integrate third parties: government and tax agencies Alert | 240d | 27 Aug 2026 | 18 Dec 2026 | -80d | Not assigned |
| CBM.2.6.6 | Integrate third parties: insurance and wealth partners Alert | 240d | 27 Aug 2026 | 18 Dec 2026 | -80d | Not assigned |
| CBM.2.6.7 | Integrate third parties: broker and aggregator channels Alert | 185d | 26 Aug 2026 | 17 Dec 2026 | -79d | Not assigned |
| CBM.2.6.8 | Integrate third parties: open banking data recipients Alert | 185d | 26 Aug 2026 | 17 Dec 2026 | -79d | Not assigned |
| CBM.2.6.9 | Integrate third parties: fintech and API partners Alert | 185d | 26 Aug 2026 | 17 Dec 2026 | -79d | Not assigned |
| CBM.2.6.10 | Integrate third parties: regional and other partners Alert | 185d | 26 Aug 2026 | 17 Dec 2026 | -79d | Not assigned |
| CBM.2.6.11 | Integration build quality gate Alert | 3d | 01 Sep 2026 | 23 Dec 2026 | -80d | V. Chakraborty |
| CBM.4.2.1 | SIT cycle 1: core platform and channels Alert | 14d | 21 Sep 2026 | 15 Jan 2027 | -80d | L. Ferreira |
| CBM.4.2.2 | SIT cycle 2: payments and internal systems | 14d | 12 Oct 2026 | 05 Feb 2027 | -80d | L. Ferreira |
| CBM.4.2.3 | SIT cycle 3: third parties and regulatory reporting | 14d | 30 Oct 2026 | 25 Feb 2027 | -79d | L. Ferreira |
| CBM.4.2.4 | Performance and volume testing | 12d | 08 Oct 2026 | 03 Feb 2027 | -75d | L. Ferreira |
| CBM.4.2.5 | Disaster recovery failover test | 6d | 16 Oct 2026 | 11 Feb 2027 | -74d | IT Operations |
| CBM.4.2.6 | Security penetration test | 15d | 13 Oct 2026 | 08 Feb 2027 | -66d | Security Architect |
| CBM.4.2.7 | Branch and ATM end-to-end testing | 12d | 28 Oct 2026 | 23 Feb 2027 | -77d | Branch Operations |
| CBM.4.2.8 | Operational readiness testing | 12d | 26 Oct 2026 | 19 Feb 2027 | -75d | IT Operations |
| CBM.4.2.9 | Business continuity test | 5d | 23 Oct 2026 | 18 Feb 2027 | -74d | IT Operations |
| CBM.4.2.10 | ◆ SIT exit approved | — | 30 Oct 2026 | 25 Feb 2027 | -79d | L. Ferreira |
| CBM.4.3.1 | UAT preparation and business user training | 15d | 02 Nov 2026 | 26 Feb 2027 | -80d | Business Teams |
| CBM.4.3.2 | UAT cycle 1: retail banking | 15d | 23 Nov 2026 | 19 Mar 2027 | -80d | Business Teams |
| CBM.4.3.3 | UAT cycle 2: business banking and payments | 15d | 14 Dec 2026 | 13 Apr 2027 | -80d | Business Teams |
| CBM.4.3.4 | ◆ UAT exit approved | — | 14 Dec 2026 | 13 Apr 2027 | -80d | L. Ferreira |
| CBM.4.4.1 | Parallel run: old and new systems running together Alert | 55d | 05 Mar 2027 | 30 Jun 2027 | -80d | All teams |
| CBM.4.4.2 | Parallel run: daily reconciliation reporting | 55d | 05 Mar 2027 | 30 Jun 2027 | -80d | A. Osei |
| CBM.4.4.3 | Parallel run exit review and reconciliation sign-off | 2d | 09 Mar 2027 | 02 Jul 2027 | -80d | S. Okafor |
| CBM.4.4.4 | ◆ Parallel run exit approved | — | 09 Mar 2027 | 02 Jul 2027 | -80d | S. Okafor |
| CBM.5.1.10 | APRA regulatory reporting parallel run | 55d | 05 Mar 2027 | 30 Jun 2027 | -78d | Compliance Systems Lead |
| CBM.6.1.1 | Cutover planning and weekend war room set-up | 30d | 15 Feb 2027 | 25 May 2027 | -63d | S. Okafor |
| CBM.6.1.2 | Cutover rollback rehearsal | 5d | 22 Feb 2027 | 01 Jun 2027 | -63d | S. Okafor |
| CBM.6.1.3 | Hypercare war room roster and shifts | 10d | 01 Mar 2027 | 08 Jun 2027 | -63d | S. Okafor |
| CBM.6.1.4 | Vendor on-call agreements: Temenos and Deloitte | 10d | 01 Mar 2027 | 08 Jun 2027 | -63d | Procurement Lead |
| CBM.6.1.5 | Cutover customer messaging: day-of communications | 5d | 01 Mar 2027 | 08 Jun 2027 | -63d | Communications Team |
| CBM.6.1.6 | Branch cutover readiness check: 42 branches | 5d | 01 Mar 2027 | 08 Jun 2027 | -63d | Branch Operations |
| CBM.6.1.7 | Go and no-go decision | 2d | 11 Mar 2027 | 06 Jul 2027 | -80d | S. Okafor |
| CBM.6.2.1 | Cutover weekend: production migration and switch | 2d | 15 Mar 2027 | 08 Jul 2027 | -80d | All teams |
| CBM.6.2.2 | ◆ GO-LIVE: Core Banking Migration | — | 15 Mar 2027 | 08 Jul 2027 | -80d | All teams |
| CBM.6.3.1 | Hypercare: intensive support | 22d | 16 Apr 2027 | 09 Aug 2027 | -77d | All teams |
| CBM.6.3.2 | Hypercare: standard support and defect burn-down | 25d | 21 May 2027 | 13 Sep 2027 | -72d | All teams |
| CBM.6.3.3 | Maintain rollback capability | 55d | 02 Jun 2027 | 23 Sep 2027 | -80d | S. Okafor |
| CBM.6.3.4 | Post-migration reconciliation and sign-off | 20d | 14 May 2027 | 06 Sep 2027 | -67d | A. Osei |
| CBM.6.3.5 | Post go-live defect triage | 22d | 16 Apr 2027 | 09 Aug 2027 | -47d | L. Ferreira |
| CBM.6.3.6 | Customer complaint monitoring | 40d | 12 May 2027 | 02 Sep 2027 | -65d | Customer Care Lead |
| CBM.6.3.7 | Knowledge transfer to operations | 30d | 28 May 2027 | 20 Sep 2027 | -77d | V. Chakraborty |
| CBM.6.3.8 | Post go-live APRA report | 15d | 07 Apr 2027 | 29 Jul 2027 | -32d | M. Andersen |
| CBM.6.3.9 | Decommission legacy platform | 8d | 15 Jun 2027 | 06 Oct 2027 | -80d | IT Operations |
| CBM.6.3.10 | Post-implementation review | 5d | 22 Jun 2027 | 13 Oct 2027 | -80d | S. Okafor |
| CBM.6.3.11 | ◆ Hypercare complete | — | 22 Jun 2027 | 13 Oct 2027 | -80d | S. Okafor |
All 53 critical activities are shown. This table is not curated or capped.
Float distribution
How this was calculatedAssumptions and limits
- Source. Every date, percentage, float and comment comes from the schedule export at the 27 Apr 2026 status date. Cherry adds only labelled calculations and recommendations. Figures such as 129 unassigned integrations and $4M to $6M are quoted from source comments and are not checked against a resource plan or budget.
- Links. The export lists predecessors by row ID and treats every link as finish-to-start. It has no lag, constraint or link-type column, so none is assumed. A task starts the next working day after its predecessor finishes; a milestone may share its predecessor's date. Cherry found no task dated before the work it depends on.
- Calendar. Working days are Monday to Friday excluding an illustrative NSW public-holiday list. The export names the list but does not contain it, so Cherry cannot verify it.
- Float. The export's Total Float is working days to the approved completion date (the baseline finish of Hypercare complete, 22 Jun 2027). Cherry recomputed it independently for the 119 incomplete activities that carry a float value, with no mismatch. Negative float means the activity is forecast to finish after that date.
- Progress. Overall 41% is duration-weighted across activities (a milestone counts as one day). Planned 58% applies the same weights to baseline dates at the status date. Phase and workstream percentages use the same method.
- Health rating. Critical, because the dated end of the project moves 80 working days against the baseline, which is 22 percent of the 372 working days remaining, above the 15 percent threshold. Cherry's rating is calculated from the schedule and is independent of any rating entered by the project team.
- Near-critical. A fixed 1 to 10 working days. At this project's remaining duration a proportional threshold of 5 percent would be about 19 days, so the count is sensitive to the rule.
- Workstream status. At risk = any incomplete task with negative float. Watch = no negative float but a task marked Delayed or Understaffed. Otherwise Complete, Not started or On plan.
- Not assessed. Cost, resource capacity, hard constraints, link types and lag. The CPS 234 notification date is treated as a normal milestone; the export holds no constraint for it, and Cherry has not assessed APRA requirements.
Nexus Bank is a fictional organisation and project, built to show how Cherry reads a project schedule export. It does not describe a real bank, and no real project team has used or endorsed Cherry for it.